Case Summary (BLD) | | | 5/22/2003 | | |
|
|
|
|
BLD-Final | 9/8/2000 | 9/11/2000 | 9/11/2000 | A | PASS |
Carl Dependahl
|
|
|
This is the one we talked about! Carl received the engineer's letter.
|
Letter of compliance | | | 9/11/2000 | | DONE |
|
|
|
Letter of Compliance #18561 issued 9-11-00
|
Fee Review-notes | 4/3/2000 | 4/3/2000 | 7/25/2000 | | DONE |
|
|
|
|
BLD-Final | 6/14/2000 | 6/15/2000 | 6/15/2000 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 17:46:43. Contact: ###-####. OK for temp. occ.- C/N need req. signatures for perm. occ. within 90 days letter from special insp. 6/16/00 8:53:25 AM
|
Temporary occupancy | | | 6/15/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4027 issued 6-15-00 to Hewlett Packard, Bldg. #27.
|
BLD-Final | 6/14/2000 | 6/14/2000 | 6/14/2000 | P | PASS |
Joe Tawney
|
|
|
Reinsp. ok for cert. of completion
|
FIRE-Final Inspection | 6/12/2000 | 6/13/2000 | 6/13/2000 | P | FAIL |
Joe Tawney
|
|
|
mike ###-#### Final fail C/N issued. 6/14/00 8:59:47 AM
|
BLD-Framing/Rough-in | 2/3/2000 | 2/4/2000 | 2/4/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 14:57:11. Contact: ###-####. HP #27 need eng'r approval letter ok to cover elec room only
|
BLD-Foundation | 12/15/1999 | 12/16/1999 | 12/16/1999 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 10:59:15. Contact: ###-####.
|
BLD-Foundation | 12/13/1999 | 12/14/1999 | 12/14/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 13:45:47. Contact: ###-####.; spec insp onsite
|
BLD-Foundation | 11/29/1999 | 11/30/1999 | 11/30/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/29/1999 at 11:37:03. Contact: ###-####. Spec. insp. Onsite.
|
BLD-Foundation | 11/17/1999 | 11/18/1999 | 11/18/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/17/1999 at 16:33:59. Contact: . Pend. Spec. insp. Report.
|
BLD-Framing/Rough-in | 11/10/1999 | 11/10/1999 | 11/10/1999 | P | FAIL |
Carl Dependahl
|
|
|
roof drains/ russ ###-#### Not frame insp.. Need plmb.
|
BLD-Foundation | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PART |
Carl Dependahl
|
|
|
rebar ken ###-#### MTL onsite.
|
BLD-Foundation | 10/26/1999 | 10/26/1999 | 10/26/1999 | P | PART |
Carl Dependahl
|
|
|
rebar kent ###-#### Spec. insp. Onsite
|
BLD-Framing/Rough-in | 10/22/1999 | 10/25/1999 | 10/25/1999 | A | PART |
Carl Dependahl
|
|
|
CONCRETE TILT UP PANELS KENT ###-#### Spec. insp. Onsite
|
BLD-Framing/Rough-in | 10/21/1999 | 10/22/1999 | 10/22/1999 | A | PART |
Carl Dependahl
|
|
|
KENT--###-#### RE-BAR Spec. insp. Onsite
|
BLD-Footing | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PART |
Carl Dependahl
|
|
|
kent ###-#### cell ft insp Int. grade beams.. Spec. insp. Onsite
|
BLD-Footing | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | PART |
Carl Dependahl
|
|
|
KENT ###-#### FT INSP tilt-up , spec insp onsite
|
BLD-Foundation | 10/1/1999 | 10/4/1999 | 10/4/1999 | P | PART |
Carl Dependahl
|
|
|
KETN ###-#### FOUND INSP\\spec insp on site
|
INSP - Foundation | 9/13/1999 | 9/13/1999 | 9/13/1999 | P | PART |
Carl Dependahl
|
|
|
SPEC. INSP.
|
INSP - Foundation | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PART |
Tom Arcoraci
|
|
|
09/03/99 408 - rebar insp-mike- ###-#### for found
|
(F) Reprint permit | | | 9/2/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/1/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/1/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/1/1999 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/25/1999 | | 9/1/1999 | | PASS |
|
|
|
SENT RESUBMITTALS TO STRUCTURAL ENGINEER CONSULANT. 8/25/99 DAR
|
Plan assigned to (MLO) | 7/30/1999 | | 9/1/1999 | | PASS |
Mike Otto
|
|
|
|
Plan resubmittals received | | | 8/24/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PINNICAL ENGINEERING. FORWARDED SAME TO MIKE OTTO 8/24/99 DAR.
|
Routing Off Site - STRUCTURAL | 7/30/1999 | | 8/17/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan resubmittals requested | | | 8/17/1999 | | FAIL |
|
|
|
CORRECTIONS FOR STRUCTURAL FAXED TO ENGINEER AND ARCHITECT. MLO
|
Routing - PLAN CHECK | 8/4/1999 | | 8/5/1999 | | PASS |
|
|
|
|
Routing - FIRE | 8/5/1999 | | 8/5/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 8/5/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 8/4/1999 | | 8/4/1999 | | PASS |
|
|
|
approved per DRH99-0120 and DRH99-0161.
|
Routing - PLUMBING | 8/3/1999 | | 8/4/1999 | | PASS |
|
|
|
upc 601-water serving eyewash in penthouse is to be frompotable service. upc 603 hose bib in penthouse if downstream of backflow preventer must be posted per section 603.4.12, 97 upc, upc 306.2- sub floor drain pan shall not recieve rainwater. per plans and specs and 97 upc
|
Routing - PUBLIC WORKS | 7/30/1999 | | 8/3/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/1999 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/30/1999 | | PASS |
|
|
|
|
Application received | | | 7/29/1999 | | |
|
|
|
|
Received Certificate of Value | | | 7/29/1999 | | PASS |
|
|
|
|
(F) Reprint permit | | | | | |
|
|
|
|