Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-01284
StatusFinaled
Name WESTGATE PLAZA
Site Address 1755 N WESTGATE DR
Project NameWESTGATE PLAZA-FLR 1
Customer Number 
ePlanReviewNo
Description
To upgrade a portion of the existing main corridor located on the first floor in the Southwest quarter, to comply with 1-hr. construction per approved plans on file. Work to include removal of existing ceiling grid system & light fixtures from corridor 101; installation of noncombustible framing with fire code sheetrock cover extending from top of existing wall to the bottom of the double concrete "T" deck; installation of complying labeled door/frame/gasketing & closure assemblies opening into corridor; installation of listed/labeled 3/4 hour glazing assemblies for sidelights and any other existing windows into corridor (to be 25% or less of wall area common to room & corridor); install new ceiling grid system & reintall light fixtures. All per plans notes & attachments. (P.C.#337-99)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  5/30/2007  
Fee Review-notes5/6/1999 4/14/2000 DONE
Print Occupancy Form  4/7/2000 DONE
Letter of compliance  4/7/2000 DONE
Letter of Compliance #18393 issued 4-7-00.
BLD-Final3/14/20003/14/20003/14/2000APASS
DetailsTom Arcoraci
Final approved for L.C.
BLD-Final3/8/20003/8/20003/8/2000PFAIL
DetailsTom Arcoraci
###-#### Ok for L/C after mech. final. 3/9/00 11:37:27 AM
BLD-Final10/13/199910/13/199910/13/1999PFAIL
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/13/1999 at 10:55:20. Contact: ###-####. No paper work at site. No answer on phone #.
FIRE-Final Inspection10/7/199910/8/199910/8/1999APASS
DetailsJoe Tawney
REINSP OK FOR CERT OF COMPLETION
FIRE-Final Inspection9/30/19999/30/199910/1/1999PFAIL
DetailsJoe Tawney
JANICE ###-#### Seal openings in utility closet walls, ceilings. Seal on top of all ducts w/fire calk to maintain 1hr. Seperation.
FIRE-Final Inspection9/22/19999/23/19999/23/1999PCANC
DetailsJoe Tawney
Larry Wickham, ###-#### - please call 1st so he can meet you there To be rescheduled later
BLD-Final9/21/19999/21/19999/21/1999PFAIL
DetailsTom Arcoraci
MARK -- ###-#### FN OCC as per plan - framing ok
INSP - Framing/Rough-in7/28/19997/29/19997/29/1999AFAIL
DetailsJim Sly
07/29/99 316 - C/N....Need Cont. gyp membrane at fountain and fire ext r
INSP - Framing/Rough-in7/14/19997/15/19997/15/1999PNR
DetailsTom Arcoraci
07/15/99 408 - MARK ###-#### FIRE-RATED CORRIDOR INSPECTION
SUPER- Supervisor's review6/24/19996/24/19996/24/1999
tom archirossi and i met with contractor to review problems with corridor. they will install metal angles and sheetrock to seal next to t beams archetect will submit detail for approval
INSP - Foundation6/23/19996/24/19996/24/1999APART
DetailsTom Arcoraci
06/24/99 408 - ###-#### LARRY//CONFERENCE ALSO NEEDS GEORGE?
INSP - Framing/Rough-in6/17/19996/18/19996/18/1999APART
DetailsTom Arcoraci
06/18/99 408 - CONFERENCE Mark Haggerty ###-####
Issue PAID IN FULL permit  6/9/1999
Telephone call  6/4/1999
called MH construction
Inspection Record Card- Bld  6/4/1999
Plan assigned to (DRS)5/11/1999 6/3/1999 PASS
DetailsDan Stuart
06/03/99 14:18:16 DRS - this action updated by action script from <<>> in Case No. BLD99-1284
Routing - PLAN CHECK6/3/1999 6/3/1999 PASS
Approved as noted and attached.
PLANS/APPL TAKEN TO FRONT DESK  6/3/1999 PASS
Approved as noted and attached. Routing to permit desk for processing for building permit.
Print Pending Permit.LaserJet4  6/3/1999 PASS
Approved as noted and attached.
Routing - PLAN CHECK5/11/1999 6/2/1999 PEND
Picked up plans to begin review.
Plan assigned to (MYS)5/6/1999 5/11/1999
DetailsMarlene Southard
Plan routing begun/TENANTS  5/11/1999
Route to PLAN CHECK. Provide a copy of the plan review and permit to Fire for their records.
Plans ACCEPTED BY PLAN TECH  5/6/1999 PASS
Recd Pcfee & Taken To Pln CK  5/6/1999
Application received  5/6/1999
Received Certificate of Value  5/6/1999 PASS