Permit NumberBLD99-00989
StatusFinaled
Name MICRON TECH
Site Address 8000 S FEDERAL WAY
Project NameMIC FAB 1X (1ST.FL.)
Customer Number 
ePlanReviewNo
Description
MICRON BUILDING #1X -EXTEND WET ETCH BAYS & PLENUMS (PROJECT 01X-992557) TO DEMO WALLS AND DOORS BETWEEN WET ETCH AND PLENUM AREAS AND MAINTENANCE CORRIDOR 102E, AND TO EXTEND THE WET ETCH BAY AND PLENUM WALLS TO THE SOUTH WALL OF AREA 100B, AND TO ADD NEW EXIT DOORS FROM THE EXTENDED WET ETCH AND PLENUM AREAS AT THE EXISTING SOUTH WALL OF AREA 100B. THE WORK IS BEING DONE AT THE NORTH WEST CORNER OF BUILDNG 01X BETWEEN GRID LINES A.1 & C.9 AND 0.51 & 0.7. ALL CONSTRUCTION PER THE APPROVED PLANS AS DRAWN. PC#263-99/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  10/17/2000 DONE
Letter of Compliance #19954 issued 10-17-00.
BLD-Final10/16/200010/16/200010/16/2000APASS
DetailsJim Storey
Added by Inspector: 301 On 10/16/2000 l/c ok
BLD-Final10/2/200010/2/200010/2/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/02/2000 at 07:02:34. Contact: ###-####. slab ongrade ok. pending report. 10/2/2000 5:11:44 PM
FIRE-Final Inspection1/12/20001/13/20001/13/2000PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/12/2000 at 15:50:03. Contact: ###-####. As shown on plans. 1/14/00 2:36:45 PM
Receive PAYMENT IN FULL  6/21/1999
INSP - Framing/Rough-in6/4/19996/7/19996/7/1999APART
DetailsJim Storey
06/07/99 301 - WORK IN PROGESS OK FOR COVER
Issue & PRINT FEE-DUE permit  5/6/1999
Telephone call  5/5/1999
called permit ready
Routing - PLAN CHECK5/4/1999 5/5/1999 PASS
Print Occupancy Form  5/5/1999
Inspection Record Card- Bld  5/5/1999
PLANS/APPL TAKEN TO FRONT DESK  5/5/1999 PASS
Plan assigned to (JCM)4/13/1999 5/5/1999 PASS
DetailsJohn Menard
Plan Review Completed(1st rev)  5/4/1999 PASS
Routing - FIRE5/3/1999 5/4/1999 PASS
Plan Reviewer's activity  5/3/1999 PASS
PLANS REVIEWED AND APPROVED AS SUBMITTED.
Routing - PLAN CHECK4/20/1999 5/3/1999 PEND
Routing - PLUMBING4/14/1999 4/20/1999 PASS
Routing - PUBLIC WORKS4/13/1999 4/14/1999 PASS
Application received  4/13/1999
Plan routing begun/TENANTS4/13/1999 4/13/1999
Plan assigned to (MYS)4/13/1999 4/13/1999 PASS
DetailsMarlene Southard
Plans ACCEPTED BY PLAN TECH  4/13/1999 PASS
Received Certificate of Value  4/13/1999 PASS
CHANGE STATUS TO (P)  4/13/1999