Fee Review-notes | 6/19/2003 | 6/19/2003 | 6/19/2003 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 4/17/2000 | | DONE |
|
|
|
|
Fee Review-notes | 5/28/1999 | | 3/30/2000 | | DONE |
|
|
|
additional value from subs
|
(F) Reprint permit | | | 3/30/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/25/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8105 issued 1-25-00 to the lyle Pearson Acura Dealership.
|
BLD-Final | 1/24/2000 | 1/24/2000 | 1/24/2000 | P | PASS |
Carl Dependahl
|
|
|
bob ###-#### cn ok ok to sign for co 1/31/00 9:00:36 AM
|
Permanent Occupancy | | 1/24/2000 | 1/24/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/24/2000 | 1/24/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/22/1999 | 12/22/1999 | 12/22/1999 | P | PASS |
Joe Tawney
|
|
|
Final, Bob ###-#### - Lyle Pearson Acura. Reinsp. ok for permanent occupancy.
|
Code Occupancy Approval | | | 12/20/1999 | | PASS |
|
|
|
Meets compliance with DRH99-00043/DRH99-00129
|
BLD-Conference | 11/30/1999 | 11/30/1999 | 11/30/1999 | A | PASS |
Carl Dependahl
|
|
|
w/supt. keep C/N.
|
BLD-Final | 11/24/1999 | 11/29/1999 | 11/29/1999 | A | FAIL |
Carl Dependahl
|
|
|
BOB ###-####
|
Override - Parcel Holds | | | 11/29/1999 | | |
|
|
|
|
Temporary occupancy | | | 11/29/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3948 issued 11-29-99 to Lyle Pearson Acura.
|
Override - Parcel Holds | | | 11/29/1999 | | |
|
|
|
|
BLD-Final | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | FAIL |
Carl Dependahl
|
|
|
C/N; listed firestop/ Top-of-wall; hand rails ok for T/O.
|
FIRE-Final Inspection | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | PART |
Joe Tawney
|
|
|
bob ###-#### Final ok for temp. occ. Rotate hydrant, provide approved exit sign.
|
Override - Parcel Holds | | | 11/24/1999 | | |
|
|
|
|
Override - Parcel Holds | | | 11/24/1999 | | |
|
|
|
|
Override - Parcel Holds | | | 11/24/1999 | | |
|
|
|
|
BLD-Other | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 16:17:05. Contact: ###-####. Ceiling, ok; keep C/N.
|
FIRE-Conference | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PART |
Joe Tawney
|
|
|
Bob ###-#### Conf. Pre-final.
|
Override - Parcel Holds | | | 11/22/1999 | | |
|
|
|
|
Override - Parcel Holds | | | 11/22/1999 | | |
|
|
|
|
BLD-Framing/Rough-in | 11/2/1999 | 11/2/1999 | 11/2/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/02/1999 at 07:23:44. Contact: ###-####. Keep C/N
|
BLD-Framing/Rough-in | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Carl Dependahl
|
|
|
bob ###-#### C/N; ok to cover int. wall except as noted.
|
BLD-Conference | 10/25/1999 | 10/25/1999 | 10/25/1999 | A | PASS |
Carl Dependahl
|
|
|
Met w/supt. re: spec. insp. req's
|
INSP - Concrete | 9/7/1999 | 9/8/1999 | 9/8/1999 | P | PART |
Carl Dependahl
|
|
|
greg ###-#### -grout pour --concrete; KLEINFELDER ONSITE, W.I.P.
|
INSP - Concrete | 9/7/1999 | 9/7/1999 | 9/7/1999 | P | PART |
Carl Dependahl
|
|
|
greg-- ###-#### masonary grout pour; 9/7 spec insp onsite, grouting. jrb
|
INSP - Concrete | 9/3/1999 | 9/3/1999 | 9/3/1999 | P | PART |
Carl Dependahl
|
|
|
09/03/99 340 - for concrete grout-greg ###-####; pend report
|
INSP - Concrete | 9/1/1999 | 9/2/1999 | 9/2/1999 | A | PART |
Tom Arcoraci
|
|
|
09/02/99 408 - spec insp
|
INSP - Concrete | 9/1/1999 | 9/1/1999 | 9/1/1999 | P | PART |
Carl Dependahl
|
|
|
09/01/99 340 - MASONRY GROUT POUR. GREGG ###-####; mti onsite
|
INSP - Concrete | 8/31/1999 | 8/31/1999 | 8/31/1999 | P | PART |
Carl Dependahl
|
|
|
08/31/99 340 - ###-####- greg-concrete-grout pour; KLEINFELDER ONSITE
|
INSP - Concrete | 8/30/1999 | 8/30/1999 | 8/30/1999 | P | PART |
Carl Dependahl
|
|
|
08/30/99 340 - GREG ###-#### MASONRY, GROUT WORK
|
INSP - Foundation | 8/26/1999 | 8/27/1999 | 8/27/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/27/99 340 - MASONARY POUR GREG ###-####; nobody onsite?
|
INSP - Foundation | 8/26/1999 | 8/26/1999 | 8/26/1999 | P | PART |
Carl Dependahl
|
|
|
08/26/99 340 - THEY ARE POURING AT ONE PM GREG ###-####
|
INSP - Concrete | 8/24/1999 | 8/25/1999 | 8/25/1999 | A | PART |
Carl Dependahl
|
|
|
08/26/99 340 - BOB ###-#### MASONRY spec insp onsite
|
INSP - Concrete | 8/24/1999 | 8/24/1999 | 8/24/1999 | P | PART |
Tom Arcoraci
|
|
|
08/24/99 408 - spec insp on site
|
INSP - Framing/Rough-in | 8/23/1999 | 8/24/1999 | 8/24/1999 | A | PART |
Carl Dependahl
|
|
|
08/24/99 340 - bob ###-#### masonary insp; KLEINFELDER ONSITE, NEED AGRE
|
INSP - Foundation | 8/9/1999 | 8/9/1999 | 8/9/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - FND POURED; PENDING ENG'S OK. SUPT. NOTIFIED
|
INSP - Foundation | 7/28/1999 | 7/29/1999 | 7/29/1999 | A | PART |
Tom Arcoraci
|
|
|
07/29/99 408 - spec insp on site
|
INSP - Foundation | 7/27/1999 | 7/27/1999 | 7/27/1999 | P | PART |
Carl Dependahl
|
|
|
07/27/99 340 - int & isolated ftgs only; keep c/n re other fnd walls: ne
|
INSP - Framing/Rough-in | 7/27/1999 | 7/27/1999 | 7/27/1999 | P | CANC |
Carl Dependahl
|
|
|
07/27/99 340 - footing inspection curtis ###-####
|
INSP - Foundation | 7/23/1999 | 7/26/1999 | 7/27/1999 | P | FAIL |
Carl Dependahl
|
|
|
07/26/99 340 - CURTIS ###-####; poured w/o insp. c/n, need eng's ok. not
|
INSP - Foundation | 7/21/1999 | 7/22/1999 | 7/22/1999 | A | PART |
Carl Dependahl
|
|
|
07/22/99 340 - CURTIS ###-#### FOOTINGS. BEFORE 10 AM PLEASE. cn, ftgs o
|
(F) Reprint permit | | | 7/21/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/19/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/15/1999 | | |
|
|
|
|
Plan resubmittals received | | | 7/15/1999 | | PASS |
|
|
|
RECEIVED SECOND SET OF REVISED PLANS.
|
Print Occupancy Form | | | 7/15/1999 | | |
|
|
|
|
Plan resubmittals requested | | | 7/15/1999 | | PEND |
|
|
|
NOTIFIED BRYAN GILBREATH AT ZGA, BY VOICE MAIL, THAT I HAD ONLY RECEIVED ONE COPY OF THE PLAN REVISIONS AND THAT A SECOND COPY WOULD NEED TO BE SUBMITTED TO FINISH THE PERMIT FOR ISSUE.
|
Routing - PLAN CHECK | 6/28/1999 | | 7/15/1999 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 6/1/1999 | | 7/15/1999 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 7/14/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ZGA ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR 7/14/99
|
Plan resubmittals requested | | | 7/1/1999 | | PEND |
|
|
|
E-MAILED AND SNAIL-MAILED ALAN GILTZOW A COPY OF THE PRELIMINARY PLAN REVIEW COMMENT LIST REQUESTING REVISIONS.
|
Routing - PUBLIC WORKS | 6/25/1999 | | 6/25/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/24/1999 | | 6/25/1999 | | PASS |
|
|
|
Sent resubs to outside engineering via PDQ
|
Plan resubmittals received | | | 6/24/1999 | | PEND |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM ZGA, FORWARDED SAME TO JOHN MENARD. DAR 6/24/99
|
Routing - FIRE | 6/24/1999 | | 6/24/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 6/24/1999 | | |
|
|
|
|
Routing - FIRE | 6/14/1999 | | 6/22/1999 | | PASS |
|
|
|
FED EXED PLANS TO FLOYD FOR GRADING AND BLDG. 6-232-99 RECEIVED PLANS AND WRITTEN COMMENTS. FAXED TO ARCH. GAVE COPY OF COMMENTS TO BILL ALONG WITH THE ONE PLAN COPY. KMM
|
Plan resubmittals requested | | | 6/15/1999 | | PEND |
|
|
|
FAXED ALAN GILTZOW AT ZGA A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 6/1/1999 | | 6/15/1999 | | FAIL |
|
|
|
PLANS FORWDED TO CONSULTING ENGINEER VIA PDQ. DAR 6/1/99 SENT ONE SET OF PLANS, SOIS REPORT AND STRUCTURAL CACULATIONS. 06-15-99 RECEIVED REVIEW FROM CH2MHILL, ROUTED TO JOHN M.
|
Routing - PLANNING | 6/9/1999 | | 6/14/1999 | | PASS |
|
|
|
x-ref. DRH99-0043 & DRH99-0129
|
Routing - PLUMBING | 6/4/1999 | | 6/8/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/1/1999 | | 6/4/1999 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. DAR 6/04/99
|
Plan assigned to (MYS) | 5/28/1999 | | 6/1/1999 | | PASS |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | 6/1/1999 | | 6/1/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/28/1999 | | |
|
|
|
|
Application received | | | 5/28/1999 | | |
|
|
|
|