BLD-Final | 3/7/2000 | 3/7/2000 | 3/7/2000 | P | PASS |
Russ Owen
|
|
|
###-####
|
BLD-Final | 3/2/2000 | 3/3/2000 | 3/3/2000 | P | FAIL |
Russ Owen
|
|
|
harvey ###-#### fn Fire caulk gas lines, set garage door, front step? 3/6/00 1:42:44 PM
|
BLD-Framing/Rough-in | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 13:53:25. Contact: . Ok to sheetrock.
|
FIRE-Final Inspection | 11/19/1999 | 11/22/1999 | 11/22/1999 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/19/1999 at 16:19:22. Contact: . Done by 407.
|
BLD-Framing/Rough-in | 11/22/1999 | 11/22/1999 | 11/22/1999 | A | PART |
Russ Owen
|
|
|
Still has (1) engineering correction posted.
|
BLD-Framing/Rough-in | 11/17/1999 | 11/17/1999 | 11/17/1999 | P | PART |
Russ Owen
|
|
|
STEVE ###-#### RE-INSP FR Ok to rock still has corrections which are posted on site.
|
BLD-Framing/Rough-in | 11/16/1999 | 11/16/1999 | 11/16/1999 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/16/1999 at 09:45:29. Contact: ###-####. Posted corrections.
|
BLD-Framing/Rough-in | 11/12/1999 | 11/15/1999 | 11/15/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 08:05:41. Contact: ###-####. No approved plans or trusses on site left notice posted.
|
BLD-Framing/Rough-in | 10/26/1999 | 10/27/1999 | 10/27/1999 | A | PART |
Jim Storey
|
|
|
exterior shear ###-#### Exterior shear ok
|
BLD-Conference | 10/18/1999 | 10/19/1999 | 10/21/1999 | A | NH |
Jim Storey
|
|
|
BRUCE ###-####
|
INSP - Foundation | 8/2/1999 | 8/3/1999 | 8/3/1999 | A | PASS |
Russ Owen
|
|
|
08/03/99 407 - note frost wall is required at garage doors opening per e
|
INSP - Foundation | 8/2/1999 | 8/2/1999 | 8/2/1999 | P | FAIL |
Russ Owen
|
|
|
08/02/99 407 - no approved plans .
|
INSP - Foundation | 7/27/1999 | 7/27/1999 | 7/27/1999 | P | PART |
Russ Owen
|
|
|
07/27/99 407 - ok subject to compaction report on garage footing.
|
Issue PAID IN FULL permit | | | 7/27/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/1999 | | |
|
|
|
|
Plan assigned to (SAM) | 7/13/1999 | | 7/26/1999 | | PASS |
Steve Munroe
|
|
|
07/26/99 16:23:06 SAM - this action updated by action script from <<>> in Case No. BLD99-1927
|
Print Pending Permit.LaserJet4 | | | 7/26/1999 | | PEND |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/13/1999 | | PEND |
|
|
|
Talked with John at Snyder Design. I informed him that I need additional engineering info. I need a letter from the engineer on the gyp. walls, how he is developing the lateral on the rear and calcs. for the great room wall. I called and talk to Harvey on 7/26 to let him know that I need another site plan to issue two set of plans. He told me to only issue one.
|
Plan assigned to (DJO) | 6/29/1999 | | 7/13/1999 | | PEND |
Dan Overy
|
|
|
|
Routing - PUBLIC WORKS | 6/29/1999 | | 7/1/1999 | | PASS |
|
|
|
|
Application received | | | 6/29/1999 | | |
|
|
|
|
Routing - PLANNING | 6/29/1999 | | 6/29/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/1/1999 | | | | PEND |
|
|
|
|