Case Summary (BLD) | | | 10/14/2015 | | |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 10/17/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8437 issued 10-17-00 to Trus Joist.
|
Permanent Occupancy | | 10/16/2000 | 10/16/2000 | | DONE |
|
|
|
|
BLD-Final | 10/13/2000 | 10/16/2000 | 10/16/2000 | A | PASS |
Russ Owen
|
|
|
Marv Meyer, ###-#### - I have the card on my desk - Cathy
|
Code Occupancy Approval | | | 10/13/2000 | | PASS |
|
|
|
CONDITIONS HAVE BEEN MET FOR THE PROJECT, OKED BY TEMPRA WILSON TO SOME MODIFICATIONS, GRASS AREA BY BUILDING NOT REQUIRED TO HAVE TREES. FINAL OCCUPANCY SIGNED OFF.
|
Telephone call | | | 9/8/2000 | | DONE |
|
|
|
Talked w/Marv Meyer re: status of temp. occ.
|
Fee Review-notes | 4/30/1999 | | 7/25/2000 | | DONE |
|
|
|
|
BLD-Final | 7/7/2000 | 7/7/2000 | 7/7/2000 | P | PART |
Russ Owen
|
|
|
Marv, ###-#### - Russ, I have the bond for this (1) stair run, top step. 7/10/00 10:31:13 AM
|
Code Occupancy Approval | | | 7/7/2000 | | FAIL |
|
|
|
THIS PROJECT STARTED IN COUNTY, ALL SITE PLANS WERE APPROVED BY COUNTY, NOW PROPERTY IS LOCATED IN CITY BUT THE REQUIRED LANDSCAPE NOT IN AS REQUIRED, TALKED TO COUNTY PERSONNEL AND WAS TOLD THEY DID NOT THINK THEY COULD ENFORCE NOW THAT PROPERTY IS NOT IN COUNTY, TO INSURE WORK COMPLETED AS APPROVED I WOULD NOT SIGN TILL ALL LANDSCAPE IN OR A BOND POSTED, THEY POSTED A $20,000 BOND TO OCCUPY, THIS AMOUNT SEEMS LOW BUT WILL TAKE IT TO ENSURE COMPLIANCE, TEMPORARY SIGNED OFF.
|
Temporary occupancy | | | 7/7/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4036 issued 7-7-00 to Trus Joist MacMillan.
|
BLD-Final | 7/3/2000 | 7/3/2000 | 6/30/2000 | P | FAIL |
Russ Owen
|
|
|
C/n stair, zonning, code enforcement required for temp.
|
FIRE-Final Inspection | 6/29/2000 | 6/30/2000 | 6/30/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/29/2000 at 13:15:24. Contact: .
|
FIRE-Final Inspection | 6/15/2000 | 6/20/2000 | 6/20/2000 | P | FAIL |
Rick Jackson
|
|
|
bob--###-#### fn fire C/N issued 6/27/00 2:55:31 PM
|
BLD-Framing/Rough-in | 5/22/2000 | 5/23/2000 | 5/23/2000 | A | FAIL |
Russ Owen
|
|
|
ceiling ted ###-#### Fail C/N posted 5/24/00 11:09:52 AM
|
BLD-Framing/Rough-in | 4/17/2000 | 4/18/2000 | 4/18/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/17/2000 at 18:16:57. Contact: ###-####. Ok to sheetrock upper floor, need top of office wall restraints. 4/18/00 2:00:21 PM
|
BLD-Framing/Rough-in | 4/14/2000 | 4/17/2000 | 4/17/2000 | A | CANC |
Russ Owen
|
|
|
###-#### 2nd floor framing Unable to do to many others inspections, people off. 4/18/00 10:51:42 AM
|
BLD-Framing/Rough-in | 4/5/2000 | 4/6/2000 | 4/6/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/05/2000 at 18:24:13. Contact: ###-####. 1st level , need plumbing, engineers letter of inspection. 4/6/00 2:57:51 PM
|
BLD-Framing/Rough-in | 4/4/2000 | 4/5/2000 | 4/5/2000 | P | CANC |
Russ Owen
|
|
|
Ted ###-#### To many other inspections, unable to do 4/6/00 8:56:32 AM
|
FIRE-Supply Line Cover | 1/20/2000 | 1/21/2000 | 1/21/2000 | A | PASS |
Rick Jackson
|
|
|
Brad ###-#### set up an appointment at 8:30 Ok to cover. 1/21/00 1:54:10 PM
|
BLD-Footing | 11/4/1999 | 11/5/1999 | 11/5/1999 | P | PART |
Russ Owen
|
|
|
TED ###-#### Special inspector approval required.
|
BLD-Footing | 11/3/1999 | 11/4/1999 | 11/3/1999 | A | CANC |
Russ Owen
|
|
|
10 -12 YARDS TED ###-#### CANCELLED BY TED
|
BLD-Footing | 11/1/1999 | 11/2/1999 | 11/2/1999 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 09:17:28. Contact: . Subject to special insp. Onsite at time.
|
BLD-Footing | 10/19/1999 | 10/20/1999 | 10/20/1999 | P | PASS |
Jim Storey
|
|
|
before 2:30 pouring at that time-pads for columns steel steamwall ted ###-#### Center pads and south wall ok
|
BLD-Footing | 10/6/1999 | 10/7/1999 | 10/7/1999 | P | PART |
|
|
|
Ted ###-#### Need spec insp letter not on site need log & proper signoffs.
|
BLD-Foundation | 10/5/1999 | 10/5/1999 | 10/5/1999 | P | PART |
Russ Owen
|
|
|
Ted Parrott ###-#### subject to strata special insp report
|
Issue PAID IN FULL permit | | | 8/26/1999 | | |
|
|
|
|
Ready Permit EXTENDED | | | 8/6/1999 | | PASS |
|
|
|
EXTENDED PERMIT UNTIL 9/1/99-AS PER LETTER DATED 8/6/99 FROM MIKE CAPSHAW-NO OTHER EXTENSIONS SHALL BE GIVEN. ANY QUESTIONS PLEASE SEE MONICA
|
Telephone call | | | 8/4/1999 | | |
|
|
|
CALLED GAVE DOLLAR AMOUNT SHE WILL LET MARV KNOW THAT PLANS ARE NEEDING TO BE PICKED UP
|
Plan assigned to (JCM) | 4/26/1999 | | 6/10/1999 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 5/14/1999 | | 6/10/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/10/1999 | | |
|
|
|
|
Telephone call | | | 6/10/1999 | | PASS |
|
|
|
###-####
|
Plan resubmittals received | | | 6/9/1999 | | |
|
|
|
RECEIVED ONE COPY OF REVISED SHEETS, S1.4, S2.4, S3.4, S7.10, S7.11S7.12, S7.13, S7.14, ROUTED TO JOHN M. KMM
|
Routing Off Site - STRUCTURAL | 6/1/1999 | | 6/8/1999 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan resubmittals received | | | 6/1/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS S1.4, S2.4, S3.4, S7.10, S7.11, S7.12, S7.13, S7.14, ONE COPY OF RESPONSE LETTER. ROUTED TO JOHN M. KMM
|
Plan resubmittals received | | | 5/25/1999 | | PEND |
|
|
|
Received plan resubmittals from Mike Capshaw of BRS ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR 5/25/99
|
Plan Reviewer's activity | | | 5/25/1999 | | PASS |
|
|
|
REVIEWED AND APPROVED RESUBMITTED PLAN REVISIONS AS DRAWN WITH ATTACHED COMMENT LIST.
|
Plan resubmittals requested | | | 5/17/1999 | | PEND |
|
|
|
FAXED MIKE CAPSHAW AT BRS REQUESTING ADDITIONAL RESUBMITTALS.
|
Plan resubmittals received | | | 5/14/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM MIKE CAP SHAW, BRS ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR 5/14/99.
|
Routing - FIRE | 5/12/1999 | | 5/13/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 5/13/1999 | | FAIL |
|
|
|
ubc
|
Routing - PLAN CHECK | 5/3/1999 | | 5/12/1999 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 5/12/1999 | | PEND |
|
|
|
FAXED AND MAILED MIKE CAPSHAW AT BRS A COPY OF THE PLAN REVIEW COMMENT LIST REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 4/27/1999 | | 5/7/1999 | | FAIL |
|
|
|
WILL SEND TO OUTSIDE ENG. AFTER I RECEIVE THE SOILS REPORT. KMM SOIL REPORT RECEIVED 4/27/99 DAR
|
Plan resubmittals requested | | | 5/7/1999 | | PEND |
|
|
|
FAXED MIKE CAPSHAW A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing - PLUMBING | 4/29/1999 | | 5/3/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/26/1999 | | 4/29/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 4/29/1999 | | 4/29/1999 | | PASS |
|
|
|
This project was approved in the County, therefore no DR was required.
|
Plan assigned to (MYS) | 4/22/1999 | | 4/26/1999 | | |
Marlene Southard
|
|
|
|
Plan routing begun/NEW & ADDTN | 4/26/1999 | | 4/26/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/26/1999 | | PASS |
|
|
|
REQUIRES SOIL REPORT BEFORE ROUTING TO OUTSIDE ENG. KMM RECEIVED SOILS REPORT FROM BRS. DAR 4/27/99
|
Received Certificate of Value | | | 4/22/1999 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/22/1999 | | |
|
|
|
|
Application received | | | 4/22/1999 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|