Case Summary (BLD) | | | 10/31/2011 | | DONE |
Sam Zahorka
|
|
|
|
BLD-Final | 4/13/2001 | 4/16/2001 | 4/16/2001 | A | PASS |
Jim Storey
|
|
|
###-####
|
FIRE-Final Inspection | 4/13/2001 | 4/16/2001 | 4/16/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/13/2001 at 13:49:25. Contact: ###-####.
|
Permanent Occupancy | | 4/16/2001 | 4/16/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/16/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8631 issued 4-16-01 to Travel Centers of America.
|
BLD-Final | 4/12/2001 | 4/13/2001 | 4/13/2001 | P | NR |
Russ Owen
|
|
|
Kelly ###-#### called contractor ,they do not have fire/life inspection ,told them to recall. 4/13/2001 4:19:31 PM
|
BLD-Final | 4/12/2001 | 4/13/2001 | 4/13/2001 | P | NR |
Russ Owen
|
|
|
kelly ###-#### fn
|
BLD-Concrete | 3/23/2001 | 3/26/2001 | 3/26/2001 | A | PASS |
Jim Storey
|
|
|
###-#### framing ok for cover / slab on grade ok. 3/26/2001 9:22:09 AM
|
BLD-Framing/Rough-in | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | PART |
Jim Storey
|
|
|
###-#### fram ok pendig plm sign off./ frame around beam for gyp. attchment. 3/14/2001 9:15:58 AM
|
BLD-Concrete | 2/14/2001 | 2/14/2001 | 2/14/2001 | A | PART |
Jim Storey
|
|
|
###-#### SLAB placed w special insp. 2/14/2001 2:56:36 PM
|
BLD-Foundation | 2/12/2001 | 2/13/2001 | 2/13/2001 | A | PASS |
Jim Storey
|
|
|
###-#### Kelly G. slab ok 2/13/2001 11:05:42 AM
|
BLD-Foundation | 1/29/2001 | 1/31/2001 | 1/31/2001 | A | PART |
Russ Owen
|
|
|
###-####poured at this time,s-i required insp. 1/31/2001 11:39:35 AM
|
BLD-Footing | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | PART |
Jim Storey
|
|
|
###-#### south wall line ground frozen special insp. to be on site at pm to check concrete will have resolve to freezing isue if resolved rebar ok for placement of concrete. 1/23/2001 10:01:11 AM
|
BLD-Footing | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by Inspector: 301 On 1/22/2001 9:27:45 AM refur to add insp same day. 1/23/2001 10:01:56 AM
|
BLD-Footing | 1/18/2001 | 1/22/2001 | 1/22/2001 | A | CANC |
Jim Storey
|
|
|
###-#### 1/22/2001 8:52:29 AM rescheduled for 1/23/01 1/22/2001 9:28:37 AM
|
BLD-Footing | 1/17/2001 | 1/18/2001 | 1/18/2001 | P | FAIL |
Jim Storey
|
|
|
FT DAVE- ###-#### ft soil failled at corner of wesa / south peir. archived engineered resubmital and left copy on site. 1/18/2001 3:10:34 PM
|
BLD-Footing | 1/12/2001 | 1/16/2001 | 1/16/2001 | A | NH |
Dave Hannah
|
|
|
FT DAVE ###-####
|
Permit EXTENDED | | | 7/17/2000 | | DONE |
|
|
|
as per Jeff jones granted extension until Jan 26th, 2001
|
Routing Off Site - A.C.H.D | 2/2/2000 | 2/2/2000 | 2/2/2000 | | DONE |
|
|
|
cert #00-09635 for $3,636.00-paid to achd-received by Hansen-Rice Inc po box 337 nampa id 83653
ck #118948 ###-####
(295)units date paid to achd was 2/1/00
|
(F) Reprint permit | | | 2/2/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/26/1999 | | |
|
|
|
|
Telephone Call | | | 8/26/1999 | | |
|
|
|
called permit ready need ACHD cert or receipt
|
Inspection Record Card- Bld | | | 8/26/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/1999 | | PASS |
|
|
|
|
Plan assigned to (MLO) | 3/26/1999 | | 8/26/1999 | | PASS |
Mike Otto
|
|
|
|
Routing - PLUMBING | 8/18/1999 | | 8/23/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/17/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM SCOTT FREEMAN, JOHNSON ARCHITECTS, FORWARDED SAME TO MIKE OTTO,8/17/99 DAR
|
Routing - PLUMBING | 7/27/1999 | | 7/27/1999 | | FAIL |
|
|
|
PROVIDE DRAWING OF OIL INTERCEPTOR AN RELATED PIPING TO SAN SEWER
|
Routing - PLANNING | 7/27/1999 | | 7/27/1999 | | PASS |
|
|
|
approved per DRH99-0076.
|
Routing Off Site - STRUCTURAL | 7/22/1999 | | 7/23/1999 | | PASS |
|
|
|
SENT RESUBMITTALS TO CONSULTING ENGINEER. DAR 7/23/99
|
Application received | | | 7/23/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 6/28/1999 | | 7/22/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/22/1999 | | 7/22/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/28/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED JOHNSON ARCH DWGS: A-1REV.2, A-3 REV.1, A-4 REV.2, A-5 REV.3, ELKHORN DEWGS: P-3 REV.D, MP3 REV.C. ROUTED TO MIKE O. KMM
|
Plan Review Completed(1st rev) | | | 6/4/1999 | | |
|
|
|
|
Routing - FIRE | 5/26/1999 | | 6/1/1999 | | PASS |
|
|
|
FED EXED FLOYD THE ISSUE COPY WITH CASE HISTORY. ROUTED THE OFFICE COPY TO BILL A. HE WILL HOLD OFFICE COPY UNTIL FLOYD RETURNS HIS COPY OF PLANS. KMM
|
Plan resubmittals requested | | | 5/25/1999 | | FAIL |
|
|
|
UBC AND STRUCTRUAL CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing Off Site - STRUCTURAL | 5/7/1999 | | 5/25/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Routing - PLAN CHECK | 5/17/1999 | | 5/25/1999 | | FAIL |
|
|
|
|
Routing - PLUMBING | 5/13/1999 | | 5/17/1999 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 5/13/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HANSEN, RICE INC. FORWARDED SAME TO MICHAEL OTTO. DAR 05/15/99
|
Routing - PLANNING | 5/12/1999 | | 5/13/1999 | | PEND |
|
|
|
pending 10 day Design Review appeal period (May 20, 1999 is the end of appeal period)
|
Routing - PUBLIC WORKS | 5/7/1999 | | 5/12/1999 | | FAIL |
|
|
|
NEED TO SHOW SUITABLE AND ADEQUATE OIL/SEDIMENT INCEPTOR PER WALT BAUMGARTNER. DAR 5/12/99
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/1999 | | PASS |
|
|
|
RECEIVED ALL ITEMS REQUESTED IN A006 DATED 3-29-99 ON 5-7-99, PLANS READY TO ROUTE. KMM
|
Plan routing begun/NEW & ADDTN | | | 3/29/1999 | | HOLD |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/29/1999 | | HOLD |
|
|
|
CONTACTED DAN RICHARDS OF HANSEN-RICE AT ###-#### TO LET HIM KNOW THAT 1. THE SCI SHEET STATES THE USE OF THE 94 CODE, AND THAT WE ARE UNDER THE 97. REQUIRE A LETTER STATING THE USE OF THE 97 CODE. 2. HE NEEDS TO TALK WITH MARTY OF P&Z REGUARDING A DR#. 3. STRUCTURAL CALCS. ARE REQUIRED. 4. LANDSCAPE PLANS ARE REQUIRED. 5. I NEED TO TALK WITH BRIAN M. ABOUT GRADING AND DRAINAGE REQUIRENMENTS. 6. ROUTING CANNOT BEGIN UNTIL I RECEIVE INFORMATION. KMM 3-30-99 1 A DESIGN REVIEW IS NEED PER MARTY S. 2 I NEED THREE ADD. CIVIL SHEETS PLUS CALCS. PER BRIAN M . CONTACTED ROPER HARTLY OF ALL THE ABOVE MENTIONED. HE IS FILLING IN FOR DAVE MARSH UNTIL 4-5-99 KMM 04-12-99 SPOKE WITH DAVE MARSH ABOUT THE ABOVE MENTIONED ITEMS. MARTY SPOKE WITH HIM ON 4-9-99 ABOUT DESIGN REVIEW. DAVE WILL BE SUBMITTING FOR DR THIS WEEK. IT WILL BE ABOUT A THREE WEEK PROCESS. KMM 5-5-99 DRH99-0076 PENDING
|
Received Certificate of Value | | | 3/26/1999 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/26/1999 | | |
|
|
|
|
Application received | | | 3/26/1999 | | |
|
|
|
|