Fee Review-notes | 5/24/1999 | | 3/22/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 1/27/2000 | | DONE |
|
|
|
Letter of Compliance #18349 issued 1-27-00.
|
Receive PAYMENT IN FULL | | | 11/8/1999 | | DONE |
|
|
|
|
Letter of compliance | | | 10/19/1999 | | DONE |
|
|
|
Letter of Compliance #17934 issued 10-19-99.
|
Temporary occupancy | | | 9/13/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3919 issued 9-13-99 to H-P (auditorium remodel).
|
INSP - Final | 8/30/1999 | 8/31/1999 | 8/31/1999 | A | PASS |
Tom Arcoraci
|
|
|
08/31/99 408 - ok for perm occ
|
INSP-Final Inspection | 8/26/1999 | 8/27/1999 | 8/27/1999 | P | PASS |
Joe Tawney
|
|
|
09/01/99 406 - REINSP OK FOR CERT OF COMPLETION/OCC
|
INSP - Final | 8/23/1999 | 8/25/1999 | 8/25/1999 | A | CANC |
Tom Arcoraci
|
|
|
08/25/99 408 - JAY ###-####
|
INSP-Final Inspection | 8/19/1999 | 8/24/1999 | 8/24/1999 | P | FAIL |
Joe Tawney
|
|
|
09/01/99 406 - FINAL FAIL C/N ISSUED
|
INSP - Framing/Rough-in | 8/17/1999 | 8/18/1999 | 8/18/1999 | A | PART |
Carl Dependahl
|
|
|
08/18/99 340 - dave ###-####; FURRED WALL OK, CHK CLG AT FINAL
|
INSP-Final Inspection | 8/16/1999 | 8/17/1999 | 8/17/1999 | P | FAIL |
Joe Tawney
|
|
|
08/17/99 406 - FINAL FAIL C/N ISSUED
|
INSP - Framing/Rough-in | 8/17/1999 | 8/17/1999 | 8/17/1999 | P | CANC |
Tom Arcoraci
|
|
|
08/17/99 408 - will recall
|
Print Occupancy Form | | | 7/1/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 7/1/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/1/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 6/30/1999 | | 6/30/1999 | | PASS |
|
|
|
Received plans back from fire dept plan review approved as noted. Processing for issuance of permit.
|
Plan Review Completed(1st rev) | | | 6/30/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/1999 | | PASS |
|
|
|
Routing to permit desk for processing.
|
Additional plans submitted | | | 6/30/1999 | | |
|
|
|
Received requested floor plan copy designating the clear room size dimensions to be used by the contractor and verified by the structural inspector to keep auditorium with in allowable area for an A-3 occupancy. Attached copy to plans.
|
Routing - PLAN CHECK | 6/29/1999 | | 6/30/1999 | | PASS |
|
|
|
Architect & HP reduced the size of the auditorium to be 2093 s.f. or less for seating area by showing new walls on interior of room to reduce overall width and by extending storage area on south thereby the existing A3 occupancy status will remain and all the construction upgrade for fire-resistance and exit system modification go away. Plans approved and routed to fire dept for review.
|
Routing - FIRE | 6/30/1999 | | 6/30/1999 | | PASS |
|
|
|
HAVE CONDITIONS BEFORE INSTALL ON COMBUSTIBLES IN CAVITY.
|
Plan assigned to (DRS) | 6/3/1999 | | 6/30/1999 | | PASS |
Dan Stuart
|
|
|
06/30/99 17:20:47 DRS - this action updated by action script from <<>> in Case No. BLD99-1508
|
Print Pending Permit.LaserJet4 | | | 6/29/1999 | | |
|
|
|
Routing to fire code plan review.
|
Plan resubmittals received | | | 6/29/1999 | | PASS |
|
|
|
New submittals received changing assembly area to continue use as exists - A3 occupancy max. 299 occupant load - to be posted in room per code section 1007.2.6 UBC
|
Plan resubmittals received | | | 6/29/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM LOMBARD CONRAD, FORWARDED SAME TO DAN STUART. DAR 6/29/99
|
Telephone call | | | 6/28/1999 | | |
|
|
|
Call from Scott Henson to question plan review. I expalined to him and suggested he go to HP and suggest the area be reduced to allow continuing occupancy group of A-3 as currently exists and remove a mountain of trouble to upgrade an existing assembly area which is located centrally and will require major modifications to the exit system to go forward as proposed.
|
Meeting | | | 6/28/1999 | | HOLD |
|
|
|
Met with Scott Henson to review the requirements noted on plan review comments & how to address them if the area is reduced to maintain the A-3 occupancy. Most of the requirements will go away if the occupancy group is not changed. Scott to resubmit plans showing method of area reduction and maximum allowable area. All one-hour construction requirements will then go away.
|
Plan resubmittals requested | | | 6/24/1999 | | FAIL |
|
|
|
Plans incomplete for proposed occupancy group change. Exit system upgrade specified for this type of assembly occupancy was not addressed on submitted plans. Copy of prliminary review sent to architect with suggestion that area of assembly be reduced by 167 s.f. to 2,093 s.f. or less w/ 299 occ. load to maintain the A3 occupancy and avoid required upgrades. Plans submitted indicate a maximum desired minimum seating of 184 which can easily be achieved by reducing the area
|
Routing - PLAN CHECK | 6/4/1999 | | 6/22/1999 | | FAIL |
|
|
|
Plans on hold - rejected. Not designed for A2.1 as to type of construction, occupancy separation or exiting.
|
Plan routing begun/TENANTS | | | 6/4/1999 | | |
|
|
|
Route to PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 5/24/1999 | | 6/3/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/25/1999 | | KPAS |
|
|
|
|
Application received | | | 5/24/1999 | | |
|
|
|
|