Permanent occupancy | | | 12/27/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8519 issued 12-27-00 to the River Quarry Apts.
|
Permanent Occupancy | | 12/21/2000 | 12/21/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/20/2000 | 12/21/2000 | 12/21/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/20/2000 at 14:13:08. Contact: ###-####.
|
BLD-Final | 12/21/2000 | 12/21/2000 | 12/21/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/21/2000 at 08:46:34. Contact: ###-####.
|
Code Occupancy Approval | | | 12/21/2000 | | PASS |
|
|
|
ALL LANDSAPE IN AS REQUIRED, FINAL SIGNED OFF.
|
BLD-Energy code compliance | 8/15/2000 | 8/16/2000 | 8/16/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 13:01:00. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/15/2000 | 8/16/2000 | 8/16/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 13:02:04. Contact: ###-####. Scheduled by a 2hr wall and ceilling protction req.contractor via Hello! on 08/15/2000 at 13:02:04. Contact: ###-####. 8/16/2000 1:33:51 PM
|
Print Occupancy Form | | | 7/25/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/24/2000 | | DONE |
|
|
|
|
FIRE-Supply Line Cover | 12/3/1999 | 12/6/1999 | 12/6/1999 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/03/1999 at 14:25:23. Contact: ###-####.
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
Issue PAID IN FULL permit | | | 9/29/1999 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 9/28/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/28/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/28/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/1999 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 6/14/1999 | | 9/28/1999 | | PASS |
Mike Phillips
|
|
|
9/28/1999 15:26:10 M_P - activity updated through activity BLDA022 from case BLD99-01708.
|
Routing - FIRE | 9/17/1999 | 9/22/1999 | 9/22/1999 | | PASS |
|
|
|
Resubmittal
|
Plan Reviewer's activity | | | 9/17/1999 | | FAIL |
|
|
|
MODIFIED TO MEET BUILDING CODE REQUIREMENTS.
|
Print Pending Permit.LaserJet4 | | | 9/17/1999 | | FAIL |
|
|
|
BUILDING MODIFIED TO MEET CODE REEQUIREMENT ADDITIONAL INFORMATION REQUESTED FOR FURTHER REVIEW.
|
Routing - PLAN CHECK | | | 9/17/1999 | | PEND |
|
|
|
ROUTING TO FIRE
|
Routing - FIRE | 7/29/1999 | | 8/5/1999 | | FAIL |
|
|
|
UFC Issues, fire access, sprinkler system, alarm issues.
|
Plan Review Completed(1st rev) | | | 8/5/1999 | | FAIL |
|
|
|
|
Routing - PLUMBING | | | 7/26/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/16/1999 | | 7/19/1999 | | PASS |
|
|
|
|
Routing - PLANNING | | | 7/14/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/25/1999 | | |
|
|
|
RECEIVED WRITTEN RESPONSES TO REVIEW COMMENTS, ROUTED TO MIKE P.
|
Routing Off Site - STRUCTURAL | 6/7/1999 | | 6/21/1999 | | FAIL |
|
|
|
faxed structural comments to architect.
|
Application received | | | 6/10/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | | | |
|
|
|
|