INSP - Framing/Rough-in | 7/26/1999 | 7/26/1999 | 7/27/2000 | P | PART |
Carl Dependahl
|
|
|
07/26/99 340 - part, furring & partitions ok to insul.
|
Fee Review-notes | 4/12/1999 | | 3/15/2000 | | DONE |
|
|
|
CK AMOUNT IS 1,801.00 WITH A VALUE OF $425,000 --
|
BLD-Final | 10/29/1999 | 10/29/1999 | 10/29/1999 | P | PASS |
Carl Dependahl
|
|
|
ok for c/o...card signed off
|
Permanent Occupancy | | 10/29/1999 | 10/29/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/29/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7976 issued 10-29-99 to Grand Auto Supply.
|
Telephone call | | | 10/27/1999 | | CALL |
|
|
|
Called ###-#### & talked w/Cindy re: 45 days before temp. expires!
|
FIRE-Final Inspection | 9/28/1999 | 9/29/1999 | 9/29/1999 | A | PASS |
Joe Tawney
|
|
|
gary ###-#### Reinsp. Ok for perm. Occ.
|
INSP - Final | 9/13/1999 | 9/13/1999 | 9/13/1999 | A | FAIL |
Carl Dependahl
|
|
|
KEEP C/N, REC'D ADD'L PERMIT FOR RACKING : BLD99-02006.
|
Code Occupancy Approval | | | 9/13/1999 | | DONE |
|
|
|
inspected 9/10/99 - Stripping for rest of parking and h/c will be completed on Wed. 9/15/99. All plants, sold and bark on site and currently being worked. arbs at the north boundary need to be larger.
|
INSP-Final Inspection | 9/9/1999 | 9/10/1999 | 9/10/1999 | A | PART |
Rick Jackson
|
|
|
FINAL OK FOR TEMP OCC, FIRE LANE STRIPING AND EXIT SIGN
|
INSP - Final | 9/9/1999 | 9/10/1999 | 9/10/1999 | P | FAIL |
Carl Dependahl
|
|
|
gary ###-####; OK FOR T/O, OK TO SIGN AT OFFICE. NEEED ADD'L PERMIT FOR RACKS, KEEP C/N...MAKE OTHER AGCY CORRECTIONS.
|
Temporary occupancy | | | 9/10/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3917 issued 9-10-99 to Grand Auto Supply.
|
INSP-Final Inspection | 9/3/1999 | 9/3/1999 | 9/3/1999 | P | FAIL |
Rick Jackson
|
|
|
need inventory list and racking; tested AHU shutdown - okay
|
INSP - Framing/ Rough-in | 8/4/1999 | 8/4/1999 | 8/4/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF W SUPT.
|
INSP - Energy code compliance | 7/27/1999 | 7/28/1999 | 7/28/1999 | A | PART |
Carl Dependahl
|
|
|
07/28/99 340 - insul ok, need arch's instruction re vapor barrier...cont
|
INSP - Framing/Rough-in | 7/19/1999 | 7/19/1999 | 7/20/1999 | P | PART |
Carl Dependahl
|
|
|
07/19/99 340 - ###-#### roof frame; c/n issued re glulam specs & racking
|
INSP - Framing/Rough-in | 7/16/1999 | 7/19/1999 | 7/19/1999 | A | NR |
Tom Arcoraci
|
|
|
07/19/99 408 - KEN ###-#### ROOF FRAMING
|
INSP - Foundation | 6/22/1999 | 6/23/1999 | 6/23/1999 | A | PART |
Carl Dependahl
|
|
|
06/23/99 340 - mpi will be coming out-masonary block grout pour-ken ###-####
|
INSP - Flatwork | 6/10/1999 | 6/10/1999 | 6/10/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - MTI ONSITE
|
INSP - Foundation | 6/4/1999 | 6/4/1999 | 6/4/1999 | P | PART |
Carl Dependahl
|
|
|
06/04/99 340 - pendspecinspreports
|
INSP - Foundation | 6/1/1999 | 6/2/1999 | 6/2/1999 | P | PART |
Carl Dependahl
|
|
|
06/02/99 340 - ###-####//STEM WALL POURING @ 2:30 pend spec insp
|
Plan resubmittals received | | | 6/1/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS E3.1, E3.2, E5.1. ROUTED TO TOM A. KMM
|
INSP - Foundation | 5/28/1999 | 5/28/1999 | 5/28/1999 | | PART |
Carl Dependahl
|
|
|
06/02/99 340 - ###-####//STEM WALL POURING @ 2:30 pend spec inspreports
|
INSP - Foundation | 5/26/1999 | 5/27/1999 | 5/27/1999 | P | PART |
Carl Dependahl
|
|
|
05/27/99 340 - ###-#### Ken; pend specinsp; front not complete
|
(F) Reprint permit | | | 5/24/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/21/1999 | | |
|
|
|
|
Print Occupancy Form | | | 5/17/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/1999 | | |
|
|
|
|
Telephone call | | | 5/17/1999 | | FAIL |
|
|
|
no answer
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/12/1999 | | 5/14/1999 | | PASS |
|
|
|
|
Plan assigned to (MLO) | 4/13/1999 | | 5/14/1999 | | PASS |
Mike Otto
|
|
|
|
Plan resubmittals received | | | 5/11/1999 | | |
|
|
|
RECEIVED THREE COPIES OF SHEET A1.1A, WHICH IS LABELED FOR REFERENCE ONLY, AND THREE COPIES OF REVISED SHEET A4.4. ONE COPY OF SOILS REPORT, AND ONE COMMENT LETTER DATED 5-10-99. ROUTED TO MIKE O. KMM
|
Plan resubmittals requested | | | 4/30/1999 | | FAIL |
|
|
|
CORRECTIONS SENT TO ARCHITECT. MLO
|
Routing - PUBLIC WORKS | 4/30/1999 | | 4/30/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/21/1999 | | 4/30/1999 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 4/27/1999 | | |
|
|
|
RECEIVED PLAN RESUBMITTALSFROM JMD ARCHITECTURE, FORWARDED SAME TO MIKE OTTO. DAR 4/27/99
|
Routing - FIRE | 4/21/1999 | | 4/22/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 4/19/1999 | | 4/21/1999 | | PASS |
|
|
|
x-ref. DRH99-0027
|
Routing - PLUMBING | 4/19/1999 | | 4/19/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/14/1999 | | 4/16/1999 | | FAIL |
|
|
|
No legal description, one is required, left message for Roger Smith at Pinnacle Engineers, per Jim Rich. DAR 4/19/99
|
Plans ACCEPTED BY PLAN TECH | 4/14/1999 | | 4/14/1999 | | |
|
|
|
|
Application received | 4/14/1999 | | 4/14/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/13/1999 | | |
|
|
|
|
Plan assigned to (MYS) | 4/13/1999 | | 4/13/1999 | | PASS |
Marlene Southard
|
|
|
|
Application received | | | 4/12/1999 | | |
|
|
|
|