BLD-Final | 9/27/2000 | 9/28/2000 | 9/28/2000 | A | PASS |
Russ Owen
|
|
|
Gordon Beck ###-#### please call for access at least a 1/2 hour before Re-inspect prior corrections complete,windows at stairs blocked off with osb. 9/28/2000 12:57:39 PM
|
BLD-Final | 9/27/2000 | 9/27/2000 | 9/27/2000 | P | FAIL |
Tony Young
|
|
|
Gordon, ###-#### - please call 1st so he can meet you there
c/n posted,, temp. glass, plans, address #s, trade sign offs, self closing door. 9/27/2000 2:00:39 PM
|
BLD-Conference | 3/7/2000 | 3/7/2000 | 3/7/2000 | P | PART |
Wes Worcester
|
|
|
Complaint of drainage onto adjacent driveway/property and trash blowing around. Driveway to be placed, final grading and reseeding in progress with trash being picked up. 3/8/00 10:00:55 AM
|
BLD-Energy code compliance | 1/14/2000 | 1/18/2000 | 1/18/2000 | A | PART |
Wes Worcester
|
|
|
gary ###-#### energy code insp 1hr. protection of stair wells required- same as lid assembly. 1/18/00 1:31:56 PM
|
BLD-Framing/Rough-in | 1/4/2000 | 1/5/2000 | 1/5/2000 | A | FAIL |
Russ Owen
|
|
|
###-####. C/N posted.
|
BLD-Framing/Rough-in | 11/16/1999 | 11/17/1999 | 11/17/1999 | A | PART |
Russ Owen
|
|
|
GARY ###-#### FR INSP Walk thru, framing.
|
Receive PAYMENT IN FULL | | | 7/15/1999 | | |
|
|
|
|
INSP - Foundation | 7/12/1999 | 7/12/1999 | 7/12/1999 | P | PASS |
Russ Owen
|
|
|
07/12/99 407 - walls ok, hold downs are being placed now.
|
INSP - Concrete | 7/8/1999 | 7/9/1999 | 7/9/1999 | P | NR |
Russ Owen
|
|
|
07/09/99 407 - CONCRETE WALL WES ###-#### EXT. 20245
|
INSP - Foundation | 7/8/1999 | 7/8/1999 | 7/8/1999 | A | PASS |
Russ Owen
|
|
|
footings.
|
INSP - Foundation | 7/7/1999 | 7/7/1999 | 7/7/1999 | P | NR |
Russ Owen
|
|
|
GARY ###-#### - FOOTING, REQUESTS 4PM.
|
(F) Reprint permit | | | 6/25/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 6/16/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/16/1999 | | |
|
|
|
|
CHANGE STATUS TO (F) | | | 6/16/1999 | | |
|
|
|
DID NOT ADD PLAN CK FEES
|
Plan assigned to (M_P) | 5/6/1999 | | 6/4/1999 | | PASS |
Mike Phillips
|
|
|
waiting for out side engineering review. 06/04/99 11:49:36 M_P - this action updated by action script from <<>> in Case No. BLD99-0795
|
Plan Reviewer's activity | | | 6/4/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/4/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/4/1999 | | |
|
|
|
|
Telephone call | | | 6/4/1999 | | |
|
|
|
left a message with Beck construction
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/1/1999 | | 6/3/1999 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM 6-3-99 PLANS BACK FROM AHJ WITH COVER LETTER. ROUTED TO MIKE P. KMM Plans approved.
|
Routing Off Site - STRUCTURAL | 5/18/1999 | | 5/21/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE RESUBMITTAL RECEIVED ON 5-17-99 TO OUTSIDE ENG. KMM Received out side review additional comments required to be resubmitted for further review. not all comments have been answered.
|
Plan resubmittals requested | | | 5/21/1999 | | FAIL |
|
|
|
Requesting additional structural comments to be resubmitted.
|
Plan resubmittals received | | | 5/17/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A-3, A-5, A-6, S-2, S-3, S-5 AND ONE RESPONSE LETTER. ARCH. SHEETS ARE NOT STAMPED OR SIGNED. ROUTED TO MIKE P. KMM
|
Routing Off Site - STRUCTURAL | 5/3/1999 | | 5/12/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM Additional comment required from outside engineering firm, faxed copy to architect.
|
Plan Reviewer's activity | | | 5/6/1999 | | PEND |
|
|
|
Waiting for out side structural review to be approved.
|
Print Pending Permit.LaserJet4 | | | 5/6/1999 | | PASS |
|
|
|
|
CHANGE STATUS TO (P) | | | 5/6/1999 | | PEND |
|
|
|
Waiting for out side engineering review.
|
Routing - PLAN CHECK | 3/26/1999 | | 5/6/1999 | | PEND |
|
|
|
Sent to PW for revieww of grease interceptor for parking garage aarea. plans reflect two floor drains in this area. Waiting for Walt to call and give me informaiton about interceptor.
|
Plan assigned to (M_P) | 3/25/1999 | | 5/6/1999 | | PASS |
Mike Phillips
|
|
|
05/06/99 14:54:32 M_P - this action updated by action script from <<>> in Case No. BLD99-0795
|
Plan Reviewer's activity | | | 5/3/1999 | | |
|
|
|
Need to talk to inspector to confir about fire resistive construction and sent plans out for outside engineering review of wide flange beams connections and lateral.
|
Plan resubmittals received | | | 4/29/1999 | | |
|
|
|
Received new plans for follow up review structural calculations have change.
|
Plan resubmittals requested | | | 4/5/1999 | | FAIL |
|
|
|
Requested additional informaiton to be submitted.
|
Routing - PUBLIC WORKS | 3/25/1999 | | 3/26/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 3/25/1999 | | 3/25/1999 | | PASS |
|
|
|
WAYNE GIBBS SIGNED OFF SET-BACKS
|
Application received | | | 3/24/1999 | | |
|
|
|
|