BLD-Final | 4/21/2000 | 4/21/2000 | 4/21/2000 | A | PASS |
|
|
|
Added by Inspector: 338 On 04/21/2000 made ok per 301
|
BLD-Conference | 4/20/2000 | 4/20/2000 | 4/20/2000 | P | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 4/20/00 brian w. brought in a sample piece of the handrail that was instaled on the circular stair of this project. I approved the shape and size of this rail section for a one time only to this job only to be ok. this configuration will have to have 1 x .5 tube inlew of 1 x .25 flat bar to molded cap in the future.
|
BLD-Final | 4/19/2000 | 4/20/2000 | 4/20/2000 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 13:36:35. Contact: ###-####. Incomplete correction notice 408 4/20/00 1:35:24 PM
|
BLD-Final | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | FAIL |
Russ Owen
|
|
|
###-#### gate entry *4444 C/N, temp. glass, handrail 2" min., return to wall, crawl space insualtion vappor barrier. 4/19/00 9:57:14 AM
|
INSP - Framing/Rough-in | 8/11/1999 | 8/11/1999 | 8/11/1999 | P | PASS |
Russ Owen
|
|
|
08/11/99 407 - SHEAR WALL BRYAN ###-####
|
INSP - Framing/Rough-in | 8/2/1999 | 8/3/1999 | 8/3/1999 | A | PASS |
Russ Owen
|
|
|
08/03/99 407 - BRIAN ###-#### ASAP
|
INSP - Framing/Rough-in | 7/30/1999 | 8/2/1999 | 8/2/1999 | A | FAIL |
Russ Owen
|
|
|
08/02/99 407 - inside framing Dwayne ###-####
|
INSP - Framing/Rough-in | 7/30/1999 | 7/30/1999 | 7/30/1999 | P | NR |
Russ Owen
|
|
|
07/30/99 407 - CODE *4240 BRIAN ###-####
|
INSP - Framing/Rough-in | 7/28/1999 | 7/28/1999 | 7/28/1999 | P | FAIL |
Russ Owen
|
|
|
07/28/99 407 - gated com. *4240 Bryan ###-####
|
INSP - Framing/Rough-in | 6/29/1999 | 6/29/1999 | 6/29/1999 | P | PASS |
Russ Owen
|
|
|
06/29/99 407 - sheer wall gate code is *4240 Bryan ###-####
|
INSP - Framing/Rough-in | 6/24/1999 | 6/25/1999 | 6/25/1999 | A | FAIL |
Russ Owen
|
|
|
06/25/99 407 - NEED MORE STAPLES.SEE CORRECTIONS.
|
INSP - Framing/Rough-in | 6/15/1999 | 6/15/1999 | 6/15/1999 | P | FAIL |
Russ Owen
|
|
|
06/15/99 407 - corrections.
|
Issue PAID IN FULL permit | | | 5/12/1999 | | |
|
|
|
|
INSP - Foundation | 5/10/1999 | 5/10/1999 | 5/10/1999 | P | FAIL |
Russ Owen
|
|
|
05/10/99 407 - about 3/4 poured before approval.
|
INSP - Foundation | 5/7/1999 | 5/7/1999 | 5/7/1999 | P | FAIL |
Russ Owen
|
|
|
05/07/99 407 - poured with-out approval,also early start.
|
Plan assigned to (SAM) | 5/6/1999 | | 5/7/1999 | | PASS |
Steve Munroe
|
|
|
05/07/99 10:01:24 SAM - this action updated by action script from <<>> in Case No. BLD99-0986
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/1999 | | PASS |
|
|
|
|
Telephone call | | | 5/7/1999 | | |
|
|
|
CALLED LEFT MESSAGE W/STATEWIDE GAVE DOLLAR AMOUNT
|
Print Pending Permit.LaserJet4 | | | 5/7/1999 | | PEND |
|
|
|
|
Inspection Record Card- Bld | | | 5/7/1999 | | |
|
|
|
|
Plan assigned to (DJO) | 4/12/1999 | | 5/6/1999 | | PEND |
Dan Overy
|
|
|
|
Application received | | | 5/5/1999 | | PEND |
|
|
|
BRIAN BROUGHT PLANS BACK IN NO CHANGED WAS DONE ON PLAN.
|
Office Staff conference/action | | | 4/19/1999 | | PASS |
|
|
|
BRIAN, TOOK PLAN. GOING TO CHANGE HOUSE DESIGN.PE 4/19/99 BRIAN BROUGHT PLANS BACK NO CHANGES MADE TO THE HOUSE.
|
Routing - PUBLIC WORKS | 4/12/1999 | | 4/13/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/12/1999 | | |
|
|
|
|
Application received | | | 4/12/1999 | | |
|
|
|
|
Routing - PLANNING | 4/12/1999 | | 4/12/1999 | | PASS |
|
|
|
BRIAN TOOK PLANS GOING TO CHANGE HOUSE DESIGN. 4/19/99 APRIL HAD DONE SET BACKS ON IT BROUGHT PLANS BACK, NO CHANGES MADE
|
Routing - PLAN CHECK | 5/5/1999 | | | | PEND |
|
|
|
BRIAN BROUGHT PLANS BACK IN NO CHANGES WAS MADE. PER NOTE.
|
Routing - PLAN CHECK | 4/13/1999 | | | | PEND |
|
|
|
CHANGED DESIGN ON HOUSE. BRINGING IN NEW PLANS BRIAN BROUGHT PLANS BACK NO CHANGED TO HOUSE WAS MADE
|