Case Summary (BLD) | | | 4/1/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 3/31/2003 | | |
|
|
|
|
Print Occupancy Form | | | 7/24/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/20/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8299 issued 7-20-00 to the River Quarry Apts.
|
BLD-Final | 7/14/2000 | 7/14/2000 | 7/14/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 10:47:47. Contact: ###-####.
|
Code Occupancy Approval | | | 7/14/2000 | | PASS |
|
|
|
FINAL SIGNED OFF AS ALL CONDITIONS HAVE BEEN MET.
|
FIRE-Final Inspection | 7/11/2000 | 7/12/2000 | 7/13/2000 | A | PASS |
Rick Jackson
|
|
|
frank ###-####
|
Code Occupancy Approval | | | 7/6/2000 | | FAIL |
|
|
|
TEMPORARY OCCUPANCY SIGNED OFF AS LANDSCAPE NOT IN AS REQUIRED.
|
BLD-Framing/Rough-in | 2/3/2000 | 2/4/2000 | 2/4/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 15:58:52. Contact: ###-####. C/N on draftstop/fireplace flue clearance/wires at fire places fire stop. 2/4/00 11:57:52 AM
|
BLD-Framing/Rough-in | 2/1/2000 | 2/2/2000 | 2/2/2000 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/01/2000 at 15:57:24. Contact: ###-####.
|
BLD-Energy code compliance | 2/1/2000 | 2/2/2000 | 2/2/2000 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/01/2000 at 15:58:08. Contact: ###-####.
|
BLD-Other | 1/18/2000 | 1/19/2000 | 1/19/2000 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/18/2000 at 13:40:07. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/18/2000 | 1/19/2000 | 1/19/2000 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/18/2000 at 13:44:23. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/18/2000 | 1/18/2000 | 1/18/2000 | P | CANC |
Jim Storey
|
|
|
###-#### Called & canceled. 1/18/00 3:51:45 PM
|
FIRE-Sprinkler Rough-in | 12/29/1999 | 12/30/1999 | 12/30/1999 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 14:44:52. Contact: ###-####. Ok on sprinkler R/I.
|
BLD-Framing/Rough-in | 12/22/1999 | 12/23/1999 | 12/23/1999 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/22/1999 at 15:24:18. Contact: ###-####. Kitchen ceiling pre rock kitchen only ok.
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
FIRE-Supply Line Cover | 10/28/1999 | 10/28/1999 | 10/28/1999 | P | PASS |
Rick Jackson
|
|
|
Ok to cover
|
BLD-Foundation | 10/14/1999 | 10/14/1999 | 10/14/1999 | P | PART |
Tom Arcoraci
|
|
|
###-#### spec. inspection
|
Issue PAID IN FULL permit | | | 9/29/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/27/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/27/1999 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 9/24/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/24/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/24/1999 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 6/14/1999 | | 9/24/1999 | | PASS |
Mike Phillips
|
|
|
9/24/1999 13:26:16 M_P - activity updated through activity BLDA022 from case BLD99-01709.
|
Routing - FIRE | 9/17/1999 | 9/17/1999 | 9/22/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/17/1999 | | PEND |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/17/1999 | | PEND |
|
|
|
ROUTING TO FIRE.
|
Routing - PLAN CHECK | | | 9/17/1999 | | |
|
|
|
rOUTING TO FIRE DEPARTMENT
|
Routing - PLUMBING | | | 7/26/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/16/1999 | | 7/19/1999 | | PASS |
|
|
|
|
Routing - PLANNING | | | 7/14/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/25/1999 | | |
|
|
|
RECEIVED WRITTEN RESPONSES TO REVIEW COMMENTS. ROUTED TO MIKE P. KMM
|
Routing Off Site - STRUCTURAL | 6/7/1999 | | 6/21/1999 | | FAIL |
|
|
|
Faxed structural comment to architect.
|
Application received | | | 6/14/1999 | | |
|
|
|
|