BLD-Final | 10/21/1999 | 10/22/1999 | 10/22/1999 | A | FAIL |
Tom Arcoraci
|
|
|
troy ###-#### reinspect for occ No access
|
BLD-Final | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | PASS |
Tom Arcoraci
|
|
|
FN OCC ---TROY-- ###-#### L.C. issued
|
BLD-Final | 10/20/1999 | 10/21/1999 | 10/21/1999 | A | FAIL |
Jim Sly
|
|
|
DAN--- ###-#### FN OCC C/N.. Gnardrail will not resist 20lb lateral load
|
INSP - Energy code compliance | 8/16/1999 | 8/16/1999 | 8/16/1999 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Framing/Rough-in | 8/12/1999 | 8/13/1999 | 8/13/1999 | A | PASS |
Jim Sly
|
|
|
08/13/99 316 -
|
INSP - Framing/Rough-in | 8/11/1999 | 8/12/1999 | 8/12/1999 | P | FAIL |
Jim Sly
|
|
|
08/12/99 316 - NR
|
INSP - Energy code compliance | 8/11/1999 | 8/12/1999 | 8/12/1999 | P | FAIL |
Jim Sly
|
|
|
08/12/99 316 - NR
|
INSP - Framing/Rough-in | 8/9/1999 | 8/10/1999 | 8/10/1999 | P | FAIL |
Jim Sly
|
|
|
08/10/99 316 - C/N...Truss and point loads
|
INSP - Framing/Rough-in | 8/5/1999 | 8/5/1999 | 8/5/1999 | P | PART |
Tom Arcoraci
|
|
|
08/05/99 408 - ok to side
|
INSP - Framing/Rough-in | 8/4/1999 | 8/4/1999 | 8/4/1999 | P | FAIL |
Tom Arcoraci
|
|
|
08/04/99 408 - incomplete correction notice
|
INSP - Framing/Rough-in | 8/2/1999 | 8/2/1999 | 8/2/1999 | P | FAIL |
Jim Sly
|
|
|
08/02/99 316 - Shear wall...C/n....Nailing
|
INSP - Foundation | 6/15/1999 | 6/15/1999 | 6/15/1999 | | FAIL |
Tom Arcoraci
|
|
|
06/15/99 408 - poured without inspection
|
INSP - Foundation | 6/14/1999 | 6/15/1999 | 6/15/1999 | A | FAIL |
Tom Arcoraci
|
|
|
06/15/99 408 - poured without inspection
|
INSP - Foundation | 6/10/1999 | 6/11/1999 | 6/11/1999 | A | PART |
Jim Sly
|
|
|
06/11/99 316 - Soil, foot and rebar OK....Setbks appear OK...
|
INSP - Foundation | 6/9/1999 | 6/9/1999 | 6/9/1999 | P | FAIL |
Jim Sly
|
|
|
06/09/99 316 - No forms or humans on site.....No address posted...3:15PM
|
Issue PAID IN FULL permit | | | 6/7/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/18/1999 | | PEND |
|
|
|
|
Telephone call | | | 5/18/1999 | | |
|
|
|
TALKED TO RANDY GAVE DOLLAR AMOUNT
|
Plan assigned to (SAM) | 5/17/1999 | | 5/18/1999 | | PASS |
Steve Munroe
|
|
|
05/18/99 09:35:05 SAM - this action updated by action script from <<>> in Case No. BLD99-1300
|
Inspection Record Card- Bld | | | 5/18/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/18/1999 | | PEND |
|
|
|
Called the designer to get some questions answered. (Engineering, bearing and truss span questions.) I had to leave a message.
|
Plan assigned to (DJO) | 5/6/1999 | | 5/17/1999 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 5/6/1999 | | 5/7/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/7/1999 | | 5/7/1999 | | PASS |
|
|
|
|
Application received | | | 5/6/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 5/7/1999 | | | | PEND |
|
|
|
|