Plan resubmittals received | | | 7/10/2002 | | DONE |
|
|
|
RECIVED 3 COPIES OF A44.1 AND A4.1 ROUTED TO JOE TAWNEY.8/10/2000
|
Fee Review-notes | 7/8/1999 | | 4/25/2001 | | DONE |
|
|
|
|
BLD-Final | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 4/12/2001 9:29:21 AM
|
DOC - Permit Finaled | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PASS |
Tony Young
|
|
|
Added by Inspector: 415 On 4/12/2001 3:04:50 PM
|
BLD-Final | 4/11/2001 | 4/12/2001 | 4/12/2001 | A | CANC |
Tony Young
|
|
|
Joel Brown ###-####
|
Letter of compliance | | | 4/12/2001 | | DONE |
|
|
|
Letter of Compliance #21466 issued 4-12-01.
|
BLD-Final | 4/11/2001 | 4/11/2001 | 4/11/2001 | P | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 4/11/2001 5:49:57 PM REinsp Pass OK for certificate of completion
|
FIRE-Final Inspection | 4/10/2001 | 4/11/2001 | 4/11/2001 | A | CANC |
Joe Tawney
|
|
|
###-#### Cancel To be rescheduled 4/11/2001 8:21:13 AM
|
CHANGE STATUS TO (ISS) | | | 4/10/2001 | | DONE |
|
|
|
???? i don't know why this shows RDY
|
BLD-Framing/Rough-in | 2/13/2001 | 2/13/2001 | 2/13/2001 | P | PART |
Tony Young
|
|
|
###-####
foundation wall (not frame) for rear ramp 2/13/2001 4:02:53 PM
|
Override - Parcel Holds | | | 2/13/2001 | | |
|
|
|
|
BLD-Footing | 2/8/2001 | 2/8/2001 | 2/8/2001 | P | NR |
Tom Arcoraci
|
|
|
unable to find footing on site no phone number to call contractor 2/8/2001 4:52:40 PM 2/8/2001 5:02:10 PM 2/8/2001 5:03:13 PM
|
Override - Parcel Holds | | | 2/8/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/8/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/1/2001 | | |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 2/1/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/1/2001 | | |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 2/1/2001 | | DONE |
|
|
|
|
Routing - FIRE | 1/26/2001 | | 1/31/2001 | | PASS |
|
|
|
APPROVED WITHOUT COMMENTS
|
Case Summary (BLD) | | | 1/31/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2001 | | PASS |
Ron Hill
|
|
|
PLAN MODIFICATION COMPLETED AND APPROVED.
|
Telephone call | | | 1/31/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/31/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/31/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/31/2001 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 1/18/2001 | | 1/31/2001 | | PASS |
|
|
|
PLAN MODIFICATION, No corrections required, routed palns to fire department, Issuance of permit pending fire department approval.
|
Routing - PLAN CHECK | 1/18/2001 | | 1/31/2001 | | PASS |
Ron Hill
|
|
|
PLAN MODIFICATION
|
Plan Review Report | | | 1/26/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/26/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/25/2001 | | DONE |
|
|
|
PLAN MODIFICATION: Received two copies of revised sheets A2.3, & A2.4. Routed to Ron Hill. KMM
|
Plan routing begun/TENANTS | | | 1/18/2001 | | DONE |
|
|
|
PLAN MODIFICATION
|
Plan Modification Accepted | | | 1/18/2001 | | DONE |
|
|
|
PLAN MODIFICATION
|
CHANGE STATUS TO (PND) | | | 1/12/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/26/2000 | | DONE |
|
|
|
Received two copis of revised sheets A2.3 & A2.4 and four copies of cut sheets on the Secure Care access controls system. Routed to Joe Tawney per Ron Hill. KMM
1/18/01 These plans are being used in the Plan Modification of 1/18/01 KMM
|
BLD-Conference | 7/14/2000 | 7/14/2000 | 7/14/2000 | P | PART |
Joe Tawney
|
|
|
Conf. on alarm system with Sam Rogers, contr., & vendors.
|
FIRE-Final Inspection | 6/28/2000 | 6/30/2000 | 6/30/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 15:57:43. Contact: ###-####. reinsp alarm system administration area resubmittal requested 6/30/00 3:18:19 PM
|
FIRE-Final Inspection | 6/28/2000 | 6/29/2000 | 6/29/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 12:10:28. Contact: ###-####. reinsp not ready reschedule to 6/30/00 6/29/00 11:34:44 AM
|
FIRE-Final Inspection | 6/23/2000 | 6/26/2000 | 6/26/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/23/2000 at 15:40:12. Contact: ###-####. Reinsp. not ready wrong permit number. 6/26/00 2:57:38 PM
|
BLD-Final | 6/21/2000 | 6/22/2000 | 6/22/2000 | A | PART |
Bob Archibald
|
|
|
Scheduled by a contractor via Hello! on 06/21/2000 at 13:20:05. Contact: ###-####. Spray on fireproofing ok'd doors 210-a & 442 require cabels door 457 needs adjust. Needs fire approval. 6/22/00 11:20:29 AM
|
FIRE-Final Inspection | 6/22/2000 | 6/22/2000 | 6/22/2000 | P | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/22/2000 at 08:23:21. Contact: ###-####. Final fail C/N issued. 6/23/00 11:23:57 AM
|
BLD-Framing/Rough-in | 6/1/2000 | 6/1/2000 | 6/1/2000 | A | PASS |
Wes Worcester
|
|
|
Kitchen area ok for cover. also approved spray-on fireproofing detail for floor joists.
|
FIRE-Alarm Testing | 5/25/2000 | 5/30/2000 | 5/30/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/25/2000 at 15:00:01. Contact: ###-####. Ok on alarm test phase 1 5/30/00 3:44:13 PM
|
BLD-Framing/Rough-in | 5/24/2000 | 5/25/2000 | 5/25/2000 | A | CANC |
|
|
|
Scheduled by a contractor via Hello! on 05/24/2000 at 14:02:08. Contact: ###-####. out of time 5/30/00 6:35:37 AM
|
FIRE-Alarm Testing | 5/24/2000 | 5/25/2000 | 5/25/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/24/2000 at 14:46:08. Contact: ###-####. Conf. on fire alarm system 5/25/00 1:39:18 PM
|
FIRE-Alarm Testing | 5/15/2000 | 5/16/2000 | 5/16/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/15/2000 at 14:08:10. Contact: ###-####. Fail approved plans not on site corrections required. 5/16/00 1:17:47 PM
|
BLD-Framing/Rough-in | 5/4/2000 | 5/5/2000 | 5/5/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/04/2000 at 15:44:36. Contact: ###-####. storege rm bath 2 hr wall ok. 5/5/00 1:09:54 PM
|
FIRE-Final Inspection | 4/19/2000 | 4/25/2000 | 4/24/2000 | A | CANC |
Joe Tawney
|
|
|
###-#### Disp set to [CANC] by a contractor via Hello! on 04/24/2000 at 15:43:24.
|
FIRE-Conference | 4/19/2000 | 4/21/2000 | 4/21/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 16:16:52. Contact: . Conf. with elect contractor about alarm system. 4/26/00 11:13:38 AM
|
BLD-Framing/Rough-in | 4/13/2000 | 4/13/2000 | 4/13/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/13/2000 at 09:25:13. Contact: . area 3# ok for celling drop. 4/13/00
|
FIRE-Conference | 4/7/2000 | 4/10/2000 | 4/10/2000 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/07/2000 at 14:03:11. Contact: . Rorner electric wanted to review door release requirements 4/11/00 11:20:33 AM
|
BLD-Framing/Rough-in | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/21/2000 at 18:22:04. Contact: . Looked at some frame work under floor. 3/22/00 1:43:49 PM
|
BLD-Framing/Rough-in | 3/21/2000 | 3/21/2000 | 3/21/2000 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/21/2000 at 08:05:48. Contact: .
|
BLD-Framing/Rough-in | 3/17/2000 | 3/20/2000 | 3/20/2000 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/17/2000 at 16:10:28. Contact: . Not ready 3/21/00 9:31:43 AM
|
BLD-Framing/Rough-in | 3/15/2000 | 3/16/2000 | 3/16/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/15/2000 at 15:16:20. Contact: . Part of 2hr wall behind kitchen 3/16/00 2:28:09 PM
|
FIRE-Conference | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 13:50:52. Contact: . Wanted to discuss location of backflow preventers- see plans. 3/14/00 1:56:21 PM
|
BLD-Framing/Rough-in | 3/9/2000 | 3/10/2000 | 3/10/2000 | A | FAIL |
Russ Owen
|
|
|
###-#### Exterior wall 2hr area separation, need detail for eaves running parallel. 3/14/00 11:56:07 AM
|
CHANGE STATUS TO (I) | | | 3/9/2000 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/6/2000 | 3/6/2000 | 3/6/2000 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/06/2000 at 09:58:06. Contact: . Ceiling at mechancial bldg. 3/7/00 1:41:42 PM
|
Receive PAYMENT IN FULL | | | 3/2/2000 | | DONE |
|
|
|
recieved money for resubmittals/plan modification
|
Telephone call | | | 2/25/2000 | | DONE |
|
|
|
talked to jackie gave dollar amount
|
Plan assigned to (R_H) | 2/8/2000 | | 2/25/2000 | | PASS |
|
|
|
3/9/2000 14:26:27 RMH - activity updated through activity BLDA022 from case BLD99-02051.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2000 | | PASS |
Ron Hill
|
|
|
Plan modification.
|
BLD-Framing/Rough-in | 2/23/2000 | 2/24/2000 | 2/24/2000 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/23/2000 at 14:35:19. Contact: . Approved 2hr wall in rm#458 and in cafeteria across from risk management office.
|
BLD-Framing/Rough-in | 2/17/2000 | 2/18/2000 | 2/18/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/17/2000 at 14:45:37. Contact: . Interior side, of a section of 2hr wall. 2/18/00 3:34:44 PM
|
Routing - PLAN CHECK | 2/15/2000 | | 2/15/2000 | | DONE |
|
|
|
PLAN MODIFICATION
|
Routing - FIRE | 2/10/2000 | 2/15/2000 | 2/15/2000 | | PASS |
Bill Alexander
|
|
|
PLAN MODIFICATION
|
Plan Review Completed(1st rev) | | | 2/15/2000 | | PASS |
|
|
|
PLAN MODIFICATION
|
BLD-Framing/Rough-in | 2/10/2000 | 2/11/2000 | 2/11/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 13:03:41. Contact: . Interior walls only of. 2/14/00 2:06:27 PM
|
Routing - PLAN CHECK | 2/9/2000 | | 2/10/2000 | | PEND |
Ron Hill
|
|
|
PLAN MODIFICATION Plan modification approved. Route to fire department.
|
Routing - PUBLIC WORKS | 2/8/2000 | | 2/9/2000 | | PASS |
|
|
|
PLAN MODIFICATION
|
Plan Modification Accepted | | | 2/8/2000 | | PEND |
|
|
|
|
BLD-Framing/Rough-in | 1/31/2000 | 2/1/2000 | 2/1/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/31/2000 at 16:36:21. Contact: . 2 hr wall in coridoor 221 opposite nurses station 203 ok for cover 2/1/00 2:05:52 PM
|
BLD-Framing/Rough-in | 1/27/2000 | 1/27/2000 | 1/27/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 07:26:39. Contact: . made pk 2/14/00 10:47:52 AM
|
BLD-Framing/Rough-in | 1/25/2000 | 1/25/2000 | 1/25/2000 | P | PART |
Wes Worcester
|
|
|
joel ###-#### Corridor (sic) on saving @ nurse's station grid ceiling & penetrations ok. 2 hr. wall in bathroom #812 & corridors at both 2 hr wall locations covered 801 & 807 1 hr construction ok. Architect details for 2hr area sep wall nor seedy document on site. 1/26/00 2:21:53 PM
|
BLD-Framing/Rough-in | 1/20/2000 | 1/20/2000 | 1/20/2000 | P | PART |
Bob Archibald
|
|
|
Verified 2hr wall construction at rooms 227,228,226,225. 4" penetration requires fire assembly. Also verified 2hr wall costruction in room 812, 2hr wall in bathroom of this room not complete. Coridoors at both 2hr wall locations require reinspection on penetrations.
|
BLD-Framing/Rough-in | 1/13/2000 | 1/13/2000 | 1/13/2000 | A | PART |
Wes Worcester
|
|
|
Conference on 2hr occ. sep. wall. Wall to be constructed as per architects detail or Paul Seedy document detail. Ceiling and bearing wall to be maintained as 1hr construction. 2nd layer of rock on 2hr wall ok.
|
BLD-Framing/Rough-in | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | FAIL |
Wes Worcester
|
|
|
###-#### joel. 2hr. Area separation wall is incorrect and not to UL listed installation criteria.
|
FIRE-Sprinkler Rough-in | 12/27/1999 | 12/27/1999 | 12/28/1999 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 08:24:44. Contact: . Ok on spklr. R/I of one corridor area in Alzheimer wing.
|
BLD-Framing/Rough-in | 12/22/1999 | 12/23/1999 | 12/23/1999 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/22/1999 at 13:34:19. Contact: . Trans. to 301.
|
BLD-Framing/Rough-in | 12/15/1999 | 12/16/1999 | 12/16/1999 | A | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 15:31:24. Contact: ###-####. 2hr wall incorrect.
|
BLD-Framing/Rough-in | 12/2/1999 | 12/3/1999 | 12/6/1999 | P | PART |
Jim Storey
|
|
|
JOEL ###-#### Membrane has to butt to ceiling membrane per code exception.
|
BLD-Framing/Rough-in | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PART |
Wes Worcester
|
|
|
joel ###-#### fr Double layer ok @ 2hr wall @ ceiling.
|
BLD-Framing/Rough-in | 10/28/1999 | 10/29/1999 | 10/29/1999 | A | PART |
Wes Worcester
|
|
|
joe--- ###-#### fr insp 2 hr walls @ group room ok
|
FIRE-Sprinkler Rough-in | 10/20/1999 | 10/21/1999 | 10/21/1999 | A | PART |
Joe Tawney
|
|
|
joel ###-#### Reached agreement on location of smoke detectors in relation to air supply grills.
|
BLD-Framing/Rough-in | 10/18/1999 | 10/18/1999 | 10/18/1999 | P | FAIL |
Wes Worcester
|
|
|
joel ###-#### 1hr const. Not to plan ck notes, not to 1hr constr. Criteria
|
BLD-Framing/Rough-in | 10/7/1999 | 10/8/1999 | 10/8/1999 | A | PART |
Wes Worcester
|
|
|
joel ###-#### no one there
|
(F) Reprint permit | | | 9/10/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/9/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/7/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/3/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/1999 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 7/14/1999 | | 9/3/1999 | | PASS |
|
|
|
09/03/99 09:23:19 RMH - this action updated by action script from <<>> in Case No. BLD99-2051
|
Routing - PLAN CHECK | 8/16/1999 | | 9/3/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/31/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED DRAWINGS SHEETS, A4.1, A4.2, A5.2, A6.2, A7.1, A8.1, A8.2, A9.1, A9.2, M1.1B, M1.1A, FP1.0, PLUS ONE COPY OF RESPONSE TO PLAN CHECK REPORT. ROUTED TO RON H. KMM
|
Routing - FIRE | 8/10/1999 | | 8/13/1999 | | PASS |
|
|
|
FED EXED OFFICE COPY TO FLOYD. ROUTED ISSUE COPY TO BILL A. KMM RECIEVED REVIEW (E.M.) 08/13/99 JWA. 8-16-99 RECEIVED OFFICE COPY OF PLANS BACK FROM FLOYD AND ROUTED TO BILL A. KMM
|
Plan Review Completed(1st rev) | | | 8/13/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 7/14/1999 | | 8/6/1999 | | FAIL |
|
|
|
ROUTE TO FIRE DEPARTMENT.
|
Plan Reviewer's activity | | | 8/6/1999 | | FAIL |
|
|
|
fAXED AND MAILED REQUIREMENTS TO STEVE PAVLICK, ARCHITECT.
|
Plan assigned to (MYS) | 7/8/1999 | | 7/14/1999 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 7/14/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Routing - PUBLIC WORKS | 7/8/1999 | | 7/13/1999 | | PASS |
|
|
|
|
Application received | | | 7/8/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/8/1999 | | PEND |
|
|
|
|