Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-02394
StatusFinaled
Name URBAN RENEWAL AGENCY OF BOI SE
Site Address 1276 W RIVER ST
Project NameRIVER PLAZA
Customer Number 
ePlanReviewNo
Description
RIVER PLAZA OFFICE BUILDING * TO CONSTRUCT A NEW 3-STORY, WOOD FRAMED, TYPE V ONE-HOUR, FULLY SPRINKLERED, SHELL AND CORE, 26,851 SQUARE FOOT OFFICE BUILDING. THE FIRST FLOOR IS APPROXIMATELY 8,987 SQ.FT THE SECOND FLOOR IS APPROXIMATELY 9,054 SQ.FT THE THIRD FLOOR IS APPROXIMATELY 8,810 SQ.FT. THE INSTALLATION OF THE FIRE SPRINKLER SYSTEM IS USED TO SUBSTITUTE FOR THE ONE-HOUR FIRE-RESISTIVE CONSTRUCTION. ALL WORK PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. FOUNDATION PERMIT IS BLD99-2056. THIS PERMIT IS FOR A SHELL BUILDING ONLY SEPARATE PERMITS REQUIRED FOR EACH FUTURE TENANT SPACE TO BE COMPLETED AND OCCUPIED. THE SECOND AND THIRD FLOORS MUST HAVE THE CORRIDOR FINISHED TO PROVIDE ACCESS TO THE SECOND MEANS OF REQUIRED EGRESS. THIS REQUIREMENT MUST BE FINISHED AT THE TIME OF THE FIRST OCCUPANT. THIS BUILDING IS LOCATED IN THE 100 YEAR FLOOD PLANE AND A CERTIFICATE OF ELEVATION IS REQUIRED TO BE SUBMITTED TO THE STRUCTURAL INSPECTOR PRIOR TO THE FRAMING COMPLETION OF THE FIRST FLOOR. DRH99-0067 PC#619-99 MJP

PLAN MODIFICATION 6/26/00 * PLANS ARE BEING MODIFIED THE EXTERIOR ROOF IS BEING REDESIGNED TO HOUSE ROOF TOP HVAC UNITS WITHIN A MECHANICAL WELL AND INSTALL HVAC DUCTING INTO SHAFTS TO THE SECOND AND FIRST FLOORS. MJP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan resubmittals received  7/10/2002 DONE
REVISED ELECTRICAL DRAWING FOR RIVER PLAZA OFFICE BUILDING E1.0 E2.0 E3.0 E4.0 GAVE TO PERRY PAINE
BLD-Final7/3/20017/3/20017/3/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 7/3/2001 2:56:47 PM shell ok for perm...l/c. t/i's need final requests
Letter of compliance  7/3/2001 DONE
Letter of Compliance #21556 issued 7-3-01.
BLD-Final6/20/20016/21/20016/21/2001ANR
DetailsCarl Dependahl
april ###-####; need verify achd & other ok's; spoke w/ Titan 6/21/2001 11:07:03 AM
BLD-Conference3/13/20013/13/20013/13/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 3/13/2001 6:41:37 PM need all sign-offs, complete c/n, draft stops at fl/clgs, waterproofing at ext decks, etc.
Telephone call  3/9/2001 DONE
Talked w/Darrel re: status of temp. occ.
BLD-Conference3/8/20013/8/20013/8/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 3/8/2001 9:20:23 AM w/ arch re c/n...need 1hr ext wall per plans at east side; prop. line assumed to be at 10'7"...no protected openings
BLD-Conference3/6/20013/6/20013/6/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 3/6/2001 6:24:09 PM w/arch re 1hr stair ways
Fee Review-notes8/6/1999 2/20/2001 DONE
BLD-Conference2/7/20012/7/20012/7/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 2/7/2001 11:09:26 AM w/ Carr const re t/i & finals
Telephone call  2/5/2001 PEND
I received a fax from Shan Miller, Tomlinson & Associates, 242 N. 8th Street, Boise, 83701, ###-#### & ###-#### (fax), for a arvised bid on the completion of the landscaping. The bid appears acceptable. Faxed back instruction to continue with bonding process.
BLD-Conference1/29/20011/29/20011/29/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/29/2001 4:01:16 PM w/ arch onsite re c/n...add gyp at passageway
BLD-Conference1/25/20011/25/20011/25/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/25/2001 2:56:06 PM w/ contractor re c/n of 1-9-01. need add gyp at stairs, etc...both sides of assy.
BLD-Conference1/18/20011/18/20011/18/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/18/2001 9:54:27 AM w/rick jackson re c/n
Temporary occupancy  1/18/2001 PART
Temp. Occ. Cert. #4508 issued 1-18-01 to the River Plaza Office Bldg. shell and core.
BLD-Conference1/17/20011/17/20011/17/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/17/2001 4:26:16 PM w/ GS re plans
BLD-Final1/5/20011/8/20001/9/2001ACANC
DetailsCarl Dependahl
DARYL W/TITAN; ###-####.
FIRE-Final Inspection1/9/20011/9/20011/9/2001APASS
DetailsRick Jackson
Scheduled by Inspector: 409 On 1/9/2001 8:56:55 AM
BLD-Final1/9/20011/9/20011/9/2001PPART
DetailsCarl Dependahl
Darrel ###-####,c/n issued, ok for t/o 1/9/2001 6:02:41 PM
FIRE-Final Inspection1/4/20011/5/20011/8/2001AFAIL
DetailsRick Jackson
DARRELL ###-#### FN FIRE sprinkler problems and alarm problems 1/8/2001 11:19:38 AM
BLD-Final1/4/20011/5/20011/5/2001ANR
DetailsCarl Dependahl
FN OCC- DARRELL ###-####
Plan resubmittals received  1/5/2001 DONE
Received plan resubmittals from Tamura and AssociatesTwo sets of A2.0and 4 sets of A2.1, forwarded same to Carl Dependahl. 1/5/01 DAR
BLD-Final1/3/20011/4/20011/4/2001PNR
DetailsCarl Dependahl
temp occ- darrell ###-#### need fire, etc. 1/4/2001 4:08:31 PM
BLD-Framing/Rough-in11/15/200011/16/200011/16/2000APART
DetailsCarl Dependahl
###-####; recd details will review 11/16/2000 4:23:38 PM
BLD-Conference11/15/200011/15/200011/15/2000PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 11/15/2000 5:42:14 PM w/ supt.
BLD-Framing/Rough-in10/23/200010/24/200010/24/2000APART
DetailsJim Storey
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
BLD-Framing/Rough-in10/23/200010/24/200010/24/2000APART
DetailsJim Storey
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
Plan resubmittals received  9/5/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM TAMURA AND ASSOCIATES, MARK KNOWLES, ONE SET OF SHEET A8.2 AND SHEET A9.1, FORWARDED SAME TO PERRY PAINE WITH SMALL DOCUMENTS. 9/5/00 DAR
BLD-Conference8/29/20008/29/20009/1/2000PPART
Details
###-#### need fire signoff 8/29/2000 4:21:10 PM wiht darrell on the exit passageway etc 9/1/2000 10:46:01 AM
(F) Reprint permit  8/28/2000 DONE
Issue PAID IN FULL permit  8/24/2000 DONE
Inspection Record Card- Bld  8/11/2000 DONE
Routing - PLAN CHECK7/17/2000 8/10/2000 DONE
PLAN MODIFICATION. Waiting for letter from engineer about adding HVAC units to roof.8/7/00
Plan assigned to (M_P)6/26/2000 8/10/2000 PASS
DetailsMike Phillips
8/10/2000 12:20:32 M_P - activity updated through activity BLDA022 from case BLD99-02394.
Plan Reviewer's activity  8/10/2000 PASS
PLAN MODIFICATION
PLANS/APPL TAKEN TO FRONT DESK  8/10/2000 DONE
PLAN MODIFICATION
Plan Reviewer's activity  8/7/2000 PEND
PLAN MODIFICATION * Waiting for letter from engineer about adding HVAC units on roof.
Routing - PLUMBING7/11/2000 7/17/2000 PASS
PLAN MODIFICATION. per plan original review and 97 upc
Routing - PLANNING6/29/2000 7/11/2000 PASS
Approved per DRH99-67.
CHANGE STATUS TO (PND)  6/23/2000 DONE
PLAN MODIFICATION FILED BY MARK SANDERS. Sheets submitted are A2.1,A2.2,A2.3,A4.0,A4.2,A5.0,A5.1,A5.2,A10.2,S2.4,M1.1,M1.2,M1.2,M1.4,M2.1,M2.2,M3.1,P1.1,P1.2,P1.3,P1.4,P2.1,E1.0,E2.0,E3.0,E4.0,E5.0. Plans given to Mike Phillips. All plan modification fees to be collected when approved per M. Southard.















BLD-Framing/Rough-in6/20/20006/21/20006/21/2000APART
Details
Scheduled by a contractor via Hello! on 06/20/2000 at 14:14:31. Contact: ###-####. with darrell 6/21/00 11:11:54 AM
BLD-Conference5/19/20005/19/20005/19/2000PPART
Details
darrell--###-#### for conf with darrell onthe requiremens for a rated shaft for ducts penetrating floors from roof. code says 1 or 2 strys this is3 story building 5/19/00 5:12:56 PM
(F) Reprint permit  4/28/2000 DONE
Issue PAID IN FULL permit  4/27/2000 DONE
Routing Off Site - A.C.H.D4/24/20004/24/20004/24/2000 DONE
As per letter from Larry Sale, Impact fee administrator-This is to advise you that the Ada County Highway District will accept the deferral of payment of applicable impact fees for the subject building until the agreement between ACHD and the Capitol City Development Corporation regarding the use of CCDC credits has been resolved. Letter dated April 21, 2000-mps
Telephone call  3/27/2000 DONE
called left message w/mark sanders told him that i will void plans unless he calls me to let me know what the statis is on the plans.Had to add fees to permit. the permit fee and the plan check fee was left out.
Telephone call  3/27/2000 DONE
mark called back said that he will be faxing over extension for plans. They are not ready to be picked up.mps
Additional plans submitted  1/25/2000 DONE
RECEIVED LETTER TO TIM HOGLAND ADDRESSED TO MIKE P. FROM MARK SANDERS. ROUTED ONE TO TIM, MIKE P. AND PUT ONE IN FILE. (ALTERMATIVE METHOD LETTER). KMM
Inspection Record Card- Bld  1/24/2000 DONE
Print Occupancy Form  1/24/2000 DONE
Telephone call  1/24/2000 DONE
called Mark Saunders left message on voice mail permit ready and fees due
Routing Off Site - STRUCTURAL1/21/20001/21/20001/21/2000 DONE
Plan Reviewer's activity  1/21/2000 DONE
Print Pending Permit.LaserJet4  1/21/2000 DONE
Case Summary (BLD)  1/21/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/21/2000 DONE
Routing - PLAN CHECK9/15/1999 1/21/2000 DONE
Second review completed waiting for responces from architect.
Plan assigned to (M_P)8/9/1999 1/21/2000 PASS
DetailsMike Phillips
1/21/2000 15:16:11 M_P - activity updated through activity BLDA022 from case BLD99-02394.
Routing Off Site - STRUCTURAL1/6/2000 1/20/2000 PEND
CONTACTED PDQ TO TAKE REVISED PLANS AND CALCS. RECEIVED ON 1/6/2000 (ONE COPY) TO OUT SIDE ENG. KMM
1/20/2000 received structural review letter by CH2MHILL dated 1/19/00. Routed to Marlene and Mike P. KMM
Plan resubmittals received  1/19/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM MARK SANDERS ARCHETECT, ARCHITECTURAL, STRUCTURAL AND MECHANICAL SHEETS, FORWARDED SAME TO MIKE PHILLIPS. 1/19/00
Plan resubmittals requested  1/7/2000 FAIL
Additional informaiton requested for third review, waiting for outside engineering firms response to third review.
Plan resubmittals received  1/6/2000 DONE
RECEIVED ONE COPY OF REVISED STRUCT. DRAWINGS SHEETS,S1.0, S2.1, S2.2, S2.3, S2.4, S3.0, S3.1, S3.2, S4.0, PLUS ONE COPY OF REVISED STRUCT. CALCS. ROUTED TO OUTSIDE ENG. PER MIKE P. KMM
Plan resubmittals received  1/4/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM TAMURA ARCHITECTS, MARK SANDERS A,S AND M SHEETS PLUS SMALL DOCUMENTSAND STRUCTURAL CACULATIONS, FORWARDED SAME TO MIKE PHILLIPS. 1/4/99 DAR
Routing - FIRE9/3/19999/5/19999/15/1999 PASS
FEDEXED OFFICE COPY TO FLOYD V. MIKE P. HAS RETAINED ISSUE COPY. KMM
9-15-99 RECEIVED PLANS BACK FROM FLOYD. ROUTED OFFICE COPY TO BILL . KMM
Plan Review Completed(1st rev)  9/15/1999 PEND
Routing Off Site - STRUCTURAL8/9/1999 9/3/1999 FAIL
ONE SET OF PLANS SENT TO CONSULTING STRUCTURAL ENGINEERING (ALSO ONE SET OF CACULATIONS INCLUDED. 8/9/99 DAR
Comments were not answered.
Plan resubmittals requested  9/2/1999 FAIL
ADDITIONAL INFORMATION REQUESTED TO BE SUBMITTED FOR FURTHER REVIEW.
Routing - PLAN CHECK8/17/1999 9/2/1999
ROUTING TO FIRE DEPARTMETN FOR THEIR REVIEW.
Routing - PLANNING8/13/1999 8/17/1999 PASS
approved per DRH99-0067; note that landscape plan is "redlined" for the Forester's requirements.
Routing - PLUMBING8/12/1999 8/13/1999 PASS
3" storm drain on 13th street side not shown on civil plan, make approiate changes to plan. min. vent at main waste and vent riser is 4".
Routing - PUBLIC WORKS8/9/1999 8/12/1999 PASS
Plans ACCEPTED BY PLAN TECH8/9/1999 8/9/1999
Application received  8/6/1999
Temporary occupancy    FAIL
Request for temp occupancy. Landscaping not completed. How to Bond for Temporary Occupancy guide sent to Shan Miller, ###-#### & ###-#### fax.
Case Summary (BLD)     
Routing - PLAN CHECK6/23/2000    
PLAN MODIFICATION SHEETS NOTED (SEE LIST OF SHEETS IN CHANGE STATUS TO PENDING NOTE) GIVEN TO MIKE PHILLIPS. MYS