Fee Review-notes | 7/20/1999 | | 6/20/2000 | | DONE |
|
|
|
|
BLD-Final | 6/15/2000 | 6/15/2000 | 6/15/2000 | P | PASS |
|
|
|
Added by Inspector: 338 On 6/15/00 made ok for letter
|
Letter of compliance | | | 6/15/2000 | | DONE |
|
|
|
Letter of Compliance #18516 issued 6-15-00.
|
BLD-Final | 3/23/2000 | 3/24/2000 | 3/24/2000 | P | PART |
|
|
|
###-#### signed the temp col 03/27/2000 6:47:56 AM
|
Temporary occupancy | | | 3/24/2000 | | PART |
|
|
|
Temp. Occ. Cert. #3998 issued 3-24-00 to McDonald's Chevron.
|
FIRE-Final Inspection | 3/22/2000 | 3/23/2000 | 3/23/2000 | P | PASS |
Rick Jackson
|
|
|
###-#### Rod
|
Print Occupancy Form | | | 3/23/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/23/2000 | | DONE |
|
|
|
|
BLD-Footing | 11/8/1999 | 11/9/1999 | 11/9/1999 | P | PART |
|
|
|
Rod ###-#### ready at 2:30 they will pour at 3:30 Ok to pour brace frame area and canopy pads.
|
Issue PAID IN FULL permit | | | 9/22/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/20/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/20/1999 | | DONE |
|
|
|
|
Telephone call | | | 9/20/1999 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (MLO) | 7/22/1999 | | 9/20/1999 | | PASS |
Mike Otto
|
|
|
9/20/1999 09:15:44 MLO - activity updated through activity BLDA022 from case BLD99-02183.
|
Routing - PLANNING | 9/14/1999 | 9/14/1999 | 9/17/1999 | | PASS |
|
|
|
approved per DRH99-0038, and as noted on lighting cut-sheets.
|
Plan resubmittals received | | | 9/14/1999 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/14/1999 | | 9/14/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/20/1999 | | 9/1/1999 | | PASS |
|
|
|
RECEIVED A STRUCTURAL REVIEW LETTER BY OUT SIDE ENG. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 8/26/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED ASSEMBLY PERSPECTIVE - OVERHANG RISE SHEET, AND ONE COPY OF WRITTEN RESPNSE. ROUTED TO MIKE O. KMM
|
Plan resubmittals requested | | | 8/20/1999 | | FAIL |
|
|
|
STRUCTRUAL CORRECTIONS AND SITE PLAN REQUIREMENTS MAILED AND FAXED TO STEVE EDDY. 8-20-99 MLO
|
Plan resubmittals received | | | 8/19/1999 | | |
|
|
|
RECEIVED FOUR COPIES OF SIGNED AND SEALED PRINTS. ONE COPY OF STRUCTURAL CALCS. ONE RESPONSE LETTER. ROUTED TO MIKE O. KMM
|
Routing - PLAN CHECK | 8/17/1999 | | 8/19/1999 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/10/1999 | | 8/17/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE REVISED SHEETS RECEIVED 8-10-99, TO OUTSIDE ENG. KMM
|
Plan resubmittals received | | | 8/10/1999 | | |
|
|
|
8-10-99 RECEIVED REVISED CERT. OF VALUE ROUTED TWO TO MIKE AND ONE IN FILE. TWO COPIES OF SHEETS C-1, AND C3.1 THREE COPIES OF REVISED SHEETS 1 (ANCHOR BOLT) AND 2 (FRAMING PLAN) THREE COPIES OF STRUCT. CALCS. AND LSI INFORMATION, AND LIGHTING SHEET. ROUTED TO MIKE O. AND SENT ONE COPY WITHOUT SITE PLAN TO OUTSIDE ENG. KMM
|
Telephone call | | | 8/4/1999 | | PEND |
|
|
|
RECEIVED CALL FROM LOY TAYLOR AND GEORGE BAKER OF MCDONALDS REGARDING FREEZER\COOLERS. A CHANGE WILL BE MADE AND MORE PLANS WILL BE SUBMITTED. STRUCTURAL CORRECTIONS ARE BEING WORKED ON BY THEIR ENGINEER AND WILL BE SUBMITTED WHEN COMPLETED. MLO
|
Telephone call | | | 7/30/1999 | | |
|
|
|
HAD CALL FROM ENGINEER ON CANOPY REGARDING ROOF OVERFLOW REQURIEMENTS. FAXED COPY OF UBC SEC. 1506 TO ENGINEER. MLO
|
Plan Review Completed(1st rev) | | | 7/29/1999 | | |
|
|
|
|
Plan resubmittals requested | | | 7/29/1999 | | FAIL |
|
|
|
NON-STRUCTURAL REVIEW CORRECTIONS FAXED AND MAILED TO STEVE EDDY. MLO
|
Routing - FIRE | 7/29/1999 | | 7/29/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/27/1999 | | 7/28/1999 | | FAIL |
|
|
|
|
Routing - PLANNING | 7/27/1999 | | 7/27/1999 | | PEND |
|
|
|
revised plans which comply with DRH99-0038 conditions of approval have not been addressed. See letter in DRH99-0038 file.
|
Routing - PUBLIC WORKS | 7/23/1999 | | 7/26/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 7/20/1999 | | 7/23/1999 | | |
Marlene Southard
|
|
|
He said that Mike Otto told him to resubmit for the canopy... THANKS!
|
Plans ACCEPTED BY PLAN TECH | | | 7/23/1999 | | PASS |
|
|
|
RECEIVED SITE PLAN, AM READY TO ROUTE. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 7/21/1999 | | PEND |
|
|
|
REQUIRES SITE PLAN. CONTACTED CHRIS CORLETT OF THIS NEED. I WILL ROUTE TO OUTSIDE ENG. BUT HOLD FOR INHOUSE ROUTING UNTIL I RECEIVE SITE PLAN. KMM
|
Application received | | | 7/20/1999 | | |
|
|
|
|
Received Certificate of Value | | | 7/20/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/22/1999 | | 7/6/1999 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan routing begun/NEW & ADDTN | 7/22/1999 | | | | |
|
|
|
WILL START INHOUSE ROUTING WHEN I RECEIVE SITE PLAN. KMM
|