BLD-Final | 1/21/2000 | 1/21/2000 | 1/21/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 01/21/2000 at 07:49:04. Contact: . glazing on stair landing c/n issued 1/24/00 8:05:28 AM
|
BLD-Energy code compliance | 10/4/1999 | 10/5/1999 | 10/5/1999 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 14:58:05. Contact: ###-####. Ok except truss company is replacing a bottom cord of the truss reinsp required
|
BLD-Framing/Rough-in | 9/30/1999 | 10/1/1999 | 10/1/1999 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/30/1999 at 08:50:45. Contact: ###-####.
|
BLD-Wall cover | 9/15/1999 | 9/16/1999 | 9/16/1999 | A | PASS |
Russ Owen
|
|
|
|
Issue PAID IN FULL permit | | | 7/29/1999 | | |
|
|
|
|
INSP - Foundation | 7/28/1999 | 7/28/1999 | 7/28/1999 | P | PASS |
Russ Owen
|
|
|
walls.
|
Inspection Record Card- Bld | | | 7/21/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/20/1999 | | PEND |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/1999 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 7/19/1999 | | 7/20/1999 | | PASS |
Steve Munroe
|
|
|
07/20/99 15:46:12 SAM - this action updated by action script from <<>> in Case No. BLD99-2071
|
Plan assigned to (DJO) | 7/12/1999 | | 7/19/1999 | | PEND |
Dan Overy
|
|
|
|
Application received | | | 7/12/1999 | | |
|
|
|
|
Routing - PLANNING | 7/12/1999 | | 7/12/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/12/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 7/12/1999 | | | | PEND |
|
|
|
|