Fee Review-notes | 3/19/1999 | | 3/15/2000 | | DONE |
|
|
|
4/27/99-update-added 3000.00 on this permit or there would have been a refund. lh THIS PERMIT WAS SUBMITTED WITH 4 ADDITIONAL BUILDINGS. THE TOTAL PROJECT VALUE FOR ALL FIVE BUILDINGS WAS $80,000 ELECT. $28,000 PLUMB. $13,000 MECH. FIRE SPRINKLER N/A. DON HUTCHISON CAME IN AND DIVIDED VALUES BY 5. THUS TOTAL PROJECT VALUE FOR EACH IS $16,000 ELEC. $5,600 PLUMB. $2,600 THERE WILL BE 5 SEPARATE PERMITS ISSUED, ONE FOR EACH RELOCATABLE. KMM
|
Permanent occupancy | | | 12/9/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8048 issued 12-9-99 to Cole Community Church.
|
Permanent Occupancy | | 12/7/1999 | 12/7/1999 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/1/1999 | 12/3/1999 | 12/3/1999 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/01/1999 at 13:55:26. Contact: ###-####. Reinsp. Ok for permanent occupancy.
|
Temporary occupancy | | | 9/10/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3912 issued 9-10-99 to Cole Community Church for a modular classroom bldg.
|
INSP - Final | 9/8/1999 | 9/8/1999 | 9/8/1999 | | FAIL |
Tom Arcoraci
|
|
|
STAN COLE--###-#### FN; 9/8 C/N issued. jrb
|
INSP-Final Inspection | 9/8/1999 | 9/8/1999 | 9/8/1999 | | PART |
Rick Jackson
|
|
|
STAN ###-#### FN FIRE; 9/8 OK for temporary occupancy. jrb
|
INSP-Final Inspection | 9/3/1999 | 9/3/1999 | 9/3/1999 | P | PART |
Rick Jackson
|
|
|
UFC issues okay - temp occ approved
|
INSP - Foundation | 9/3/1999 | 9/3/1999 | 9/3/1999 | P | PASS |
Tom Arcoraci
|
|
|
09/03/99 408 - steve evans ###-#### foundation
|
Receive PAYMENT IN FULL PRINT | | | 9/3/1999 | | |
|
|
|
|
Telephone call | | | 9/2/1999 | | |
|
|
|
LEFT MESSAGE FOR STAN COLE GAVE DOLLAR AMOUNT
|
INSP - Final | 9/1/1999 | 9/1/1999 | 9/1/1999 | | FAIL |
|
|
|
5 day N&O issued.
|
SUPER- Supervisor's review | 9/2/1999 | 9/1/1999 | 9/1/1999 | | FAIL |
|
|
|
N&O
|
Routing - PLANNING | 8/30/1999 | | 9/1/1999 | | PASS |
|
|
|
|
Plan assigned to (MLO) | 8/18/1999 | | 9/1/1999 | | PASS |
Mike Otto
|
|
|
PLAN MODIFICATION 09-01-99 MODIFICATION TAKEN TO FRONT DESK. MLO
|
Routing - PLAN CHECK | 8/27/1999 | | 8/30/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/27/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BRUCE POE OF STAN COLE ASSOCIATES ARCHITECTS, FORWARDED SAME TO MIKE OTTO. 8/27/99 DAR
|
Plan resubmittals requested | | | 8/24/1999 | | FAIL |
|
|
|
CORRECTIONS FAXED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 8/18/1999 | | 8/23/1999 | | FAIL |
|
|
|
PLAN MODIFICATION. KMM
|
Plan resubmittals received | | | 8/20/1999 | | |
|
|
|
PLAN MODIFICATION - RECEIVED FIVE COPIES OF REVISED CIVIL SHEETS C1.3 ROUTED TO MIKE O. KMM
|
Plan Modification Accepted | 8/18/1999 | | 8/18/1999 | | |
|
|
|
|
INSP - Concrete | 7/29/1999 | 7/30/1999 | 7/30/1999 | A | FAIL |
Tom Arcoraci
|
|
|
07/30/99 408 - conf on ramps and stairs
|
Issue PAID IN FULL permit | | | 5/4/1999 | | |
|
|
|
|
Print Occupancy Form | | | 4/27/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/27/1999 | | |
|
|
|
|
Plan assigned to (MLO) | 3/22/1999 | | 4/27/1999 | | PASS |
Mike Otto
|
|
|
04/27/99 08:15:50 MLO - this action updated by action script from <<>> in Case No. BLD99-0736
|
Routing - PUBLIC WORKS | 4/21/1999 | | 4/26/1999 | | PASS |
|
|
|
site plan changed
|
Routing - FIRE | 4/21/1999 | | 4/21/1999 | | PASS |
|
|
|
plans for site revised
|
Routing - PLUMBING | 4/20/1999 | | 4/20/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/8/1999 | | FAIL |
|
|
|
plan coordination
|
Routing - FIRE | 4/5/1999 | | 4/8/1999 | | FAIL |
|
|
|
revised drainage plan does not match the arch plans
|
Routing - PUBLIC WORKS | 3/31/1999 | | 4/5/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 3/29/1999 | | 3/31/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | 3/31/1999 | | 3/31/1999 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/31/1999 | | 3/31/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/22/1999 | | 3/24/1999 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy. DAR 3/29/99
|
Plan routing begun/NEW & ADDTN | 3/22/1999 | | 3/22/1999 | | |
|
|
|
|
Plan assigned to (MYS) | 3/18/1999 | | 3/22/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/19/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 3/19/1999 | | PASS |
|
|
|
|
Application received | | | 3/18/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/18/1999 | | |
|
|
|
|
INSP-Final Inspection | 8/26/1999 | 8/30/1999 | 3/9/1990 | A | PART |
Joe Tawney
|
|
|
09/01/99 406 - ALARM TEST OK EXC SOUND LEVELS IN RESTROOMS & BKR LOCKS
|
Code Occupancy Approval | | | | | FAIL |
|
|
|
Bonded for conditions - landscaping per C.U. ($16,500.) Signed Temporary
|