Fee Review-notes | 6/19/2003 | 6/19/2003 | 6/19/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 7/26/2000 | 7/26/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/24/2000 | 7/26/2000 | 7/26/2000 | A | PASS |
Rick Jackson
|
|
|
###-#### fire fn
|
BLD-Final | 7/24/2000 | 7/26/2000 | 7/26/2000 | P | PASS |
Jim Storey
|
|
|
###-#### fn occ
|
Permanent occupancy | | | 7/26/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8310 issued 7-26-00 to the Boise Cascade Distribution Center.
|
Plan resubmittals received | | | 4/21/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS ONE SET OF A3 AND A6 BY OLS0N AND ASSOCIATES VIA K2 CONSTRUCTION, FORWARDED SAME TO JIM STOREY. 4/21/00 DAR
|
BLD-Final | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | PART |
Jim Storey
|
|
|
###-#### temp occ. only. 4/18/00
|
BLD-Final | 4/14/2000 | 4/17/2000 | 4/17/2000 | P | FAIL |
|
|
|
###-#### need to recall 04/17/2000
|
Code Occupancy Approval | | | 4/17/2000 | | PASS |
|
|
|
all required landscape, parking and building colors as required under DRH99-0011, FINAL SIGNED OFF.
|
FIRE-Final Inspection | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | PART |
Rick Jackson
|
|
|
###-#### Temp. occ. approved per Dave Miller; awaiting smoke vents 4/17/00 1:48:57 PM
|
BLD-Other | 3/31/2000 | 3/31/2000 | 3/31/2000 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 3/31/00 RESUBMATIAL FOR DELEATING RATED CHEM-STORAGE ROOM APPROVED. OVER EXEMPT AMOUNTS PER THE 97 UBC 3-D.
|
BLD-Other | 3/31/2000 | 3/31/2000 | 3/31/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by Inspector: 301 On 3/31/00 resubmital droped off at site. 4/4/00
|
Fee Review-notes | 5/11/1999 | | 3/30/2000 | | DONE |
|
|
|
|
Fee Review-notes | 6/11/1999 | | 3/30/2000 | | DONE |
|
|
|
LINDA, THIS PERMIT WAS INITIALLY SUBMITTED WITH THE PARKING LOT AND T.I. ALSO, UNDER BLD99-1352 WITH A PROJECT VALUE OF $500,000. I HAD DANA SEPARATE THE INITIAL SUBMITTAL INTO THREE SEPARATE PERMITS. 1.PARKING LOT - NO PLAN CHECK FEE REQUIRED. 2. WAREHOUSE ADDITION AND 3. T.I. IF YOU NEED TO SEE WHAT MONIES WERE PAID PLEASE LOOK AT BLD99-1352. THANK YOU, KATHY MILLER
|
BLD-Framing/Rough-in | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | PART |
Jim Storey
|
|
|
###-#### 1hr wall frame ok also boxed out ele. panel. 3/14/00 10:38:30 AM
|
FIRE-Supply Line Cover | 1/20/2000 | 1/20/2000 | 1/20/2000 | A | PART |
Rick Jackson
|
|
|
not connected to UW; 10 feet remaining to complete to street
|
Issue PAID IN FULL permit | | | 11/10/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/9/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/9/1999 | | DONE |
|
|
|
called Dana Kauffman ###-#### permit ready with fees but he needs ACHD before issuance
|
Plan assigned to (MLO) | 6/11/1999 | | 11/9/1999 | | PASS |
Mike Otto
|
|
|
|
Routing - PUBLIC WORKS | 11/8/1999 | 11/8/1999 | 11/8/1999 | | PASS |
|
|
|
|
Routing - FIRE | 10/29/1999 | 10/29/1999 | 11/2/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/28/1999 | | 10/29/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/28/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM OLOSON AND ASSOCIATES, FORWARDED SAME TO MIKE OTTO. 10/28/99 DAR
|
Meeting | | | 10/20/1999 | | PEND |
|
|
|
had meeitng with owner, contractor, architect, fire and building dept. in regards to storage of hazardous materials and liquid storage room with secondary requirement. MLO
|
Routing - FIRE | 9/28/1999 | 9/28/1999 | 10/4/1999 | | FAIL |
|
|
|
Flammable liquids storage room lacks detailed information required to make any review possible by the fire department. Requirements meeting UFC 78, 80 and 81 and NFPA.
|
Plan resubmittals received | | | 9/29/1999 | | PEND |
|
|
|
RECEIVED MDS SHEETS FROM OLSON AND ASSOCIATES, FORWARDED SAME TO MIKE OTTO. 9/29/99 DAR
|
Routing - PLAN CHECK | 9/14/1999 | | 9/28/1999 | | FAIL |
|
|
|
plans have been modified with the addition of a hazardous liquid store room. additional corrections faxed to architect 9-28-99. mlo
|
Plan resubmittals requested | | | 9/28/1999 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/22/1999 | 9/23/1999 | 9/23/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/22/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF STRUCTURAL PLAN CHECK REVIEW RESPONSE. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 9/14/1999 | | PEND |
|
|
|
Received plan resubmittals from Olson and associates , forwarded same to mike otto
|
Routing - FIRE | 9/9/1999 | 9/9/1999 | 9/10/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/30/1999 | | 9/9/1999 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/9/1999 | | FAIL |
|
|
|
faxed and mailed corrections to architect. mlo
|
Plan resubmittals requested | | | 9/3/1999 | | FAIL |
|
|
|
STRUCTRUAL CORRECTIONS FAXED TO ARCHITECT. MLO
|
Routing Off Site - STRUCTURAL | 8/16/1999 | | 9/2/1999 | | FAIL |
|
|
|
I WILL SEND TO OUTSIDE ENG. WHEN I RECEIVE PLANS FOR THE METAL BUILDING. I CONTACTED DANA KAUFFMAN OF THIS NEED. HE STATED THEY WILL BE BRINGING IN THE METAL BUILDING PLANS THE WEEK OF THE 21ST. I ALSO INFORMED DANA THAT OUTSIDE ENG. HAS 15 WORKING DAYS TO COMPLETE THEIR REVIEW. KMM 7-1-99 CONTACTED DANA ABOUT ENG. STATES COUPLE WEEKS OUT YET. KMM 7-21-99 STILL NO PLANS FOR THE METAL BUILDING. KMM 8-11-99 CONTACTED DANA ABOUT PLANS FOR METAL BUILDING. KMM 8-16-99 RECEIVED PLANS WITH CALCS. FOR THE METAL BUILDING AND ROUTED TO OUTSIDE ENG. VIA PDQ. KMM
|
Plan resubmittals received | | | 8/30/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM OLSON AND ASSOCIATES, FORWARDED SAME TO MIKE OTTO. 8/30/99 DAR
|
Plan resubmittals received | | | 8/20/1999 | | |
|
|
|
Received three copies of revised foundation designs, and three copies of stamped and signed drawings from Butler. Also received revised calcs. Routed to Mike O. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/1999 | | PASS |
|
|
|
8-16-99 RECEIVED ENG. FOR THE METAL BUILDING FROM DANA. HOWEVER THE COVER SHEET WAS THE ONLY SHEET SIGNED. WILL SEND TO OUTSIDE ENG. BUT ASKED DANA TO GET THE REST OF THE SHEETS STAMPED AND SIGNED. ALSO RECEIVED CALCS. KMM
|
Telephone call | | | 8/12/1999 | | |
|
|
|
CONTACTED DANA ABOUT METAL BUILDING. HE WAS NOT THERE, SO LEFT MESSAGE WITH OFFICE. KMM
|
Telephone call | | | 7/21/1999 | | |
|
|
|
CONTACTED DANA KAUFMAN REGUARDING THE PLANS FOR THE METAL BUILDING AND THE FACT THAT I NEED THEM BEFORE I CAN SEND TO OUTSIDE ENG. KMM
|
Plan Review Completed(1st rev) | | | 6/30/1999 | | FAIL |
|
|
|
|
Routing - FIRE | 6/29/1999 | | 6/30/1999 | | FAIL |
|
|
|
A Fire hydrant location not found within spacing.
|
Routing - PLAN CHECK | 6/17/1999 | | 6/29/1999 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 6/29/1999 | | FAIL |
|
|
|
CORRECTIONS SENT TO ARCHITECT. PLANS FOR METAL BUILDING NOT PROVIDED FOR AT THIS TIME. MLO
|
Routing - PLUMBING | 6/16/1999 | | 6/17/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 6/16/1999 | | 6/16/1999 | | PASS |
|
|
|
DRH99-0011
|
Routing - PUBLIC WORKS | 6/11/1999 | | 6/16/1999 | | FAIL |
|
|
|
Failed because they require Drainage Plan Revisions as per Brian Murphy.mps
|
Plan assigned to (MYS) | 5/11/1999 | | 6/11/1999 | | PASS |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/11/1999 | | PEND |
|
|
|
7-21-99 STILL WAITING FOR THE METAL BLD. PLANS TO SEND TO OUTSIDE ENG. KMM
|
Received Certificate of Value | | | 6/11/1999 | | PASS |
|
|
|
REVISED CERT. OF VALUE. PROJECT VALUE NOW READS $200,000 ELEC. $15,000 PLUMB. MECH. N/A AND FIRE SPRINKLER #28,000 KMM
|
Plan routing begun/NEW & ADDTN | 6/11/1999 | | 6/11/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/13/1999 | | HOLD |
|
|
|
APPL. SUBMITTED THREE PROJECTS UNDER ONE PERMIT. WE WILL SEPARATE OUT INTO THREE PERMITS. 1. ADDITION TO WAREHOUSE. 2. T. I. FOR EXISTING WAREHOUSE 3. GRADING AND DRAINAGE FOR WAREHOUSE ADD. AND PARKING LOT. I WILL USE SAME SET OF PLANS FOR GRADING AND ADD. ADD. REQUIRES ELEC. PLUMB. AND MECH. PLANS AS APPLIES. NEW APPLICATION, AND OUTSIDE ENG. PACKAGE. STRUCT. CALCS WERE SUMITTED UNDER THE 94 CODE. PARKING LOT REQUIRES NEW APPLICATION WITH CERT. OF VALUE CALLING OUT SITE UTILITY VALUES. T.I. REQUIRES PLUMB. PLANS PER GARY ZIGLER. AND TWO SETS OF PLANS. CONTACTED DANA KAUFFMAN OF THESE NEEDS AT ###-#### KMM 5-24-99 DANA KAUFFMAN CALLED AND STATED THAT HE WILL BE IN NEXT WEEK WITH PLANS FOR THE WAREHOUSE ADD. AND PARKING LOT. I WILL USE THE BLD99-1352 NUMBER FOR THIS PERMIT. HE WILL THEN PICK UP THE T.I. PLANS AND SUBMITT AT A LATER DATE. THEY ARE MAKING INTERIOR CHANGES TO T.I. I TOLD DANA THAT TIME FRAME OF 8 WEEKS WILL NOT START UNTIL I RECEIVE AND CAN START ROUTING BLD99-1352. KMM
|
Recd Pcfee & Taken To Pln CK | | | 5/11/1999 | | |
|
|
|
|
Application received | | | 5/11/1999 | | |
|
|
|
|