Receive PAYMENT IN FULL | | | 4/5/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 2/3/2000 | 2/3/2000 | | DONE |
|
|
|
|
BLD-Final | 2/3/2000 | 2/3/2000 | 2/3/2000 | P | PASS |
Alan Hauser
|
|
|
Gil; ###-####. Ok for perm. occ. 2/4/00 11:39:06 AM
|
Permanent occupancy UNPAID FEE | | | 2/3/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8120 issued 2-3-00 to Albertson's Express (convenience store).
|
Fee Review-notes | 7/21/1999 | | 1/24/2000 | | DONE |
|
|
|
additional value from subs lh
|
Telephone call | | | 1/24/2000 | | DONE |
|
|
|
Called Gordon Bates and gave him a heads up on status of temp. occ.
|
(F) Reprint permit | | | 1/24/2000 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 12/20/1999 | | PASS |
|
|
|
Meets complaince - signed final
|
Temporary occupancy | | | 11/29/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3949 issued 11-29-99 to Albertson's A Express.
|
BLD-Final | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | PART |
Jim Sly
|
|
|
###-#### C/N.. Need (stamped) letter from engineer for fix or approval of discrepancies in CMN wall ok for temp. occ. Obtain perm. Occ. Status withing 90 days.
|
Code Occupancy Approval | | | 11/24/1999 | | PASS |
|
|
|
H/C Signs up - wheel restraints in - slats in gate at dumpster encl. in - compliance met.
|
BLD-Final | 11/23/1999 | 11/23/1999 | 11/23/1999 | P | FAIL |
Jim Sly
|
|
|
wes ###-#### fn occ C/N.. Need final letter from sp. Insp. Agency, need all req. signatures.
|
Code Occupancy Approval | | | 11/23/1999 | | FAIL |
|
|
|
Still needed: above grade H/C parking sign; gate on dumpster enclosure and five (5) wheel restraints at the sidewalk/parking area to the south end of the building. Rescheduled for inspection 11/24/99 at 4:00 p.m.
Reinspect - 11/26/99 -signed temporary - all that remains are the slats in the gate for the dumpster enclosure.
|
FIRE-Final Inspection | 11/18/1999 | 11/19/1999 | 11/19/1999 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 11/18/1999 at 15:14:26. Contact: ###-####. Final ok for permanent occ.
|
BLD-Framing/Rough-in | 11/10/1999 | 11/10/1999 | 11/11/1999 | P | PART |
Jim Sly
|
|
|
grid ceiling wes ###-#### Ceiling grid ok.
|
BLD-Framing/Rough-in | 10/27/1999 | 10/28/1999 | 10/28/1999 | A | PASS |
Jim Sly
|
|
|
roger ###-#### Pending special inspection and approvals
|
BLD-Framing/Rough-in | 10/19/1999 | 10/20/1999 | 10/20/1999 | A | PART |
Tom Arcoraci
|
|
|
###-#### fr ---roger Ok to cover Ext. walls
|
BLD-Framing/Rough-in | 10/15/1999 | 10/15/1999 | 10/15/1999 | P | PART |
Jim Sly
|
|
|
rOGER ###-#### Ok to cover ext. wall only, bracing ok (exterior side)
|
Plan resubmittals received | | | 9/21/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/21/1999 | | PASS |
|
|
|
RECEIVED ELECTRICAL PLAN RESUBMITTALS , FORWARDE THEM TO RECORDS. 9/21/99 DAR
|
(F) Reprint permit | | | 9/2/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/1999 | | |
|
|
|
|
Print Occupancy Form | | | 8/30/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/1999 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/26/1999 | | 8/24/1999 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 8/10/1999 | | 8/24/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/18/1999 | | 8/24/1999 | | PASS |
|
|
|
ROUTED ONE COPY OF REVISED DRAWINGS WITH CALCS. TO OUTSIDE ENG. VIA PDQ. KMM 8-24-99 ROUTED STRUCTURAL PLAN CHECK RE-REVIEW COMMENTS TO JOHN M. KMM
|
Plan resubmittals received | | | 8/17/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED DRAWINGS, CALCULATIONS AND RESPONSE LETTER FROM THE STRUCTURAL ENG. FOR THE CONVENIENCE STORE. ROUTED ONE COPY TO OUTSIDE ENG. AND TWO TO JOHN M. KMM
|
Plan resubmittals requested | | | 8/17/1999 | | PEND |
|
|
|
FAXED CURTIS CRYSTAL JOHN MENARDS'S PLAN REVIEW COMMENTS DATED AUGUST 12, 1999. 8/17/99 DAR
|
Routing - FIRE | 8/12/1999 | | 8/16/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 8/16/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/12/1999 | | PASS |
|
|
|
PLANS WERE REVIEWED AND APPROVED AS SUBMITTED WITH ATTACHED PLAN REVIEW COMMENT LIST AND PLAN NOTES.
|
Routing - PLANNING | 8/10/1999 | | 8/10/1999 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 8/10/1999 | | PEND |
|
|
|
FAXED CURTIS CRYSTAL AT CSHQA A COPY OF THE COMMENT LIST FROM THE CONSULTING ENGINEER REQUESTING REVISIONS.
|
Routing - PLUMBING | 7/28/1999 | | 8/9/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/27/1999 | | 8/9/1999 | | |
|
|
|
REQUIRES SOILS REPORT. CONTACTED PDQ TO TAKE TO OUTSIDE ENG. KMM 08-10-99 ROUTED RESPONSE LETTER FROM ATWOOD HINZMAN JONES TO JOHN M. KMM
|
Routing - PUBLIC WORKS | 7/26/1999 | | 7/28/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 7/21/1999 | | 7/26/1999 | | PASS |
Marlene Southard
|
|
|
|
Plan routing begun/NEW & ADDTN | 7/26/1999 | | 7/26/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/1999 | | FAIL |
|
|
|
REQUIRES 1. ADDITIONAL COPY OF CANOPY SHEETS CA1, CS1, AND CS2 2. ONE COPY OF SHEETS 9.3A, AND 9.3B, BECAUSE THEY WERE NOT SIGNED 3. SOILS REPORT CONTACTED GORDON BATES OF THESE NEEDS I PUT ONE COPY OF CANOPY SHEETS WITH OUTSIDE ENG. AND ONE WITH ISSUE COPY. KMM 7-27-99 RECEIVED ALL OF THE ABOVE MENTIONED ITEMS. KMM
|
Application received | | | 7/21/1999 | | |
|
|
|
|
Routing Off Site - C.D.H | 7/21/1999 | | 7/21/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 7/21/1999 | | PASS |
|
|
|
|