BLD-Final | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PASS |
Tom Arcoraci
|
|
|
Jeff ###-#### L.C. Issued
|
INSP - Energy code compliance | 5/11/1999 | 5/11/1999 | 5/11/1999 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Framing/Rough-in | 5/7/1999 | 5/10/1999 | 5/10/1999 | A | PASS |
Jim Sly
|
|
|
05/10/99 316 -
|
INSP - Framing/Rough-in | 5/5/1999 | 5/6/1999 | 5/6/1999 | P | FAIL |
Jim Sly
|
|
|
05/06/99 316 - C/N......Verify thermo break and add bearing 2ply gird
|
INSP - Framing/Rough-in | 4/22/1999 | 4/23/1999 | 4/23/1999 | A | PART |
Jim Sly
|
|
|
04/23/99 316 - Shear wall only...OK
|
Issue PAID IN FULL permit | | | 4/7/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/29/1999 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 3/18/1999 | | 3/29/1999 | | PASS |
Dan Overy
|
|
|
03/29/99 09:07:45 DJO - this action updated by action script from <<>> in Case No. BLD99-0728
|
Plans ACCEPTED BY PLAN CHECK | | | 3/29/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/29/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/1999 | | PASS |
|
|
|
|
Telephone call | | | 3/29/1999 | | |
|
|
|
talked to rob truax gave dollar amounts
|
Plan Reviewer's activity | | | 3/29/1999 | | PASS |
|
|
|
HAVE MARKED UP THIS SET. TALKED TO DESIGNER (BOYER) ABOUT INFORMATION THAT WILL BE REQUIRED WITH FUTURE SUBMITTALS.
|
INSP - Concrete | 3/23/1999 | 3/24/1999 | 3/24/1999 | P | PART |
Jim Sly
|
|
|
03/24/99 316 - Wall and rebar OK....Setbks?.....No appr plans on site.
|
INSP - Foundation | 3/23/1999 | 3/23/1999 | 3/23/1999 | P | PART |
Jim Sly
|
|
|
03/23/99 316 - Foot and bar OK....setbks?....No appr plans on site.
|
Routing - PUBLIC WORKS | 3/18/1999 | | 3/19/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/18/1999 | | |
|
|
|
|
Application received | | | 3/18/1999 | | |
|
|
|
|
Routing - PLANNING | 3/18/1999 | | 3/18/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/19/1999 | | | | PEND |
|
|
|
|