Letter of compliance | | | 12/8/1999 | | DONE |
|
|
|
Letter of Compliance #18200 issued 12-8-99.
|
FIRE-Final Inspection | 11/3/1999 | 11/4/1999 | 11/4/1999 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 11/03/1999 at 16:09:05. Contact: ###-####. Reinsp. Ok for cert. Of completion.
|
BLD-Framing/Rough-in | 11/3/1999 | 11/4/1999 | 11/4/1999 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/03/1999 at 16:11:31. Contact: ###-####. Cancelled by contractor.
|
FIRE-Final Inspection | 10/31/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/31/1999 at 15:08:03. Contact: ###-####. Reinsp. Was trying to schedule structural inspection on Hello system.
|
BLD-Framing/Rough-in | 11/1/1999 | 11/1/1999 | 11/1/1999 | P | PART |
Carl Dependahl
|
|
|
NEIL ###-#### WALL INSP
|
FIRE-Final Inspection | 10/27/1999 | 10/28/1999 | 10/28/1999 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/27/1999 at 14:27:12. Contact: ###-####. Final fail install ceiling tile at sprklr. Heads
|
FIRE-Final Inspection | 10/21/1999 | 10/22/1999 | 10/22/1999 | A | PART |
Joe Tawney
|
|
|
###-#### Ok on sprkl. R/I, ok to cover
|
BLD-Framing/Rough-in | 10/20/1999 | 10/20/1999 | 10/20/1999 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/20/1999 at 08:45:45. Contact: ###-####. Met w/ proj. mgr; ok to cover walls; need sprinkler R/I
|
Issue PAID IN FULL permit | | | 8/9/1999 | | |
|
|
|
|
Telephone call | | | 8/4/1999 | | |
|
|
|
LEFT MSG FOR NEIL THAT PERMIT IS READY FOR PICK UP
|
Inspection Record Card- Bld | | | 7/30/1999 | | |
|
|
|
|
Print Occupancy Form | | | 7/30/1999 | | |
|
|
|
|
Plan assigned to (DRS) | 7/28/1999 | | 7/29/1999 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 7/29/1999 | | 7/29/1999 | | PASS |
|
|
|
Approved as noted & attached.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/1999 | | PASS |
|
|
|
Routing to permit desk for issuance of permit.
|
Print Pending Permit.LaserJet4 | | | 7/29/1999 | | PASS |
|
|
|
|
Meeting | | | 7/28/1999 | | |
|
|
|
Met with Neil Boel, Facilities Manager, Central District Health Bldg @ 707 Armstrong Pl.
|
Plan Reviewer's activity | | | 7/28/1999 | | |
|
|
|
Researched files & Micro fiche to determine the actual construction type of the builidng and if there are any rated corridors required. File indicates V-1hour construction but fiche indicate construction type was changed to VN by provideing 5 separate tenant zones, each area having it's own exits & 20 min. door assemblies called for at doors between tenant areas. The builidng is fully sprinkled, the corridors are protected by smoke detection; areas are 10,000 sq. ft. or less and occupanct load under 100 per section 3305(g)5, 1991 UBC.
|
Application received | | | 7/28/1999 | | |
|
|
|
|