Print Occupancy Form | | | 7/25/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 7/24/2000 | 7/24/2000 | | DONE |
|
|
|
|
BLD-Final | 7/21/2000 | 7/24/2000 | 7/24/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/21/2000 at 17:57:17. Contact: ###-####.
|
Permanent occupancy | | | 7/24/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8309 issued 7-26-00 to the River Quarry Apts.
|
Code Occupancy Approval | | | 7/17/2000 | | DONE |
|
|
|
FINAL SIGNED OFF AS ALL CONDITIONS HAVE BEEN MET.
|
BLD-Final | 7/14/2000 | 7/14/2000 | 7/14/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 07:56:19. Contact: ###-####. temp occ pending mech and perm hardware. 7/14/2000 3:47:58 PM
|
FIRE-Final Inspection | 7/11/2000 | 7/12/2000 | 7/13/2000 | A | PASS |
Rick Jackson
|
|
|
frank ###-#### rec room only; occupancy approved
|
BLD-Final | 7/10/2000 | 7/10/2000 | 7/10/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/10/2000 at 08:34:52. Contact: ###-####. thumb lock not allowd ada protection and signage mirror. 7/11/00 12:38:13 PM
|
Code Occupancy Approval | | | 7/6/2000 | | FAIL |
|
|
|
THIS PROJECT IS IN 3 PHASES, I WILL HOLD PHASE 3 AS HOSTAGE FOR ALL REQIREMENTS OF DR, I SIGNED OFF A TEMPORARY OCCUPANCY AS LANDSCAPE IN IN AS REQUIRED.
|
BLD-Energy code compliance | 4/6/2000 | 4/6/2000 | 4/6/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/06/2000 at 07:57:23. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/3/2000 | 4/3/2000 | 4/3/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/03/2000 at 07:20:00. Contact: ###-####.
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
|
FIRE-Conference | 11/9/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Footing | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | PART |
Tom Arcoraci
|
|
|
###-#### spec insp on site
|
(F) Reprint permit | | | 9/30/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/29/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/1999 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 9/27/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/27/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/27/1999 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 6/14/1999 | | 9/27/1999 | | PASS |
Mike Phillips
|
|
|
9/27/1999 09:47:01 M_P - activity updated through activity BLDA022 from case BLD99-01731.
|
Routing - FIRE | 9/17/1999 | 9/22/1999 | 9/22/1999 | | PASS |
|
|
|
Resubmittal
|
Routing - PLAN CHECK | | | 9/17/1999 | | PEND |
|
|
|
ROUTING TO FIRE.
|
Plan Review Completed(1st rev) | | | 8/5/1999 | | PASS |
|
|
|
|
Routing - FIRE | 7/29/1999 | | 8/5/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | | | 7/26/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/16/1999 | | 7/19/1999 | | PASS |
|
|
|
|
Routing - PLANNING | | | 7/14/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/25/1999 | | |
|
|
|
RECEIVED WRITTEN RESPONSES TO REVIEW COMMENTS. ROUTED TO MIKE P. KMM
|
Application received | | | 6/14/1999 | | |
|
|
|
|