Fee Review-notes | 6/18/2003 | 6/18/2003 | 6/18/2003 | | DONE |
|
|
|
|
Fee Review-notes | 7/26/1999 | | 6/20/2000 | | DONE |
|
|
|
|
BLD-Final | 9/28/1999 | 9/28/1999 | 9/30/1999 | P | PASS |
|
|
|
DON-- ###-#### FN OCC Signed perm. Col. Occ. Req. card
|
Permanent occupancy | | | 9/30/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7921 issued 9-30-99 to Best Consulting in Forest River IX.
|
FIRE-Final Inspection | 9/27/1999 | 9/28/1999 | 9/28/1999 | A | PASS |
Rick Jackson
|
|
|
BRIAN-- ###-#### FN FIRE-RE-INSP Occupancy approved
|
FIRE-Final Inspection | 9/23/1999 | 9/23/1999 | 9/23/1999 | P | FAIL |
Rick Jackson
|
|
|
DON-- ###-#### FIRE FN Sprinklers no complete; Door closure; Fire extinguisher
|
INSP - Conference | 9/13/1999 | 9/13/1999 | 9/13/1999 | A | PART |
|
|
|
with 409 and with the super, Don on the west exit a more perm wall is required to guide people to the exit door
|
INSP - Framing/Rough-in | 9/8/1999 | 9/9/1999 | 9/9/1999 | P | PART |
|
|
|
ceiling grid not complete ned perimeter wires completed lights and diffusers need proper attachmentSUITE 210. DON ###-####
|
Issue PAID IN FULL permit | | | 8/31/1999 | | |
|
|
|
|
Telephone call | | | 8/27/1999 | | PASS |
|
|
|
###-####
|
Inspection Record Card- Bld | | | 8/27/1999 | | |
|
|
|
|
Print Occupancy Form | | | 8/27/1999 | | |
|
|
|
|
testing condition printout | | | 8/26/1999 | | |
|
|
|
|
Print permit w/o conditions | | | 8/26/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/26/1999 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Plan assigned to (CJW) | 7/29/1999 | | 8/26/1999 | | PASS |
Carl Westfall
|
|
|
08/26/99 14:28:26 CJW - this action updated by action script from <<>> in Case No. BLD99-2240
|
Routing - PLAN CHECK | 8/16/1999 | | 8/26/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/25/1999 | | |
|
|
|
|
Routing - FIRE | 8/11/1999 | | 8/16/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 8/16/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 7/29/1999 | | 8/11/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/10/1999 | | |
|
|
|
UBC plan review started August 10, 1999 and finished August 11, 1999. A response from the architect is required. See the conditions list.
|
Plan routing begun/TENANTS | | | 7/29/1999 | | |
|
|
|
Route to PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 7/26/1999 | | 7/29/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/1999 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/26/1999 | | |
|
|
|
|
Received Certificate of Value | 7/27/1999 | | 7/26/1999 | | PASS |
|
|
|
|
Application received | | | 7/23/1999 | | |
|
|
|
|
Print Occupancy Form | | | | | |
|
|
|
|