Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-01688
StatusFinaled
Name BOISE CASCADE CORP
Site Address 4300 S ENTERPRISE ST
Project NameBOISE CASCADE
Customer Number 
ePlanReviewNo
Description
To remodel the interior of this 35,000 sq.ft. existing office/warehouse facility, per approved plans on file. Work to include, remodel of the entire office area to create an open sales area, offices and waiting room, by removing numerous bearing and non bearing partitions, replacing bearing partitions with posts per engineering, create accessible restrooms, and to construct a 1952 sq ft one story addtion with a 1952 sq ft mezzanine above in the existing warehouse area. The floor level area will be used for breakroom and conference room the mezzanine to be used for storage and mechanical equipment. NOTE: This building is fully fire sprinklered for area increase. All modifications and alterations to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. NOTE: Building addition of warehouse to be constructed under BLD99-1352. (P.C.#361-99) *RMH*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/11/1999 3/21/2001 DONE
LINDA THIS PERMIT WAS INITIALLY SUBMITTED UNDER BLD99-1352 WITH A PROJECT VALUE OF $500,000.00 DANA SEPRATED THE INITIAL PERMIT INTO THREE SEPRATE PERMITS. 1. PARKING LOT - NOPLAN CHECK FEE REQUIRED. 2.WAREHOUSE ADDITION. 3.T.I. IF YOU NEED TO SEE WHAT MONIES WERE PAID PLEASE LOOK AT BLD99-1352. THANK YOU DAVE RADFORD
FIRE-Final Inspection7/24/20007/26/20007/26/2000APASS
DetailsRick Jackson
gary ###-#### fn fire
BLD-Final7/24/20007/26/20007/26/2000PPASS
DetailsJim Storey
###-####-- fn occ
Letter of compliance  7/26/2000 DONE
Letter of Compliance #18529 issued 7-26-00.
FIRE-Supply Line Hydro6/26/20006/26/20006/26/2000PPASS
DetailsRick Jackson
terry ###-#### overhead sprinkler hydro okay 6/27/00 2:47:33 PM
FIRE-Sprinkler Rough-in6/26/20006/26/20006/26/2000PPASS
DetailsRick Jackson
terry ###-#### air compressor replacement; alarm system not complete 6/27/00 2:48:01 PM
BLD-Framing/Rough-in6/22/20006/23/20006/23/2000ACANC
DetailsJim Storey
###-#### n/r fire fail. 6/23/00 10:55:33 AM
FIRE-Hydro test above ground6/23/20006/23/20006/23/2000APART
DetailsJoe Tawney
Flow test; Trip test WEL time 58 seconds with connect 1/2" onfile.
FIRE-Hydro test above ground6/22/20006/22/20006/22/2000PFAIL
DetailsRick Jackson
###-#### System not pumped up to be rescheduled 6/23/00 11:23:01 AM
FIRE-Sprinkler Rough-in6/6/20006/7/20006/7/2000AFAIL
DetailsRick Jackson
Mark Alexander ###-#### Hydro fail 6/13/00 3:21:47 PM
FIRE-Final Inspection4/25/20004/27/20004/27/2000AFAIL
DetailsRick Jackson
###-#### Sprinklers not complete 4/28/00 9:02:27 AM
BLD-Wall cover2/16/20002/16/20002/16/2000PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/16/2000 at 10:47:45. Contact: ###-####. Need detail for metal beam and connections. 2/17/00 9:07:48 AM
BLD-Framing/Rough-in1/6/20001/7/20001/7/2000APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/06/2000 at 15:33:38. Contact: ###-####. Ok to cover North West corner int. walls beam will need inspection.
BLD-Other12/13/199912/14/199912/14/1999APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/13/1999 at 13:36:52. Contact: ###-####. Ceiling ok.
FIRE-Sprinkler Rough-in12/7/199912/7/199912/7/1999PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/07/1999 at 10:47:41. Contact: ###-####. Ok to cover new addition in warehouse only.
BLD-Framing/Rough-in11/9/199911/10/199911/12/1999APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/09/1999 at 15:23:27. Contact: ###-####.
BLD-Framing/Rough-in10/29/199910/29/199910/29/1999PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/29/1999 at 10:47:00. Contact: ###-####. Ok for Gyp. Ceiling cover.
BLD-Conference10/25/199910/26/199910/26/1999PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/25/1999 at 14:04:44. Contact: ###-####. Provide 125 lbs./ft2 for BCI change on print.
BLD-Framing/Rough-in10/15/199910/18/199910/18/1999ANR
DetailsJim Storey
ROD--- ###-#### REBAR Special inso. On site work in progress pending report
Issue PAID IN FULL permit  10/8/1999 DONE
Print Occupancy Form  10/5/1999 DONE
Inspection Record Card- Bld  10/5/1999 DONE
Telephone call  10/5/1999 DONE
dana ###-####
Routing - PLAN CHECK9/22/19999/22/199910/1/1999 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/1/1999 PASS
DetailsRon Hill
Plan assigned to (R_H)6/17/1999 10/1/1999 PASS
Details
10/1/1999 14:21:00 RMH - activity updated through activity BLDA022 from case BLD99-01688.
Routing - PLAN CHECK7/27/1999 10/1/1999 PASS
DetailsRon Hill
Plan resubmittals received  9/29/1999 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A1,A3, A4, A4.1, A6, M1. ONE COPY OF CALCS. ROUTED TO RON HILL. KMM
Routing - FIRE9/22/19999/22/19999/22/1999 PASS
Fire sprinkler system upgrade will be required for storage elevation and racking. Field inspectors should verify existing racking permit.
Plan Review Completed(1st rev)  7/26/1999 FAIL
Plan Reviewer's activity  7/22/1999 FAIL
fAXED AND MAILED REQUIRED CORRECTIONS TO DANA, ON 7/21/99 AND FAXED REQUIRMENTS FOR ADDITONAL ENGINEEERING ON 7/22/99. WILL ROUTE TO FIRE DEPARTMENT.
Routing - PLAN CHECK6/21/1999 7/22/1999 FAIL
Plan resubmittals received  7/21/1999
ONE COPY OF STRUCTURAL CALCS. ROUTED TO RON H. KMM
Plan Reviewer's activity  7/20/1999
called Dana and asked for the engineering.
Routing - FIRE7/22/1999 6/26/1999 FAIL
UFC exiting issues. UFC Storage Questions.
Routing - PUBLIC WORKS6/17/1999 6/21/1999 PASS
Plan routing begun/TENANTS  6/17/1999
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Application received  6/11/1999
Case Summary (BLD)