Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD99-02201
StatusFinaled
Name RUMSEY HAROLD E
Site Address 1421 N LIBERTY ST
Project NameASPEN APARTMENTS
Customer Number 
ePlanReviewNo
Description
UNIT TYPE "A-1" * TO CONSTRUCT A NEW 2,838 SQ,FT. TWO STORY, WOOD FRAMED TYPE V NONRATED, FOUR UNIT APARTMENT BUILDING. THERE ARE TWO TYPE A UNITS ON THE FIRST FLOOR AT 710 SQ.FT. EACH AND TWO TYPE A UNITS ON THE SECOND FLOOR AT 710 SQ.FT. EACH. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A17.1 AND THE 1997 EDITION OF THE UBC. PERMIT TO INCLUDE ON SITE PARKING AND LANSCAPING. MJP DRH99-0064 CUP99-0042 PC#
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/18/20036/18/20036/18/2003 DONE
Permanent occupancy  12/18/2000 DONE
Perm. Occ. Cert. #8508 issued 12-18-00 to the Aspen Apts.
Permanent Occupancy 12/15/200012/15/2000 DONE
Details
BLD-Final12/15/200012/15/200012/15/2000PPASS
DetailsTom Arcoraci
FN DON-- ###-#### ok for perm occ 12/15/2000 3:54:39 PM
FIRE-Final Inspection11/1/200011/1/200011/1/2000APASS
DetailsJoe Tawney
###-####. Final OK for permanant occupancy 11/1/2000 12:19:47 PM
BLD-Final11/1/200011/1/200011/1/2000PPART
DetailsTom Arcoraci
###-#### DON 11/1/2000 3:09:16 PM cn posted e/code and door closers ok for temp occ 11/1/2000 3:21:33 PM
FIRE-Final Inspection10/31/200010/31/200010/31/2000PCANC
DetailsJoe Tawney
Don ###-####
BLD-Framing/Rough-in9/19/20009/20/20009/20/2000APASS
DetailsTom Arcoraci
###-#### drytwall shear ok 9/20/2000 11:05:22 AM
BLD-Framing/Rough-in9/15/20009/15/20009/15/2000PCANC
DetailsTony Young
DON ###-#### DRYWALL INSP
Inspector's copy Bld permit  9/14/2000 DONE
Inspection Record Card- Bld  9/14/2000 DONE
Print Occupancy Form  9/14/2000 DONE
BLD-Framing/Rough-in9/7/20009/8/20009/8/2000APART
DetailsCarl Dependahl
don ###-####; ok to cover, need gyp nailing insp at firewalls 9/8/2000 1:59:07 PM
BLD-Framing/Rough-in9/5/20009/5/20009/5/2000PPART
DetailsCarl Dependahl
this is a framing and a shear Don ###-####; int & ext osb ok. ok to side both floors 9/5/2000 2:41:21 PM
BLD-Framing/Rough-in8/30/20008/30/20008/30/2000AFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 8/30/2000 renail shear panels at 2nd fl; recall
BLD-Framing/Rough-in8/28/20008/28/20008/28/2000PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 8/28/2000
BLD-Wall cover8/24/20008/25/20008/25/2000APART
DetailsCarl Dependahl
Added by Inspector: 340 On 8/24/2000 GYPSUM
BLD-Framing/Rough-in8/23/20008/23/20008/23/2000PPART
DetailsCarl Dependahl
shear ###-####; ok to insulate 1st fl shear walls and add osb. 8/23/2000 1:17:43 PM
BLD-Energy code compliance8/23/20008/23/20008/23/2000PPART
DetailsCarl Dependahl
###-####, ok to side, ext sheathing ok 8/23/2000 11:54:34 AM
BLD-Framing/Rough-in8/22/20008/22/20008/22/2000AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/22/2000 at 07:10:34. Contact: ###-####.
BLD-Framing/Rough-in8/17/20008/18/20008/18/2000AFAIL
DetailsCarl Dependahl
Don ###-####; missed panels at nw corner, nail &recall 8/18/2000 11:21:41 AM
BLD-Framing/Rough-in8/17/20008/17/20008/17/2000PNR
DetailsCarl Dependahl
Daon ###-####
BLD-Framing/Rough-in8/11/20008/14/20008/14/2000APART
DetailsCarl Dependahl
don ###-#### shear nailing insp
BLD-Framing/Rough-in8/11/20008/11/20008/11/2000PCANC
DetailsTony Young
SHEAR NAIL-- FR --###-####- DON--PLEASE CALL 1/2 HR BEFORE INSP
per don cancel -re-scheduled. canceled by 325

BLD-Framing/Rough-in8/10/20008/10/20008/10/2000PFAIL
DetailsRuss Owen
shear wall Don ###-#### Approved plans not on site,prior c/n not at site.new c/n. 8/11/2000 9:23:32 AM
BLD-Framing/Rough-in8/8/20008/9/20008/9/2000AFAIL
DetailsCarl Dependahl
shear nailing don ###-####; ok to side n & s ends only. c/n issued. 8/9/2000 12:18:10 PM
BLD-Framing/Rough-in8/8/20008/8/20008/8/2000PNR
DetailsTom Arcoraci
shear nailing don ###-####
BLD-Foundation6/14/20006/14/20006/14/2000PPART
DetailsJim Sly
they are going to pour foundation walls at 3pm Clay ###-####
BLD-Footing6/8/20006/9/20006/9/2000PPART
DetailsJim Sly
Clay ###-####
Issue PAID IN FULL permit  6/7/2000 DONE
Routing - PLAN CHECK3/17/2000 3/29/2000  
Plan Reviewer's activity  3/29/2000 DONE
Print Pending Permit.LaserJet4  3/29/2000 DONE
Case Summary (BLD)  3/29/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/29/2000 DONE
Print Occupancy Form  3/29/2000 DONE
Inspection Record Card- Bld  3/29/2000 DONE
Plan assigned to (M_P)7/21/1999 3/29/2000 PASS
DetailsMike Phillips
3/29/2000 12:07:54 M_P - activity updated through activity BLDA022 from case BLD99-02201.
Routing - PLANNING3/10/2000 3/17/2000 PASS
Approved as per revised site plan and parking plan submitted 3/16/00. As per CUP99-00142. TAC
Routing - PLAN CHECK3/6/2000 3/10/2000  
Routing to P & Z for parking modification.
Routing - PLUMBING3/3/2000 3/6/2000 DONE
Routing - PLAN CHECK12/29/1999 3/3/2000  
routing to plumbing
Routing - PUBLIC WORKS3/2/2000 3/3/2000 DONE
Plan resubmittals received  2/29/2000 DONE
resubmittal received from tamura
Plan resubmittals received  2/29/2000  
Routing - FIRE12/20/199912/28/199912/28/1999 PASS
Plan Review Completed(1st rev)  12/28/1999  
Plan resubmittals requested  12/18/1999 FAIL
ADDITIONAL INFORMAITON REQUESTED TO BE SUBMITTED FOR FURTHER REVIEW.
Print Pending Permit.LaserJet4  12/18/1999 FAIL
ADDITIONAL INFORMATION REQUESTED FOR FURTHER REVIEW.
Routing - PLAN CHECK10/1/1999 12/18/1999  
ROUTING TO FIRE FOR REVIEW.
Plan resubmittals requested  10/25/1999 FAIL
Called and requested additional structural plans to be submitted prior to completing my review.
Routing - PUBLIC WORKS9/28/19999/28/199910/1/1999 FAIL
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. KMM
Plan resubmittals received  9/28/1999  
Plan resubmittals received  9/27/1999 PEND
PLAN RESUBMITTALS RECEIVED FROM MARK SANDERS, FORWARDED SAME TO MIKE PHILLIPS. 9/28/99 DAR
Routing - PLAN CHECK8/12/1999 8/20/1999 HOLD
requesting new plans to be submitted for review
Plan resubmittals requested  8/20/1999 FAIL
Sent submittal letter requesting new plans to be submitted.
Routing - PLANNING8/5/1999 8/12/1999 PASS
Developer must provide 3 bicycle parking spaces and 2 handicapped parking spaces. Buildiing must be constructed to 1993 Boise City Energy Code standards. TAC
Routing - PLUMBING7/28/1999 8/5/1999 PASS
4 plex doesnt need review
Routing - PLAN CHECK8/5/1999 8/5/1999
Routing to planning
Routing - PUBLIC WORKS7/23/1999 7/28/1999 FAIL
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. 7/28/99 DAR
Application received  7/21/1999