Inspection Record Card- Bld | | | 10/10/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/28/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/23/2001 | | DONE |
|
|
|
|
Fee Review-notes | 7/21/1999 | | 4/11/2001 | | DONE |
|
|
|
4/10 called GC for cert will fax
|
Fee Review-notes | 10/28/1999 | 10/28/1999 | 3/21/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/27/2001 | | |
|
|
|
|
BLD-Final | 2/16/2001 | 2/20/2001 | 2/20/2001 | A | PASS |
Jim Storey
|
|
|
###-####
|
Permanent Occupancy | | 2/20/2001 | 2/20/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/20/2001 | | |
|
|
|
|
Permanent occupancy | | | 2/20/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8576 issued 2-20-01 to Fred Meyer.
|
Code Occupancy Approval | | | 2/20/2001 | | PASS |
|
|
|
ALL CONDITIONS IN THE BUILDING AREA ARE COMPLETE, FINAL OCCUPANCY SIGNED OFF.
|
BLD-Final | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | FAIL |
Jim Storey
|
|
|
###-#### wes fn occ c/n door smoke seal/hardware/closers/fire stopping in machenry rm. 2/20/2001 8:45:44 AM
|
Override - Parcel Holds | | | 2/16/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/16/2001 | | |
|
|
|
|
FIRE-Final Inspection | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/15/2001 4:07:49 PM
|
Override - Parcel Holds | | | 2/15/2001 | | |
|
|
|
|
Issue & PRINT permit | | | 2/15/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/14/2001 | | 2/14/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2001 | | PASS |
|
|
|
|
Telephone call | | | 2/14/2001 | | DONE |
|
|
|
talked to john to verify plans are ready
|
Routing - FIRE | 2/9/2001 | | 2/14/2001 | | PASS |
|
|
|
Plan modification for Starbucks. Approved with no comments.
|
Plan assigned to (JCM) | 2/6/2001 | | 2/14/2001 | | PASS |
John Menard
|
|
|
2/14/01 13:27:23 JCM - activity updated through activity BLDA022 from case BLD99-02185.
|
FIRE-Final Inspection | 2/8/2001 | 2/12/2001 | 2/12/2001 | A | FAIL |
Rick Jackson
|
|
|
Jon Small ###-#### need balance report for hood system and exit sign above personnel door by MPU overhead door per plans 2/12/2001 3:23:42 PM
|
BLD-Final | 2/8/2001 | 2/12/2001 | 2/12/2001 | P | NR |
Jim Storey
|
|
|
###-#### John
|
Override - Parcel Holds | | | 2/12/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/12/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/12/2001 | | |
|
|
|
|
Code Occupancy Approval | | | 2/12/2001 | | FAIL |
|
|
|
received request for occupancy 2-8-01, made meeting for 10:00 am monday 2-12-01, site inspection showed some items not completed so I only signed Temp. Occupancy till all done.
While making this entry I found a parcel Hold in effect, I'm not sure what is reason but will check with Jim Storey.
|
Plan Reviewer's activity | | | 2/9/2001 | | PASS |
|
|
|
Plan modification for the Starbucks Coffee bar area has been reviewed and approved as submitted. JCM
|
Routing - PLAN CHECK | 2/8/2001 | | 2/9/2001 | | PASS |
|
|
|
Plan Modification for the Starbucks. KMM
|
Override - Parcel Holds | | | 2/8/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 2/8/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/6/2001 | | 2/8/2001 | | PASS |
|
|
|
Plan Modification for the Starbucks. KMM
|
Routing - PLUMBING | 2/8/2001 | | 2/8/2001 | | PASS |
|
|
|
Plan Modification for the Starbucks. KMM floor sinks and indirect waste receptors must be in full view at all times., additional cross connection protection may be required.
|
Override - Parcel Holds | | | 2/8/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2001 | | DONE |
|
|
|
Plan modification for the Starbucks. KMM
|
Plan routing begun/TENANTS | | | 2/6/2001 | | DONE |
|
|
|
Plan Modification for the starbucks. KMM
|
CHANGE STATUS TO (PND) | | | 2/5/2001 | | DONE |
|
|
|
plan mod received/mls
|
CHANGE STATUS TO (PND) | | | 2/2/2001 | | DONE |
|
|
|
collected $500 plan modification fee and resubmittals for the plan modification...
|
CHANGE STATUS TO (ISS) | | | 2/2/2001 | | DONE |
|
|
|
decided that he couldn't do a plan modification as of yet...
|
FIRE-Alarm Testing | 1/25/2001 | 1/26/2001 | 1/26/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/25/2001 at 10:02:31. Contact: ###-####. c/n issued (exit signs, smoke vents, alarms, address, etc) 1/26/2001 3:53:30 PM
|
BLD-Framing/Rough-in | 12/20/2000 | 12/21/2000 | 12/21/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/20/2000 at 11:16:06. Contact: ###-####. cellings in tennent spaces ok 12/21/2000 11:01:30 AM
|
BLD-Framing/Rough-in | 12/11/2000 | 12/11/2000 | 12/11/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/11/2000 at 09:16:56. Contact: ###-####. ceilling ok jewellery store. 12/11/2000 3:48:17 PM
|
BLD-Framing/Rough-in | 12/1/2000 | 12/1/2000 | 12/1/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/01/2000 at 09:42:28. Contact: ###-####. north corridor ok for cover plm acess door must be rated check at later date. 12/1/2000 2:29:56 PM
|
BLD-Framing/Rough-in | 11/21/2000 | 11/21/2000 | 11/21/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/21/2000 at 10:37:10. Contact: ###-####. coridor plm/screws on 12 inch ceilling and clips/light wires and seismic pods./putty pads 2 loc corrdor. 11/24/2000 12:44:48 PM
|
BLD-Framing/Rough-in | 11/16/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/16/2000 at 16:00:29. Contact: ###-####. main canopy framing screw atchment not per plan leadger on slpit face not per plan rfi for atchment. 11/17/2000 5:01:49 PM
|
BLD-Framing/Rough-in | 11/8/2000 | 11/9/2000 | 11/9/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/08/2000 at 14:57:21. Contact: ###-####. c/n previous rated const. ok/ east canopy front ok for cover. 11/13/2000 9:19:25 AM
|
BLD-Framing/Rough-in | 11/7/2000 | 11/7/2000 | 11/7/2000 | P | FAIL |
Jim Storey
|
|
|
Wes ###-#### colums at mech. mez. not wrapped/ ele putty pads required at center coridor north / south coridor blow patch. 11/8/2000 8:52:39 AM
|
BLD-Framing/Rough-in | 11/1/2000 | 11/2/2000 | 11/2/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/01/2000 at 13:32:00. Contact: ###-####. tennent spaces ok at north west corner of bldg curtian wall west /south area ok for cover . 11/2/2000 4:15:17 PM
|
BLD-Framing/Rough-in | 10/20/2000 | 10/23/2000 | 10/23/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/20/2000 at 09:03:04. Contact: ###-####. framing ok exterior and interior walls / pending mech mez. and frnt tunnel corridors. 10/23/2000 12:49:37 PM
|
BLD-Framing/Rough-in | 10/5/2000 | 10/6/2000 | 10/6/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/05/2000 at 11:19:23. Contact: ###-####. home storage area south west walls and all south tunnel corridors ok for cover. 10/6/2000 11:03:07 AM
|
BLD-Framing/Rough-in | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/28/2000 at 15:50:15. Contact: ###-####. east coridor must have speaker gyp box protection. 9/29/2000 5:30:14 PM
|
BLD-Framing/Rough-in | 9/22/2000 | 9/25/2000 | 9/25/2000 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/22/2000 at 16:04:15. Contact: ###-####. good to cover east to west grid line 10 only one side rated tunnels for reinsp c/n . 9/25/2000 11:42:04 AM
|
BLD-Framing/Rough-in | 8/29/2000 | 8/30/2000 | 8/30/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/29/2000 at 13:11:04. Contact: ###-####.
|
Additional plans submitted | | | 8/18/2000 | | DONE |
|
|
|
RECEIVED ONE COPY OF THERMOPLASTIC SINGL-PLY MEMBRANE ROOFING RESUBMITTAL. ROUTED TO JIM STORY. KMM
|
BLD-Framing/Rough-in | 8/14/2000 | 8/15/2000 | 8/15/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 16:08:13. Contact: ###-####. roof decking ok pending s/i report. 8/16/2000 1:31:46 PM
|
BLD-Concrete | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 8/14/2000 aproved resubmital and archived plan.
|
BLD-Footing | 8/9/2000 | 8/10/2000 | 8/10/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 08/09/2000 at 11:27:29. Contact: ###-####. pending spinsp approvals 8/10/2000 3:38:57 PM
|
BLD-Footing | 8/7/2000 | 8/8/2000 | 8/8/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 08/07/2000 at 13:06:15. Contact: ###-####. on site with 301 c/nissued for bolt projection at post bases and for changes for the steel decking attachments, concrete approved with sp insp approvals 8/8/2000 9:28:15 AM
|
BLD-Foundation | 8/3/2000 | 8/4/2000 | 8/4/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/03/2000 at 12:52:53. Contact: ###-####. rebar ok south wall line at loading docl/ walked roof joist and girder to colum atchaments ok steel deck atachments changed to hilti shot pins requir enginer of record to submit change. east deck 4 bays to the west ok pending aproval of resubmital 8/4/2000 10:33:04 AM
|
BLD-Footing | 7/27/2000 | 7/28/2000 | 7/28/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 15:57:37. Contact: ###-####. pending report s/i. 7/28/2000 11:49:08 AM
|
BLD-Footing | 7/26/2000 | 7/27/2000 | 7/27/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/26/2000 at 15:02:42. Contact: ###-####. pending report from s/i. 7/27/2000 9:56:34 AM
|
BLD-Footing | 7/24/2000 | 7/25/2000 | 7/25/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/24/2000 at 08:22:37. Contact: ###-####. rebar ok pending s/i report. 7/25/2000 8:16:15 AM
|
BLD-Footing | 7/24/2000 | 7/24/2000 | 7/24/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/24/2000 at 08:35:17. Contact: ###-####. south/east 100 ft to 200 ft. pending report appears ok on rebar. 7/24/2000 1:30:55 PM
|
BLD-Footing | 7/19/2000 | 7/20/2000 | 7/20/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 10:59:43. Contact: ###-####. covered with s/i. 7/20/2000 2:53:42 PM
|
BLD-Footing | 7/17/2000 | 7/18/2000 | 7/18/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/17/2000 at 15:11:00. Contact: ###-####.
|
BLD-Footing | 7/14/2000 | 7/17/2000 | 7/17/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 15:25:38. Contact: ###-####. pending s/i report. 7/17/2000 1:34:18 PM
|
BLD-Footing | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 14:31:36. Contact: ###-####.
|
BLD-Foundation | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 14:33:21. Contact: ###-####.
|
BLD-Footing | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 12:58:19. Contact: ###-####. pending s/i report. 7/13/00 11:16:21 AM
|
BLD-Footing | 7/11/2000 | 7/12/2000 | 7/12/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 14:43:07. Contact: ###-####. gil called and cancled via phone. 7/12/00 1:37:58 PM
|
BLD-Footing | 7/11/2000 | 7/12/2000 | 7/12/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 14:43:07. Contact: ###-####.
|
BLD-Footing | 7/10/2000 | 7/11/2000 | 7/11/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/10/2000 at 13:52:01. Contact: ###-####. pending s/i report . 7/11/00 1:46:56 PM
|
BLD-Footing | 7/7/2000 | 7/10/2000 | 7/10/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/07/2000 at 16:28:53. Contact: ###-####. pending s/i report. 7/10/00 5:11:19 PM
|
BLD-Footing | 7/6/2000 | 7/7/2000 | 7/7/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 15:12:50. Contact: ###-####.
|
BLD-Footing | 7/5/2000 | 7/6/2000 | 7/6/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 07/05/2000 at 11:56:51. Contact: . SOUTH EAST TO NORTHEAST FOOTER 7/7/00 6:29:36 AM
|
(F) Reprint permit | | | 12/30/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/29/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/22/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/22/1999 | | DONE |
|
|
|
|
Telephone call | | | 12/22/1999 | | DONE |
|
|
|
called Evan Eagle, was on vacation, talked to a Jennifer who was covering for him. Permit ready and fees due and need ACHD cert.
|
Routing - PLAN CHECK | 9/28/1999 | 9/28/1999 | 12/21/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/1999 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/28/1999 | | 12/21/1999 | | PASS |
John Menard
|
|
|
12/21/1999 14:23:18 JCM - activity updated through activity BLDA022 from case BLD99-02185.
|
Plan resubmittals received | | | 12/20/1999 | | PASS |
|
|
|
RECIEVED COPIES OF RECORDED RECORD OF SURVEY AND NONBUILD AGREEMENT FOR UNLIMITED AREA OF THIS BUILDING.
|
Plan resubmittals requested | | | 11/1/1999 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/7/1999 | 10/7/1999 | 10/13/1999 | | PASS |
|
|
|
RESUBMITTAL PLANS SENT TO ENGINEERING CONSULTANT VIA PDQ. 10/7/99 DAR RESUBMITTED STRUCTURAL PLAN REVISIONS HAVE BEEN REVIEWED AND APPROVED BY THE CONSULTING ENGINEER.
|
Plan resubmittals requested | | | 10/12/1999 | | PEND |
|
|
|
FAXED EVAN EAGLE A REQUEST FOR ADDITIONAL INFORMATION AND PLAN REVISIONS. THIS REQUEST IS BASED ON THE LAST REVISIONS SUBMITTAL, RECEIVED 10/5/99.
|
Plan resubmittals received | | | 10/5/1999 | | PEND |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM SIENNA ARCHITECTS, SAME FORWARDED TO JOHN MENARD. 10/5/99 DAR
|
Plan Reviewer's activity | | | 10/3/1999 | | PEND |
|
|
|
FAXED TOM AT THE DAKOTA COMPANY THE INFORMATION NEEDED TO COMPLETE A RECORDED SHARED YARD EASEMENT FOR AN UNLIMITED AREA BUILDING.
|
Plan resubmittals received | | | 9/29/1999 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS S1.0, S2.1, S2.2, S2.3, S2.4, S2.5, S2.6, S3.1, S3.2, S3.3, S3.4, S3.5, S3.6, S3.7, S4.0, S5.0, S5.1, S6.0, S6.1, S6.2, S6.3. ONE COPY OF RESPONSE LETTER. ROUTED TO JOHN M. KMM
|
Routing - PLUMBING | 9/20/1999 | | 9/28/1999 | | PASS |
|
|
|
provide backwater valve for trench drain in garden area, all traps not on an approved combination waste and vent system must be vented, case wash downs may require additional cross connection protection, poin of use backflow protection may be required
|
Plan resubmittals received | | | 9/26/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM SIENNA ARCHITECTS, FORWARDED SAME TO JOHN MENARD. 10/26/99 DAR
|
Routing - PUBLIC WORKS | 9/20/1999 | 9/20/1999 | 9/20/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/13/1999 | 9/13/1999 | 9/20/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/20/1999 | | PEND |
|
|
|
INSERTED REVISED PLUMBING, ELECTRICAL AND KITCHEN PLANS AND ROUTED TO PUBLIC WORKS AND PLUMBING FOR REVIEW.
|
Plan Review Completed(1st rev) | | | 9/13/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 9/13/1999 | | PEND |
John Menard
|
|
|
RECEIVED PLAN RESUBMITTALS FOR PLUMBING FROM GAUSMAN & MOORE FORWARDED SAME TO JOHN MENARD. 9/13/99 DAR
|
Routing - FIRE | 9/1/1999 | 9/7/1999 | 9/7/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/13/1999 | | 9/1/1999 | | |
|
|
|
|
Plan resubmittals requested | | | 8/30/1999 | | PEND |
|
|
|
FAXED EVAN EAGLE AT SIENNA A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Plan resubmittals requested | | | 8/30/1999 | | PEND |
|
|
|
MAILED EVAN EAGLE AT SIENNA A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 7/28/1999 | | 8/26/1999 | | |
|
|
|
SENT ONE SET OF PLANS AND STRUCTURAL CACULATIONS,ONE PROJECT MANUAL(VOLUMES 1 & 2) TO STRUCTURAL ENGINEERING CONSULANT. 8-26-99 RECEIVED STRUCTURAL REVIEW LETTER FOR FRED MEYER FROM CH2MHILL. ROUTED TO JOHN M. KMM
|
Routing - PLANNING | 8/11/1999 | | 8/13/1999 | | PASS |
|
|
|
Mike Hall reviewed per CUP98-0099 and Marty Santoyo reviewed per DRH98-0239.
|
Routing - PLUMBING | 8/10/1999 | | 8/11/1999 | | FAIL |
|
|
|
public works approval required prior to plumbing review
|
Routing - PUBLIC WORKS | 7/28/1999 | | 8/9/1999 | | FAIL |
|
|
|
NO GARBAGE DISPOSAL ALLOWED BY CITY ORDANANCE. PER WALT BAUMGARTNER, ENVIRONMENTAL SERVICES. 8/10/99 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 7/28/1999 | | PEND |
|
|
|
RECEIVED PLANS ON 7/21/99 SEVERAL GROUPS STAMPE NOT FOR CONSTRUCTION. QUADRANT ENGINEERING REPLACED ALL OF THOSE PLANS ON 7/27/99. 7/28/99 DAR
|
Plan assigned to (MYS) | 7/21/1999 | | 7/28/1999 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/21/1999 | | |
|
|
|
|
Application received | | | 7/20/1999 | | |
|
|
|
|
Extend Permit 180 days | | | | | EXTE |
|
|
|
permit extended by jeff jones-letter sent out feb 23, 2000 to Mr. Eagle- new expiration date is 8/21/2000
|