BLD-Final | 10/21/1999 | 10/22/1999 | 10/22/1999 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/21/1999 at 22:11:21. Contact: ###-####. C/C #16272
|
BLD-Framing/Rough-in | 9/21/1999 | 9/22/1999 | 9/22/1999 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/21/1999 at 10:31:19. Contact: ###-####. (add energy code.. Ok)
|
BLD-Energy code compliance | 9/22/1999 | 9/22/1999 | 9/22/1999 | A | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 9/20/1999 | 9/21/1999 | 9/21/1999 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/20/1999 at 13:49:55. Contact: ###-####. C/N truss bracing
|
INSP - Framing/Rough-in | 9/14/1999 | 9/14/1999 | 9/14/1999 | P | PART |
Jim Sly
|
|
|
SHEAR WALL OK
|
Issue PAID IN FULL permit | | | 8/25/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/25/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/18/1999 | | |
|
|
|
|
Plan assigned to (DJO) | 8/3/1999 | | 8/17/1999 | | PASS |
Dan Overy
|
|
|
08/17/99 17:25:13 DJO - this action updated by action script from <<>> in Case No. BLD99-2347
|
INSP - Foundation | 8/13/1999 | 8/16/1999 | 8/16/1999 | A | FAIL |
Alan Hauser
|
|
|
08/16/99 350 - early start
|
INSP - Foundation | 8/12/1999 | 8/13/1999 | 8/13/1999 | A | FAIL |
Alan Hauser
|
|
|
08/13/99 350 - poured without inspection
|
INSP - Foundation | 8/11/1999 | 8/12/1999 | 8/12/1999 | A | PART |
Jim Sly
|
|
|
08/12/99 316 - Early start footing appears OK....Single horiz with 16"oc
|
INSP - Foundation | 8/11/1999 | 8/11/1999 | 8/11/1999 | P | CANC |
Jim Sly
|
|
|
FOOTING ###-#### BILL. CANC BY HUGH, RESCHEDULED FOR TOMORROW
|
Print Pending Permit.LaserJet4 | | | 8/4/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/3/1999 | | 8/3/1999 | | PASS |
|
|
|
|
Application received | | | 8/3/1999 | | |
|
|
|
|
Routing - PLANNING | 8/3/1999 | | 8/3/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/3/1999 | | | | PEND |
|
|
|
|