Permit Information
Permit NumberBLD99-01547
StatusFinaled
Name PEARSON LYLE N & MARTHA C AND
Site Address 7675 W GRATZ DR
Project NameLYLE PEARSON ACURA
Customer Number 
ePlanReviewNo
Description
LYLE PERASON ACURA * TO CONSTRUCT A NEW 9830 SQ. FT., TWO STORY AUTOMOBILE SALES AND SERVICE BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF CONCRETE SLAB FLOOR, MASONRY AND METAL WALLS AND STEEL FRAME. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. GRADING UNDER PERMIT BLD99-1546. PC#403-99/JCM & PC#403-99. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/19/20036/19/20036/19/2003 DONE
Receive PAYMENT IN FULL  4/17/2000 DONE
Fee Review-notes5/28/1999 3/30/2000 DONE
additional value from subs
(F) Reprint permit  3/30/2000 DONE
Permanent occupancy  1/25/2000 DONE
Perm. Occ. Cert. #8105 issued 1-25-00 to the lyle Pearson Acura Dealership.
BLD-Final1/24/20001/24/20001/24/2000PPASS
DetailsCarl Dependahl
bob ###-#### cn ok ok to sign for co 1/31/00 9:00:36 AM
Permanent Occupancy 1/24/20001/24/2000 DONE
Details
Permanent Occupancy 1/24/20001/24/2000 DONE
Details
FIRE-Final Inspection12/22/199912/22/199912/22/1999PPASS
DetailsJoe Tawney
Final, Bob ###-#### - Lyle Pearson Acura. Reinsp. ok for permanent occupancy.
Code Occupancy Approval  12/20/1999 PASS
Meets compliance with DRH99-00043/DRH99-00129
BLD-Conference11/30/199911/30/199911/30/1999APASS
DetailsCarl Dependahl
w/supt. keep C/N.
BLD-Final11/24/199911/29/199911/29/1999AFAIL
DetailsCarl Dependahl
BOB ###-####
Override - Parcel Holds  11/29/1999  
Temporary occupancy  11/29/1999 PART
Temp. Occ. Cert. #3948 issued 11-29-99 to Lyle Pearson Acura.
Override - Parcel Holds  11/29/1999  
BLD-Final11/24/199911/24/199911/24/1999PFAIL
DetailsCarl Dependahl
C/N; listed firestop/ Top-of-wall; hand rails ok for T/O.
FIRE-Final Inspection11/24/199911/24/199911/24/1999PPART
DetailsJoe Tawney
bob ###-#### Final ok for temp. occ. Rotate hydrant, provide approved exit sign.
Override - Parcel Holds  11/24/1999  
Override - Parcel Holds  11/24/1999  
Override - Parcel Holds  11/24/1999  
BLD-Other11/22/199911/23/199911/23/1999APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 11/22/1999 at 16:17:05. Contact: ###-####. Ceiling, ok; keep C/N.
FIRE-Conference11/22/199911/23/199911/23/1999APART
DetailsJoe Tawney
Bob ###-#### Conf. Pre-final.
Override - Parcel Holds  11/22/1999  
Override - Parcel Holds  11/22/1999  
BLD-Framing/Rough-in11/2/199911/2/199911/2/1999APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 11/02/1999 at 07:23:44. Contact: ###-####. Keep C/N
BLD-Framing/Rough-in10/29/199911/1/199911/1/1999AFAIL
DetailsCarl Dependahl
bob ###-#### C/N; ok to cover int. wall except as noted.
BLD-Conference10/25/199910/25/199910/25/1999APASS
DetailsCarl Dependahl
Met w/supt. re: spec. insp. req's
INSP - Concrete9/7/19999/8/19999/8/1999PPART
DetailsCarl Dependahl
greg ###-#### -grout pour --concrete; KLEINFELDER ONSITE, W.I.P.
INSP - Concrete9/7/19999/7/19999/7/1999PPART
DetailsCarl Dependahl
greg-- ###-#### masonary grout pour; 9/7 spec insp onsite, grouting. jrb
INSP - Concrete9/3/19999/3/19999/3/1999PPART
DetailsCarl Dependahl
09/03/99 340 - for concrete grout-greg ###-####; pend report
INSP - Concrete9/1/19999/2/19999/2/1999APART
DetailsTom Arcoraci
09/02/99 408 - spec insp
INSP - Concrete9/1/19999/1/19999/1/1999PPART
DetailsCarl Dependahl
09/01/99 340 - MASONRY GROUT POUR. GREGG ###-####; mti onsite
INSP - Concrete8/31/19998/31/19998/31/1999PPART
DetailsCarl Dependahl
08/31/99 340 - ###-####- greg-concrete-grout pour; KLEINFELDER ONSITE
INSP - Concrete8/30/19998/30/19998/30/1999PPART
DetailsCarl Dependahl
08/30/99 340 - GREG ###-#### MASONRY, GROUT WORK
INSP - Foundation8/26/19998/27/19998/27/1999PFAIL
DetailsCarl Dependahl
08/27/99 340 - MASONARY POUR GREG ###-####; nobody onsite?
INSP - Foundation8/26/19998/26/19998/26/1999PPART
DetailsCarl Dependahl
08/26/99 340 - THEY ARE POURING AT ONE PM GREG ###-####
INSP - Concrete8/24/19998/25/19998/25/1999APART
DetailsCarl Dependahl
08/26/99 340 - BOB ###-#### MASONRY spec insp onsite
INSP - Concrete8/24/19998/24/19998/24/1999PPART
DetailsTom Arcoraci
08/24/99 408 - spec insp on site
INSP - Framing/Rough-in8/23/19998/24/19998/24/1999APART
DetailsCarl Dependahl
08/24/99 340 - bob ###-#### masonary insp; KLEINFELDER ONSITE, NEED AGRE
INSP - Foundation8/9/19998/9/19998/9/1999 FAIL
DetailsCarl Dependahl
/ / 340 - FND POURED; PENDING ENG'S OK. SUPT. NOTIFIED
INSP - Foundation7/28/19997/29/19997/29/1999APART
DetailsTom Arcoraci
07/29/99 408 - spec insp on site
INSP - Foundation7/27/19997/27/19997/27/1999PPART
DetailsCarl Dependahl
07/27/99 340 - int & isolated ftgs only; keep c/n re other fnd walls: ne
INSP - Framing/Rough-in7/27/19997/27/19997/27/1999PCANC
DetailsCarl Dependahl
07/27/99 340 - footing inspection curtis ###-####
INSP - Foundation7/23/19997/26/19997/27/1999PFAIL
DetailsCarl Dependahl
07/26/99 340 - CURTIS ###-####; poured w/o insp. c/n, need eng's ok. not
INSP - Foundation7/21/19997/22/19997/22/1999APART
DetailsCarl Dependahl
07/22/99 340 - CURTIS ###-#### FOOTINGS. BEFORE 10 AM PLEASE. cn, ftgs o
(F) Reprint permit  7/21/1999
Issue PAID IN FULL permit  7/19/1999
PLANS/APPL TAKEN TO FRONT DESK  7/15/1999 PASS
Inspection Record Card- Bld  7/15/1999
Plan resubmittals received  7/15/1999 PASS
RECEIVED SECOND SET OF REVISED PLANS.
Print Occupancy Form  7/15/1999
Plan resubmittals requested  7/15/1999 PEND
NOTIFIED BRYAN GILBREATH AT ZGA, BY VOICE MAIL, THAT I HAD ONLY RECEIVED ONE COPY OF THE PLAN REVISIONS AND THAT A SECOND COPY WOULD NEED TO BE SUBMITTED TO FINISH THE PERMIT FOR ISSUE.
Routing - PLAN CHECK6/28/1999 7/15/1999 PASS
Plan assigned to (JCM)6/1/1999 7/15/1999 PASS
DetailsJohn Menard
Plan resubmittals received  7/14/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM ZGA ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR 7/14/99
Plan resubmittals requested  7/1/1999 PEND
E-MAILED AND SNAIL-MAILED ALAN GILTZOW A COPY OF THE PRELIMINARY PLAN REVIEW COMMENT LIST REQUESTING REVISIONS.
Routing - PUBLIC WORKS6/25/1999 6/25/1999 PASS
Routing Off Site - STRUCTURAL6/24/1999 6/25/1999 PASS
Sent resubs to outside engineering via PDQ
Plan resubmittals received  6/24/1999 PEND
PLAN RESUBMITTALS RECEIVED FROM ZGA, FORWARDED SAME TO JOHN MENARD. DAR 6/24/99
Routing - FIRE6/24/1999 6/24/1999 PASS
Plan Review Completed(1st rev)  6/24/1999
Routing - FIRE6/14/1999 6/22/1999 PASS
FED EXED PLANS TO FLOYD FOR GRADING AND BLDG. 6-232-99 RECEIVED PLANS AND WRITTEN COMMENTS. FAXED TO ARCH. GAVE COPY OF COMMENTS TO BILL ALONG WITH THE ONE PLAN COPY. KMM
Plan resubmittals requested  6/15/1999 PEND
FAXED ALAN GILTZOW AT ZGA A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
Routing Off Site - STRUCTURAL6/1/1999 6/15/1999 FAIL
PLANS FORWDED TO CONSULTING ENGINEER VIA PDQ. DAR 6/1/99 SENT ONE SET OF PLANS, SOIS REPORT AND STRUCTURAL CACULATIONS. 06-15-99 RECEIVED REVIEW FROM CH2MHILL, ROUTED TO JOHN M.
Routing - PLANNING6/9/1999 6/14/1999 PASS
x-ref. DRH99-0043 & DRH99-0129
Routing - PLUMBING6/4/1999 6/8/1999 PASS
Routing - PUBLIC WORKS6/1/1999 6/4/1999 FAIL
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. DAR 6/04/99
Plan assigned to (MYS)5/28/1999 6/1/1999 PASS
DetailsMarlene Southard
Plans ACCEPTED BY PLAN TECH6/1/1999 6/1/1999
Recd Pcfee & Taken To Pln CK  5/28/1999
Application received  5/28/1999