Fee Review-notes | 6/18/2003 | 6/18/2003 | 6/18/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/8/2000 | | DONE |
|
|
|
|
Fee Review-notes | 1/7/2000 | 1/7/2000 | 6/20/2000 | | DONE |
|
|
|
ele-45,800.00 plm23,800.00 mech33,564.00//9/11/00-office called said they were sending check...lh
|
BLD-Final | 6/7/2000 | 6/8/2000 | 6/8/2000 | A | PASS |
Tom Arcoraci
|
|
|
rick ###-#### fn OK FOR PERM
|
Permanent occupancy | | | 6/8/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8254 issued 6-8-00 to S.T. Investments.
|
Permanent Occupancy | | 6/7/2000 | 6/7/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/31/2000 | 6/1/2000 | 6/1/2000 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/31/2000 at 13:07:10. Contact: ###-####. Final ok for permanent occ. 6/1/00 2:34:52 PM
|
FIRE-Hydro test above ground | 5/15/2000 | 5/15/2000 | 5/15/2000 | P | PART |
Joe Tawney
|
|
|
Charles Lamb ###-#### Ok on above ground hydro test. 5/16/00 10:04:36 AM
|
BLD-Other | 5/11/2000 | 5/12/2000 | 5/12/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/11/2000 at 13:03:57. Contact: ###-####. Grid ok 5/15/00 10:55:49 AM
|
FIRE-Hydro test above ground | 5/10/2000 | 5/11/2000 | 5/11/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/10/2000 at 13:23:33. Contact: ###-####. Not ready for hydro test. 5/11/00 2:42:51 PM
|
BLD-Framing/Rough-in | 3/31/2000 | 4/3/2000 | 4/3/2000 | A | FAIL |
Tom Arcoraci
|
|
|
###-#### See C/N 4/3/00 1:27:12 PM
|
FIRE-Sprinkler Rough-in | 4/3/2000 | 4/3/2000 | 4/3/2000 | P | PART |
Joe Tawney
|
|
|
###-#### Ok R/I of 4 restrooms conf. on AHV duct detectors 4/4/00 9:28:33 AM
|
BLD-Framing/Rough-in | 3/30/2000 | 3/31/2000 | 3/31/2000 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### RICK Not ready 4/3/00 8:49:25 AM
|
BLD-Other | 2/9/2000 | 2/9/2000 | 2/9/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/09/2000 at 10:40:34. Contact: ###-####. Grout pour
|
BLD-Other | 2/8/2000 | 2/8/2000 | 2/8/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 08:09:05. Contact: ###-####.
|
BLD-Other | 2/4/2000 | 2/7/2000 | 2/7/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/04/2000 at 16:42:41. Contact: ###-####. Grout pour. 2/7/00 1:31:29 PM
|
BLD-Other | 2/3/2000 | 2/3/2000 | 2/3/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 09:18:18. Contact: ###-####. Grout pour ok. 2/4/00 11:29:50 AM
|
BLD-Other | 1/31/2000 | 2/1/2000 | 2/1/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/31/2000 at 14:52:04. Contact: ###-####. grout pour 2/1/00 2:11:49 PM partial grout pour 2/1/00 2:46:00 PM
|
BLD-Other | 1/25/2000 | 1/25/2000 | 1/25/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/25/2000 at 09:38:47. Contact: ###-####. 1st pour 4ft masonry. 1/26/00 8:57:34 AM
|
FIRE-Supply Line Cover | 12/28/1999 | 12/29/1999 | 12/29/1999 | A | PART |
Joe Tawney
|
|
|
Terry Nelson ###-####. Ok for supply line cover.
|
BLD-Footing | 12/23/1999 | 12/27/1999 | 12/27/1999 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/23/1999 at 09:08:02. Contact: ###-####. Ft. ok bar ok.
|
BLD-Footing | 12/27/1999 | 12/27/1999 | 12/27/1999 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 09:39:16. Contact: ###-####. Interior ft ok for cover, bar ok.
|
BLD-Footing | 12/22/1999 | 12/23/1999 | 12/23/1999 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/22/1999 at 14:10:12. Contact: ###-####. NR recall.
|
BLD-Footing | 12/21/1999 | 12/21/1999 | 12/21/1999 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/21/1999 at 10:31:12. Contact: ###-####. Wall ok.
|
BLD-Footing | 12/16/1999 | 12/20/1999 | 12/20/1999 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/16/1999 at 11:27:39. Contact: ###-####. Ext. footings ok.
|
(F) Reprint permit | | | 12/6/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/3/1999 | | DONE |
|
|
|
achd fees paid 00-09265
|
Inspection Record Card- Bld | | | 11/9/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/9/1999 | | DONE |
|
|
|
called Mike Baker at ###-####. permit ready and fees due. also need an ACHD certificate upon pick up. faxed a break down of fees.
|
Routing - PLAN CHECK | 11/3/1999 | 11/3/1999 | 11/8/1999 | | PASS |
|
|
|
ONLY THE PERMIT COPY WAS ROUTED TO PLAN CHECK. THE OFFICE COPY WAS SENT TO FLOYD.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/1999 | | PASS |
|
|
|
PERMIT COPY SENT TO FRONT DESK FOR ISSUE. THE OFFICE COPY HAS NOT YET RETURNED FROM FLOYD.
|
Inspection Record Card- Bld | | | 11/8/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/8/1999 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 8/11/1999 | | 11/8/1999 | | PASS |
John Menard
|
|
|
11/8/1999 13:32:14 JCM - activity updated through activity BLDA022 from case BLD99-02399.
|
Routing - FIRE | 11/1/1999 | 11/1/1999 | 11/3/1999 | | PASS |
|
|
|
ROUTED OFFICE COPY TO FLOYD FOR PLAN REVIEW. ROUTED ISSUE COPY BACK TO BILL TO HOLD UNTIL ISSUE COPY IS BACK FROM FLOYD. KMM. Received comments. Modified attached and issued approval. jwa.
11/9/99 RECEIVED OFFICE COPY BACK FROM FLOYD. DID NOT FAX RESPONSE TO ARCH. PER BILL A. ROUTED OFFICE COPY BACK TO JOHN M. FIRE NEEDS TO SIGN OFF. KMM
|
Routing - PLAN CHECK | 10/27/1999 | 10/27/1999 | 11/1/1999 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 10/25/1999 | 10/25/1999 | 10/27/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/24/1999 | | 10/25/1999 | | |
|
|
|
|
Routing - PLANNING | 8/30/1999 | 9/8/1999 | 9/13/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/13/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ROGER FOSTER, BRS ARCHITECTS, FORWARDED SAME TO MIKE PHILLIPS. 9/14/99 DAR
|
Plan resubmittals requested | | | 9/8/1999 | | PEND |
|
|
|
FAXED ROGER FOSTER AT BRS A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing - FIRE | 9/2/1999 | 9/8/1999 | 9/7/1999 | | FAIL |
|
|
|
Need complete water supply information for fire sprinkler design. Needed riser relocated or verification the underground water supply will not be burried under the floor of the building, etc.
|
Routing Off Site - STRUCTURAL | 8/12/1999 | | 9/7/1999 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan Review Completed(1st rev) | | | 9/7/1999 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 9/2/1999 | | PASS |
|
|
|
PLANS REVIEWED AND APPROVED AS SUBMITTED WITH ATTACHED PLAN REVIEW COMMENT LIST AND PLAN RELINED NOTES.
|
Routing - PLUMBING | 8/20/1900 | | 8/24/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/13/1999 | | 8/19/1999 | | FAIL |
|
|
|
requires street light plan REQUIRES STREET LIGHT PLAN PER BILL COLSON. REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 08/20/99 DAR
|
Plan resubmittals received | | | 8/18/1999 | | |
|
|
|
RECEIVED MISSING SHEET A-5 ROUTED ONE COPY TO OUTSIDE ENG. VIA PDQ THE COPIES TO JOHN M. KMM
|
Routing - PLANNING | 8/12/1999 | | 8/13/1999 | | FAIL |
|
|
|
A revised landscape plan which complies with DRH99-0017 conditions of approval must be submitted to Staff for review and approval (see August 13, 1999 letter to Roger Foster, BRS, in DRH99-0017 file).
|
Plans ACCEPTED BY PLAN TECH | | | 8/11/1999 | | PEND |
|
|
|
SHEET A-5 MISSING. CONTACTED ARCH. OF THIS NEED. KMM
|
Plan routing begun/TENANTS | | | 8/11/1999 | | PASS |
|
|
|
WILL ROUTE TO P&Z FIRST. CANNOT ROUTE TO PW UNTIL I RECEIVE APPLICATIONS FOR THE GAS ISLAND CANOPY AND CARWASH WHICH ARE PART OF PHASE I. PHASE I CONTAINS THE GRADING AND DRAINAGE FOR ALL OF THESE PROJECTS. KMM
|
Application received | | | 8/9/1999 | | |
|
|
|
|
Received Certificate of Value | | | 8/9/1999 | | PASS |
|
|
|
|