BLD-Final | 12/7/1999 | 12/7/1999 | 12/7/1999 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/07/1999 at 09:04:39. Contact: ###-####. C/C #17222, ok'd per Tim Hogland to final house w/o driveway (model home).
|
BLD-Energy code compliance | 9/21/1999 | 9/22/1999 | 9/22/1999 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/21/1999 at 17:40:56. Contact: ###-####. (add- framing insp.. Ok)
|
BLD-Framing/Rough-in | 9/22/1999 | 9/22/1999 | 9/22/1999 | A | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 9/20/1999 | 9/20/1999 | 9/20/1999 | P | FAIL |
Tom Arcoraci
|
|
|
GREG- ###-#### R/I INSP ok to insulate after F/P inspection
|
BLD-Framing/Rough-in | 9/16/1999 | 9/17/1999 | 9/17/1999 | P | FAIL |
Tom Arcoraci
|
|
|
No pcans or truss FNG
|
INSP - Framing/Rough-in | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PART |
Jim Sly
|
|
|
09/03/99 316 - Shear wall OK
|
INSP - Framing/Rough-in | 8/11/1999 | 8/11/1999 | 8/11/1999 | | PART |
Jim Sly
|
|
|
/ / 316 - STRAP NAILING ONLY...FOR SHEAR
|
INSP - Framing/Rough-in | 8/10/1999 | 8/11/1999 | 8/11/1999 | A | CANC |
Jim Sly
|
|
|
STRAP INSPECTION. GREG ###-####\\wants pm
|
INSP - Framing/Rough-in | 8/11/1999 | 8/11/1999 | 8/11/1999 | P | CANC |
Tom Arcoraci
|
|
|
08/11/99 408 - done by 316
|
INSP - Foundation | 7/7/1999 | 7/8/1999 | 7/8/1999 | A | PASS |
Jim Sly
|
|
|
07/08/99 316 -
|
INSP - Foundation | 7/8/1999 | 7/8/1999 | 7/8/1999 | | PASS |
Jim Sly
|
|
|
07/08/99 316 -
|
INSP - Foundation | 7/7/1999 | 7/7/1999 | 7/7/1999 | P | PART |
Jim Sly
|
|
|
07/07/99 316 - Soil, foot and rebar OK...Setbks appear OK per appr plan
|
INSP - Foundation | 7/6/1999 | 7/7/1999 | 7/6/1999 | A | CANC |
Jim Sly
|
|
|
DEAN - ###-#### FOOTINGS---CANCELLED BY DEAN
|
Issue PAID IN FULL permit | | | 6/22/1999 | | |
|
|
|
|
Plan assigned to (SAM) | 6/18/1999 | | 6/21/1999 | | PASS |
Steve Munroe
|
|
|
06/21/99 13:26:09 SAM - this action updated by action script from <<>> in Case No. BLD99-1684
|
Inspection Record Card- Bld | | | 6/21/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/21/1999 | | PEND |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/1999 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 6/10/1999 | | 6/18/1999 | | PEND |
Dan Overy
|
|
|
|
Routing - PUBLIC WORKS | 6/10/1999 | | 6/11/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 6/10/1999 | | 6/11/1999 | | PASS |
|
|
|
|
Application received | | | 6/10/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 6/11/1999 | | | | PEND |
|
|
|
|