Plan resubmittals received | | | 7/10/2002 | | DONE |
|
|
|
REVISED ELECTRICAL DRAWING FOR RIVER PLAZA OFFICE BUILDING E1.0 E2.0 E3.0 E4.0 GAVE TO PERRY PAINE
|
BLD-Final | 7/3/2001 | 7/3/2001 | 7/3/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/3/2001 2:56:47 PM shell ok for perm...l/c. t/i's need final requests
|
Letter of compliance | | | 7/3/2001 | | DONE |
|
|
|
Letter of Compliance #21556 issued 7-3-01.
|
BLD-Final | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | NR |
Carl Dependahl
|
|
|
april ###-####; need verify achd & other ok's; spoke w/ Titan 6/21/2001 11:07:03 AM
|
BLD-Conference | 3/13/2001 | 3/13/2001 | 3/13/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/13/2001 6:41:37 PM need all sign-offs, complete c/n, draft stops at fl/clgs, waterproofing at ext decks, etc.
|
Telephone call | | | 3/9/2001 | | DONE |
|
|
|
Talked w/Darrel re: status of temp. occ.
|
BLD-Conference | 3/8/2001 | 3/8/2001 | 3/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/8/2001 9:20:23 AM w/ arch re c/n...need 1hr ext wall per plans at east side; prop. line assumed to be at 10'7"...no protected openings
|
BLD-Conference | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/6/2001 6:24:09 PM w/arch re 1hr stair ways
|
Fee Review-notes | 8/6/1999 | | 2/20/2001 | | DONE |
|
|
|
|
BLD-Conference | 2/7/2001 | 2/7/2001 | 2/7/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/7/2001 11:09:26 AM w/ Carr const re t/i & finals
|
Telephone call | | | 2/5/2001 | | PEND |
|
|
|
I received a fax from Shan Miller, Tomlinson & Associates, 242 N. 8th Street, Boise, 83701, ###-#### & ###-#### (fax), for a arvised bid on the completion of the landscaping. The bid appears acceptable. Faxed back instruction to continue with bonding process.
|
BLD-Conference | 1/29/2001 | 1/29/2001 | 1/29/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/29/2001 4:01:16 PM w/ arch onsite re c/n...add gyp at passageway
|
BLD-Conference | 1/25/2001 | 1/25/2001 | 1/25/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/25/2001 2:56:06 PM w/ contractor re c/n of 1-9-01. need add gyp at stairs, etc...both sides of assy.
|
BLD-Conference | 1/18/2001 | 1/18/2001 | 1/18/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/18/2001 9:54:27 AM w/rick jackson re c/n
|
Temporary occupancy | | | 1/18/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4508 issued 1-18-01 to the River Plaza Office Bldg. shell and core.
|
BLD-Conference | 1/17/2001 | 1/17/2001 | 1/17/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/17/2001 4:26:16 PM w/ GS re plans
|
BLD-Final | 1/5/2001 | 1/8/2000 | 1/9/2001 | A | CANC |
Carl Dependahl
|
|
|
DARYL W/TITAN; ###-####.
|
FIRE-Final Inspection | 1/9/2001 | 1/9/2001 | 1/9/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 1/9/2001 8:56:55 AM
|
BLD-Final | 1/9/2001 | 1/9/2001 | 1/9/2001 | P | PART |
Carl Dependahl
|
|
|
Darrel ###-####,c/n issued, ok for t/o 1/9/2001 6:02:41 PM
|
FIRE-Final Inspection | 1/4/2001 | 1/5/2001 | 1/8/2001 | A | FAIL |
Rick Jackson
|
|
|
DARRELL ###-#### FN FIRE sprinkler problems and alarm problems 1/8/2001 11:19:38 AM
|
BLD-Final | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | NR |
Carl Dependahl
|
|
|
FN OCC- DARRELL ###-####
|
Plan resubmittals received | | | 1/5/2001 | | DONE |
|
|
|
Received plan resubmittals from Tamura and AssociatesTwo sets of A2.0and 4 sets of A2.1, forwarded same to Carl Dependahl. 1/5/01 DAR
|
BLD-Final | 1/3/2001 | 1/4/2001 | 1/4/2001 | P | NR |
Carl Dependahl
|
|
|
temp occ- darrell ###-#### need fire, etc. 1/4/2001 4:08:31 PM
|
BLD-Framing/Rough-in | 11/15/2000 | 11/16/2000 | 11/16/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; recd details will review 11/16/2000 4:23:38 PM
|
BLD-Conference | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/15/2000 5:42:14 PM w/ supt.
|
BLD-Framing/Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PART |
Jim Storey
|
|
|
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
|
BLD-Framing/Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PART |
Jim Storey
|
|
|
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
|
Plan resubmittals received | | | 9/5/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM TAMURA AND ASSOCIATES, MARK KNOWLES, ONE SET OF SHEET A8.2 AND SHEET A9.1, FORWARDED SAME TO PERRY PAINE WITH SMALL DOCUMENTS. 9/5/00 DAR
|
BLD-Conference | 8/29/2000 | 8/29/2000 | 9/1/2000 | P | PART |
|
|
|
###-#### need fire signoff 8/29/2000 4:21:10 PM wiht darrell on the exit passageway etc 9/1/2000 10:46:01 AM
|
(F) Reprint permit | | | 8/28/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/24/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/11/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/17/2000 | | 8/10/2000 | | DONE |
|
|
|
PLAN MODIFICATION. Waiting for letter from engineer about adding HVAC units to roof.8/7/00
|
Plan assigned to (M_P) | 6/26/2000 | | 8/10/2000 | | PASS |
Mike Phillips
|
|
|
8/10/2000 12:20:32 M_P - activity updated through activity BLDA022 from case BLD99-02394.
|
Plan Reviewer's activity | | | 8/10/2000 | | PASS |
|
|
|
PLAN MODIFICATION
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2000 | | DONE |
|
|
|
PLAN MODIFICATION
|
Plan Reviewer's activity | | | 8/7/2000 | | PEND |
|
|
|
PLAN MODIFICATION * Waiting for letter from engineer about adding HVAC units on roof.
|
Routing - PLUMBING | 7/11/2000 | | 7/17/2000 | | PASS |
|
|
|
PLAN MODIFICATION. per plan original review and 97 upc
|
Routing - PLANNING | 6/29/2000 | | 7/11/2000 | | PASS |
|
|
|
Approved per DRH99-67.
|
CHANGE STATUS TO (PND) | | | 6/23/2000 | | DONE |
|
|
|
PLAN MODIFICATION FILED BY MARK SANDERS. Sheets submitted are A2.1,A2.2,A2.3,A4.0,A4.2,A5.0,A5.1,A5.2,A10.2,S2.4,M1.1,M1.2,M1.2,M1.4,M2.1,M2.2,M3.1,P1.1,P1.2,P1.3,P1.4,P2.1,E1.0,E2.0,E3.0,E4.0,E5.0. Plans given to Mike Phillips. All plan modification fees to be collected when approved per M. Southard.
|
BLD-Framing/Rough-in | 6/20/2000 | 6/21/2000 | 6/21/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 06/20/2000 at 14:14:31. Contact: ###-####. with darrell 6/21/00 11:11:54 AM
|
BLD-Conference | 5/19/2000 | 5/19/2000 | 5/19/2000 | P | PART |
|
|
|
darrell--###-#### for conf with darrell onthe requiremens for a rated shaft for ducts penetrating floors from roof. code says 1 or 2 strys this is3 story building 5/19/00 5:12:56 PM
|
(F) Reprint permit | | | 4/28/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/27/2000 | | DONE |
|
|
|
|
Routing Off Site - A.C.H.D | 4/24/2000 | 4/24/2000 | 4/24/2000 | | DONE |
|
|
|
As per letter from Larry Sale, Impact fee administrator-This is to advise you that the Ada County Highway District will accept the deferral of payment of applicable impact fees for the subject building until the agreement between ACHD and the Capitol City Development Corporation regarding the use of CCDC credits has been resolved. Letter dated April 21, 2000-mps
|
Telephone call | | | 3/27/2000 | | DONE |
|
|
|
called left message w/mark sanders told him that i will void plans unless he calls me to let me know what the statis is on the plans.Had to add fees to permit. the permit fee and the plan check fee was left out.
|
Telephone call | | | 3/27/2000 | | DONE |
|
|
|
mark called back said that he will be faxing over extension for plans. They are not ready to be picked up.mps
|
Additional plans submitted | | | 1/25/2000 | | DONE |
|
|
|
RECEIVED LETTER TO TIM HOGLAND ADDRESSED TO MIKE P. FROM MARK SANDERS. ROUTED ONE TO TIM, MIKE P. AND PUT ONE IN FILE. (ALTERMATIVE METHOD LETTER). KMM
|
Inspection Record Card- Bld | | | 1/24/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/24/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2000 | | DONE |
|
|
|
called Mark Saunders left message on voice mail permit ready and fees due
|
Routing Off Site - STRUCTURAL | 1/21/2000 | 1/21/2000 | 1/21/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/21/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/21/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/21/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/21/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/15/1999 | | 1/21/2000 | | DONE |
|
|
|
Second review completed waiting for responces from architect.
|
Plan assigned to (M_P) | 8/9/1999 | | 1/21/2000 | | PASS |
Mike Phillips
|
|
|
1/21/2000 15:16:11 M_P - activity updated through activity BLDA022 from case BLD99-02394.
|
Routing Off Site - STRUCTURAL | 1/6/2000 | | 1/20/2000 | | PEND |
|
|
|
CONTACTED PDQ TO TAKE REVISED PLANS AND CALCS. RECEIVED ON 1/6/2000 (ONE COPY) TO OUT SIDE ENG. KMM
1/20/2000 received structural review letter by CH2MHILL dated 1/19/00. Routed to Marlene and Mike P. KMM
|
Plan resubmittals received | | | 1/19/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM MARK SANDERS ARCHETECT, ARCHITECTURAL, STRUCTURAL AND MECHANICAL SHEETS, FORWARDED SAME TO MIKE PHILLIPS. 1/19/00
|
Plan resubmittals requested | | | 1/7/2000 | | FAIL |
|
|
|
Additional informaiton requested for third review, waiting for outside engineering firms response to third review.
|
Plan resubmittals received | | | 1/6/2000 | | DONE |
|
|
|
RECEIVED ONE COPY OF REVISED STRUCT. DRAWINGS SHEETS,S1.0, S2.1, S2.2, S2.3, S2.4, S3.0, S3.1, S3.2, S4.0, PLUS ONE COPY OF REVISED STRUCT. CALCS. ROUTED TO OUTSIDE ENG. PER MIKE P. KMM
|
Plan resubmittals received | | | 1/4/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM TAMURA ARCHITECTS, MARK SANDERS A,S AND M SHEETS PLUS SMALL DOCUMENTSAND STRUCTURAL CACULATIONS, FORWARDED SAME TO MIKE PHILLIPS. 1/4/99 DAR
|
Routing - FIRE | 9/3/1999 | 9/5/1999 | 9/15/1999 | | PASS |
|
|
|
FEDEXED OFFICE COPY TO FLOYD V. MIKE P. HAS RETAINED ISSUE COPY. KMM
9-15-99 RECEIVED PLANS BACK FROM FLOYD. ROUTED OFFICE COPY TO BILL . KMM
|
Plan Review Completed(1st rev) | | | 9/15/1999 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/9/1999 | | 9/3/1999 | | FAIL |
|
|
|
ONE SET OF PLANS SENT TO CONSULTING STRUCTURAL ENGINEERING (ALSO ONE SET OF CACULATIONS INCLUDED. 8/9/99 DAR
Comments were not answered.
|
Plan resubmittals requested | | | 9/2/1999 | | FAIL |
|
|
|
ADDITIONAL INFORMATION REQUESTED TO BE SUBMITTED FOR FURTHER REVIEW.
|
Routing - PLAN CHECK | 8/17/1999 | | 9/2/1999 | | |
|
|
|
ROUTING TO FIRE DEPARTMETN FOR THEIR REVIEW.
|
Routing - PLANNING | 8/13/1999 | | 8/17/1999 | | PASS |
|
|
|
approved per DRH99-0067; note that landscape plan is "redlined" for the Forester's requirements.
|
Routing - PLUMBING | 8/12/1999 | | 8/13/1999 | | PASS |
|
|
|
3" storm drain on 13th street side not shown on civil plan, make approiate changes to plan. min. vent at main waste and vent riser is 4".
|
Routing - PUBLIC WORKS | 8/9/1999 | | 8/12/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | 8/9/1999 | | 8/9/1999 | | |
|
|
|
|
Application received | | | 8/6/1999 | | |
|
|
|
|
Temporary occupancy | | | | | FAIL |
|
|
|
Request for temp occupancy. Landscaping not completed. How to Bond for Temporary Occupancy guide sent to Shan Miller, ###-#### & ###-#### fax.
|
Case Summary (BLD) | | | | | |
|
|
|
|
Routing - PLAN CHECK | 6/23/2000 | | | | |
|
|
|
PLAN MODIFICATION SHEETS NOTED (SEE LIST OF SHEETS IN CHANGE STATUS TO PENDING NOTE) GIVEN TO MIKE PHILLIPS. MYS
|