BLD-Final | 3/27/2000 | 3/27/2000 | 3/27/2000 | P | PASS |
Wes Worcester
|
|
|
###-#### C/C #18475 issued. 3/28/00 9:06:23 AM
|
BLD-Grading Inspection | 3/27/2000 | 3/27/2000 | 3/27/2000 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete. Revegetation is not complete. Roof gutters have not been installed. Roof drain connection to stubout has been verified and is correct. Engineer has approved grading and recommended a $400.00 bond for reveg and a $500.00 bond for roof gutters. This has been submitted and the grading is conditionally approved pending completion of the reveg and roof gutters.
|
BLD-Final | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 08:17:45. Contact: ###-####. Not ready- previous C/N not done- guard rails not installed- public works bond not posted etc. 3/27/00 9:58:27 AM
|
BLD-Final | 3/15/2000 | 3/16/2000 | 3/16/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-#### eric C/N 3/17/00 10:25:43 AM
|
BLD-Final | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 11:29:44. Contact: ###-####. Not ready. 3/16/00 11:28:48 AM
|
BLD-Framing/Rough-in | 1/19/2000 | 1/20/2000 | 1/20/2000 | A | CANC |
Wes Worcester
|
|
|
2###-#### John
|
BLD-Framing/Rough-in | 1/18/2000 | 1/18/2000 | 1/18/2000 | P | PART |
|
|
|
###-#### made ok to insulate c/n issued 1/18/00 4:53:52 PM
|
Telephone call | | | 1/18/2000 | | DONE |
|
|
|
called Seidl Homes number changed for the new set of plans on site. new number ###-####
|
BLD-Framing/Rough-in | 1/11/2000 | 1/11/2000 | 1/11/2000 | P | FAIL |
Russ Owen
|
|
|
john ###-#### fr insp. No approved plans, hold-downs mislocated.
|
BLD-Framing/Rough-in | 1/6/2000 | 1/6/2000 | 1/6/2000 | P | NR |
Russ Owen
|
|
|
john-- ###-#### for shear wall No approved plans on site, called builder.
|
BLD-Framing/Rough-in | 12/22/1999 | 12/23/1999 | 12/23/1999 | A | NR |
Russ Owen
|
|
|
John ###-####. Told framer to recall.
|
BLD-Foundation | 10/13/1999 | 10/13/1999 | 10/13/1999 | P | CANC |
Russ Owen
|
|
|
dan ###-#### Not required non structural and no detail on plans
|
BLD-Footing | 10/12/1999 | 10/12/1999 | 10/12/1999 | P | PART |
Russ Owen
|
|
|
###-####--danny for ft insp Footing at interior garage and front porch, ok rebar in place not required by plan.
|
BLD-Foundation | 9/27/1999 | 9/28/1999 | 9/28/1999 | P | PASS |
Russ Owen
|
|
|
DAN-- ###-#### FOUND WALL INSP Foundation walls
|
INSP - Foundation | 9/14/1999 | 9/15/1999 | 9/15/1999 | A | PASS |
Wes Worcester
|
|
|
PLACING AN ADDITIONAL (5) VERTICAL #8'S
|
Issue PAID IN FULL permit | | | 9/14/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/24/1999 | | |
|
|
|
|
CHANGE STATUS TO (R) | | | 8/24/1999 | | |
|
|
|
Dan forgot to change the status.
|
Plan assigned to (DJO) | 7/13/1999 | | 8/24/1999 | | PASS |
Dan Overy
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/16/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/13/1999 | | PASS |
|
|
|
REVISED PLANS SUBMITTED. STILL NEED CONCRETE COLUMN DETAIL, STRAP VERIFICATION AND BEAM CALCULATION.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/5/1999 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 8/5/1999 | | PEND |
|
|
|
STAMPED ENGINEERED RED-LINE SHEETS AND CALCULATIONS NEEDED FOR LATERAL BRACING, HOLDOWNS, AND CONCRETE PIER AND FOOTING.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/3/1999 | | PEND |
|
|
|
|
Routing - PLANNING | 7/22/1999 | | 7/23/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/13/1999 | | 7/21/1999 | | PASS |
|
|
|
took to terry records 7/13/99/pe
|
Routing - PUBLIC WORKS GRADING | 7/21/1999 | | 7/21/1999 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3. Wrote letter to contractor requiring confirmation from soils engineer that expansive clay that was identified in soils report will not affect foundation
|
Application received | | | 7/13/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 7/23/1999 | | | | PEND |
|
|
|
|