BLD-Final | 5/20/2004 | 5/21/2004 | 5/21/2004 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Final | 5/20/2004 | 5/20/2004 | 5/20/2004 | A | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 3/15/2000 | 3/17/2000 | 3/17/2000 | A | PART |
Joe Tawney
|
|
|
###-#### Reinsp. ok on alarm system 3/17/00 2:38:17 PM
|
FIRE-Final Inspection | 1/12/2000 | 1/18/2000 | 1/18/2000 | A | FAIL |
Joe Tawney
|
|
|
ready at 10 marty ###-#### Alarm test fail C/N issued. 1/19/00 11:09:30 AM
|
INSP - Final | 8/18/1999 | 8/19/1999 | 8/19/1999 | A | FAIL |
Carl Dependahl
|
|
|
08/19/99 340 - PLEASE CALL BEFORE GOING. ART, ###-####. COURTESY INSP. i
|
INSP - Final | 8/17/1999 | 8/18/1999 | 8/18/1999 | A | FAIL |
Carl Dependahl
|
|
|
08/18/99 340 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 8/17/1999 | 8/17/1999 | 8/17/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/17/99 340 - art-- ###-#### call 1st pre fn insp--front off in lobby & new bathrooms & daycare; nr, recall
|
INSP-Conference | 7/19/1999 | 7/19/1999 | 7/19/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF REG ALARM SYSTEM ART BUSWELL
|
INSP - Framing/Rough-in | 7/19/1999 | 7/19/1999 | 7/19/1999 | P | FAIL |
Carl Dependahl
|
|
|
07/19/99 340 - ceiling leon ###-####; need elec at new grid, struct ok;
|
INSP - Framing/ Rough-in | 7/16/1999 | 7/16/1999 | 7/16/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF W/ BLDR RE 1HR CONST; NEED DISCUSS PLAN W/ DAN S.
|
INSP - Framing/ Rough-in | 7/15/1999 | 7/15/1999 | 7/15/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF ONLY W/ FRAMER
|
INSP-Conference | 7/14/1999 | 7/14/1999 | 7/14/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/ ART BUSSWELL REG ALARM DEF
|
INSP - Framing/Rough-in | 7/12/1999 | 7/12/1999 | 7/12/1999 | A | PART |
Carl Dependahl
|
|
|
07/12/99 340 - keep c/n, ok to cover at windows at cardio rm.. Contact
|
INSP - Framing/Rough-in | 6/30/1999 | 7/1/1999 | 7/1/1999 | A | PART |
|
|
|
07/01/99 338 - made ok to cover restroom walls fire caulking complete
|
INSP - Framing/Rough-in | 6/28/1999 | 6/29/1999 | 6/29/1999 | A | FAIL |
Carl Dependahl
|
|
|
06/29/99 340 - keep c/n, install firestops, dampers. ok to cover alcoves
|
INSP - Framing/ Rough-in | 6/28/1999 | 6/28/1999 | 6/28/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - KEEP C/N, CONF W/ DAN S.; NEED ADD'L SUBMITTAL.
|
INSP - Framing/Rough-in | 6/24/1999 | 6/25/1999 | 6/25/1999 | A | FAIL |
Carl Dependahl
|
|
|
06/25/99 340 - ###-####//FRAMING; c/n, do not cover
|
Plan resubmittals received | | | 6/7/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A0, A2.0, A3.0, A3.1, A4.0 ONE COVER LETTER. ONE COPY OF CALCS. ROUTED TO CARL D. KMM
|
Issue PAID IN FULL permit | | | 6/3/1999 | | |
|
|
|
|
INSP - Framing/Rough-in | 5/25/1999 | 5/25/1999 | 5/25/1999 | P | FAIL |
Carl Dependahl
|
|
|
no insp; rec'd resub from arch
|
Plan resubmittals received | | | 5/24/1999 | | PEND |
|
|
|
Received plan resubmittals from Mark Sanders, forwarded same to Carl Dependahl. DAR 5/24/99
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/1999 | | PASS |
|
|
|
Plans reviewed and inserted into original plans.
|
CHANGE STATUS TO (P) | | | 5/4/1999 | | |
|
|
|
AS PER KATHY RESUMMITTAL BROUGHT IN CHANGE TO PENDING STATUS.MPS
|
Plan resubmittals received | 5/4/1999 | | 5/4/1999 | | PASS |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A0, A2.0, A3.0, A3.1, A4.0. I HAD THE PERMIT CHANGED TO PENDING AND ROUTED PLANS TO DAN S. KMM 5-7-99 New Plans reviewed and notes made on plans. Copy to records for addition to original approved plans and copy to Carl Dependahl for taking to contractor to add to approved plans on site.
|
Telephone call | | | 4/29/1999 | | PASS |
|
|
|
talked to mark sanders to verify plans are ready
|
Inspection Record Card- Bld | | | 4/29/1999 | | |
|
|
|
|
Print Occupancy Form | | | 4/29/1999 | | |
|
|
|
|
Plan assigned to (DRS) | 3/31/1999 | | 4/28/1999 | | PASS |
Dan Stuart
|
|
|
04/28/99 10:03:19 DRS - this action updated by action script from <<>> in Case No. BLD99-0842
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/1999 | | PASS |
|
|
|
PLANS TO PERMIT DESK FOR ISSUANCE.
|
Routing - PLAN CHECK | 4/27/1999 | | 4/28/1999 | | PASS |
|
|
|
RD LINED PLANS. rEVIEWED WITH ARCHITECT BY PHONE & WITH BRENT JACKSON OF HILBERS, INC., CONTRACTOR IN PERSON A CITY OFFICE TO VERIFY HE UNDERSTOOD REQUIREMENTS AND TO EXPIDITE ISSUANCE OF PERMIT.
|
Meeting | | | 4/28/1999 | | |
|
|
|
MET WITH BRENT JACKSON, HILBERS, INC. TO REVIEW RED LINE COMMENTS ON PLANS & REQUIREMENTS FOR RATED EXIT CORRIDOR.
|
Telephone call | | | 4/27/1999 | | |
|
|
|
CALLED MARK SANDERS TO REVIEW CODE REQUIREMENTS FOR THIS PROJECT AND TO HAVE HIM RESPOND BY ADDENDUM TO CONTRACTOR AND THROUGH STRUCTURAL INSPECTOR TO ASSIST IN ISUUANCE OF PERMIT. HE AGREED.
|
Telephone call | | | 4/27/1999 | | |
|
|
|
Called Mark Sanders, architect to review with him the fact that this remodel will be within a rated 1-hour corridor and openings & penetrations will need to be protected per 97' UBC. I will note on plans requirements & send Mark copy of comments. He will follow up with addendum to contractor.
|
Print Pending Permit.LaserJet4 | | | 4/27/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/1/1999 | | 4/22/1999 | | |
|
|
|
Routed to Fire Dept for review.
|
Routing - FIRE | 4/22/1999 | | 4/22/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/6/1999 | | PEND |
|
|
|
Received plan resubmittals from Kenneth Douglass, forwarded same to Dan Stuart. DAR 4/6/99
|
Routing - PUBLIC WORKS | 3/31/1999 | | 4/1/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 3/31/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Received Certificate of Value | | | 3/30/1999 | | PASS |
|
|
|
|
Application received | | | 3/30/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/30/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/30/1999 | | PASS |
|
|
|
MARK WILL BE FAXING OVER RECORD DECLARATION FORM. KMM
|
Fee Review-notes | 9/9/1999 | 9/9/1999 | | | |
|
|
|
|