Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-00757
StatusFinaled
Name STEVE HARRELL
Site Address 8775 W USTICK RD
Project NameSCHOOL (RELOCATABLE)
Customer Number 
ePlanReviewNo
Description
COLE COMMUNITY CHURCH * TO ADD A 28' X 70' NEW RELOCATABLE CLASSROOM AT COLE COMMUNITY CHURCH. ADD FOUNDATION PIERS, TIE DOWNS, DECK WITH STAIRS AND RAMP, SKIRTING, SIDEWALKS, LANDSCAPING AND ELECTRICAL. ALL PER APPROVED PLANS. CUP98-0117 PC#203-99 ID. TAG NUMBER 7286CC
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  12/9/1999 DONE
Perm. Occ. Cert. #8049 issued 12-9-99 to Cole Community Church.
Permanent Occupancy 12/7/199912/7/1999 DONE
Details
FIRE-Final Inspection12/3/199912/3/199912/3/1999APASS
DetailsJoe Tawney
Reinsp ok for permanent occupancy.
Temporary occupancy  9/10/1999 PART
Temp. Occ. Cert. #3913 issued 9-10-99 to Cole Community Church for a modular classroom bldg.
INSP - Final9/8/19999/8/19999/8/1999 FAIL
DetailsTom Arcoraci
STAN COLE ###-#### FN; 9/8 C/N ossued. jrb
INSP-Final Inspection9/8/19999/8/19999/8/1999 PART
DetailsRick Jackson
STAN COLE ###-#### FN FIRE; 9/8 OK for temporary occupancy. jrb
INSP - Foundation9/3/19999/3/19999/3/1999PPASS
DetailsTom Arcoraci
09/03/99 408 - steve- ###-#### foundation
INSP-Final Inspection9/3/19999/3/19999/3/1999PPART
DetailsRick Jackson
UFC issues okay
INSP - Final9/2/19999/1/19999/1/1999 FAIL
5 day N&O issued.
SUPER- Supervisor's review9/2/19999/1/19999/1/1999 FAIL
N&O
Routing - PLANNING8/30/1999 9/1/1999 PASS
Plan assigned to (MLO)8/18/1999 9/1/1999 PASS
DetailsMike Otto
PLAN MODIFICATION 09-01-99 MODFICATION TAKEN TO FRONT DESK. MLO
INSP-Final Inspection8/26/19998/30/19998/30/1999APART
DetailsJoe Tawney
09/01/99 406 - ALARM TEST OK EXC SOUND LEVELS IN RESTROOMS & BKR LOCKS
Routing - PLAN CHECK8/27/1999 8/30/1999 PASS
Plan resubmittals received  8/27/1999 PASS
Plan resubmittals requested  8/24/1999 FAIL
CORRECTIONS FAXED TO ARCHITECT. MLO
Routing - PLAN CHECK8/18/1999 8/23/1999 FAIL
PLAN MODIFICATION. KMM
Plan resubmittals received  8/20/1999
PLAN MODIFICATION. RECEIVED FIVE COPIES OF REVISED CIVIL SHEET C1.3. ROUTED TO MIKE O. KMM
Plan Modification Accepted  8/18/1999
Issue PAID IN FULL permit  5/4/1999
Inspection Record Card- Bld  4/27/1999
Print Occupancy Form  4/27/1999
PLANS/APPL TAKEN TO FRONT DESK  4/27/1999 PASS
Plan assigned to (MLO)3/22/1999 4/27/1999 PASS
DetailsMike Otto
Routing - PUBLIC WORKS4/21/1999 4/26/1999 PASS
site plans changed
Routing - FIRE4/21/1999 4/21/1999 PASS
site plans changed
Routing - PLUMBING4/20/1999 4/20/1999 PASS
Plan Review Completed(1st rev)  4/8/1999 FAIL
site plan coordination
Routing - FIRE4/5/1999 4/8/1999 FAIL
site plans do not match
Routing - PUBLIC WORKS3/31/1999 4/5/1999 PASS
Routing - PLAN CHECK3/31/1999 3/31/1999 PASS
Routing - PLUMBING3/31/1999 3/31/1999 FAIL
Routing - PLANNING3/29/1999 3/31/1999 PASS
Routing - PUBLIC WORKS3/22/1999 3/29/1999 FAIL
Requires drainage plan revision per Brian Murphy. DAR 3/29/99
Plan routing begun/NEW & ADDTN3/22/1999 3/22/1999
Received Certificate of Value  3/19/1999 PASS
Plans ACCEPTED BY PLAN TECH  3/19/1999 PASS
Application received  3/19/1999
Code Occupancy Approval    FAIL
Bonded for Temporary per C.U. Landscaping ($16,500).