Fee Review-notes | 6/11/1999 | | 3/21/2001 | | DONE |
|
|
|
LINDA THIS PERMIT WAS INITIALLY SUBMITTED UNDER BLD99-1352 WITH A PROJECT VALUE OF $500,000.00 DANA SEPRATED THE INITIAL PERMIT INTO THREE SEPRATE PERMITS. 1. PARKING LOT - NOPLAN CHECK FEE REQUIRED. 2.WAREHOUSE ADDITION. 3.T.I. IF YOU NEED TO SEE WHAT MONIES WERE PAID PLEASE LOOK AT BLD99-1352. THANK YOU DAVE RADFORD
|
FIRE-Final Inspection | 7/24/2000 | 7/26/2000 | 7/26/2000 | A | PASS |
Rick Jackson
|
|
|
gary ###-#### fn fire
|
BLD-Final | 7/24/2000 | 7/26/2000 | 7/26/2000 | P | PASS |
Jim Storey
|
|
|
###-####-- fn occ
|
Letter of compliance | | | 7/26/2000 | | DONE |
|
|
|
Letter of Compliance #18529 issued 7-26-00.
|
FIRE-Supply Line Hydro | 6/26/2000 | 6/26/2000 | 6/26/2000 | P | PASS |
Rick Jackson
|
|
|
terry ###-#### overhead sprinkler hydro okay 6/27/00 2:47:33 PM
|
FIRE-Sprinkler Rough-in | 6/26/2000 | 6/26/2000 | 6/26/2000 | P | PASS |
Rick Jackson
|
|
|
terry ###-#### air compressor replacement; alarm system not complete 6/27/00 2:48:01 PM
|
BLD-Framing/Rough-in | 6/22/2000 | 6/23/2000 | 6/23/2000 | A | CANC |
Jim Storey
|
|
|
###-#### n/r fire fail. 6/23/00 10:55:33 AM
|
FIRE-Hydro test above ground | 6/23/2000 | 6/23/2000 | 6/23/2000 | A | PART |
Joe Tawney
|
|
|
Flow test; Trip test WEL time 58 seconds with connect 1/2" onfile.
|
FIRE-Hydro test above ground | 6/22/2000 | 6/22/2000 | 6/22/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### System not pumped up to be rescheduled 6/23/00 11:23:01 AM
|
FIRE-Sprinkler Rough-in | 6/6/2000 | 6/7/2000 | 6/7/2000 | A | FAIL |
Rick Jackson
|
|
|
Mark Alexander ###-#### Hydro fail 6/13/00 3:21:47 PM
|
FIRE-Final Inspection | 4/25/2000 | 4/27/2000 | 4/27/2000 | A | FAIL |
Rick Jackson
|
|
|
###-#### Sprinklers not complete 4/28/00 9:02:27 AM
|
BLD-Wall cover | 2/16/2000 | 2/16/2000 | 2/16/2000 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/16/2000 at 10:47:45. Contact: ###-####. Need detail for metal beam and connections. 2/17/00 9:07:48 AM
|
BLD-Framing/Rough-in | 1/6/2000 | 1/7/2000 | 1/7/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/06/2000 at 15:33:38. Contact: ###-####. Ok to cover North West corner int. walls beam will need inspection.
|
BLD-Other | 12/13/1999 | 12/14/1999 | 12/14/1999 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 13:36:52. Contact: ###-####. Ceiling ok.
|
FIRE-Sprinkler Rough-in | 12/7/1999 | 12/7/1999 | 12/7/1999 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/07/1999 at 10:47:41. Contact: ###-####. Ok to cover new addition in warehouse only.
|
BLD-Framing/Rough-in | 11/9/1999 | 11/10/1999 | 11/12/1999 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/09/1999 at 15:23:27. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/29/1999 | 10/29/1999 | 10/29/1999 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/29/1999 at 10:47:00. Contact: ###-####. Ok for Gyp. Ceiling cover.
|
BLD-Conference | 10/25/1999 | 10/26/1999 | 10/26/1999 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/25/1999 at 14:04:44. Contact: ###-####. Provide 125 lbs./ft2 for BCI change on print.
|
BLD-Framing/Rough-in | 10/15/1999 | 10/18/1999 | 10/18/1999 | A | NR |
Jim Storey
|
|
|
ROD--- ###-#### REBAR Special inso. On site work in progress pending report
|
Issue PAID IN FULL permit | | | 10/8/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/5/1999 | | DONE |
|
|
|
dana ###-####
|
Routing - PLAN CHECK | 9/22/1999 | 9/22/1999 | 10/1/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/1999 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 6/17/1999 | | 10/1/1999 | | PASS |
|
|
|
10/1/1999 14:21:00 RMH - activity updated through activity BLDA022 from case BLD99-01688.
|
Routing - PLAN CHECK | 7/27/1999 | | 10/1/1999 | | PASS |
Ron Hill
|
|
|
|
Plan resubmittals received | | | 9/29/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A1,A3, A4, A4.1, A6, M1. ONE COPY OF CALCS. ROUTED TO RON HILL. KMM
|
Routing - FIRE | 9/22/1999 | 9/22/1999 | 9/22/1999 | | PASS |
|
|
|
Fire sprinkler system upgrade will be required for storage elevation and racking. Field inspectors should verify existing racking permit.
|
Plan Review Completed(1st rev) | | | 7/26/1999 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 7/22/1999 | | FAIL |
|
|
|
fAXED AND MAILED REQUIRED CORRECTIONS TO DANA, ON 7/21/99 AND FAXED REQUIRMENTS FOR ADDITONAL ENGINEEERING ON 7/22/99. WILL ROUTE TO FIRE DEPARTMENT.
|
Routing - PLAN CHECK | 6/21/1999 | | 7/22/1999 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 7/21/1999 | | |
|
|
|
ONE COPY OF STRUCTURAL CALCS. ROUTED TO RON H. KMM
|
Plan Reviewer's activity | | | 7/20/1999 | | |
|
|
|
called Dana and asked for the engineering.
|
Routing - FIRE | 7/22/1999 | | 6/26/1999 | | FAIL |
|
|
|
UFC exiting issues. UFC Storage Questions.
|
Routing - PUBLIC WORKS | 6/17/1999 | | 6/21/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 6/17/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Application received | | | 6/11/1999 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|