Permit Information
Permit NumberBLD99-02437
StatusFinaled
Name BOISE CONTEMPORARY THEATER
Site Address 520 S 9TH ST
Project NameBOISE CONTEMPORARY THEATER
Customer Number 
ePlanReviewNo
Description
(BOISE CONTEMPORARY THEATRE) Fire sprinklers substitute for 1-hr fire-resistive construction of the building. To convert a former warehouse to an assembly occupancy (220 seat theater) with supporting uses. Work is to include 4 restrooms accessible to the disabled, interior non-bearing walls, elevated seating, interior and exterior stairways, elevator and shaft, fire sprinkler system, elevated exterior "dock", new 2nd level floor structure, and new 2nd level roof structure all per approved drawings, engineering, and plan review conditions on file. The fire sprinkler system shall comply with NFPA 13-1996 as regulated by the Fire Department. PC-643-99 **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Additional values from subcontractors.
Permanent Occupancy 11/22/200011/22/2000 DONE
Details
BLD-Final11/22/200011/22/200011/22/2000PPASS
DetailsCarl Dependahl
###-####; ok for c/o. 11/22/2000 2:43:20 PM
FIRE-Final Inspection11/22/200011/22/200011/22/2000PPASS
DetailsRick Jackson
reinspection ###-#### /// update of records - passed final 11/22/2000 4:11:32 PM
Permanent occupancy  11/22/2000 DONE
Perm. Occ. Cert. #8480 issued 11-22-00 to the Boise Contemporary Theater.
BLD-Final11/20/200011/21/200011/21/2000ANR
DetailsCarl Dependahl
###-####, recall on 22nd 11/21/2000 11:56:13 AM
BLD-Conference11/21/200011/21/200011/21/2000APART
DetailsCarl Dependahl
Added by Inspector: 340 On 11/21/2000 11:03:12 AM w/bldr, need elec...address now on Fulton???
Fee Review-notes8/11/1999 7/25/2000 DONE
BLD-Final5/19/20005/19/20005/19/2000PPART
Details
mid afternoon per John...338 temp occ ok 310 signed for 338 5/22/00 9:57:13 AM
Temporary occupancy  5/19/2000 PART
Temp. Occ. Cert. #4017 issued 5-19-00 to Boise Contemporary Theater.
BLD-Other5/17/20005/18/20005/18/2000PFAIL
Details
Scheduled by a contractor via Hello! on 05/17/2000 at 19:07:31. Contact: ###-####. not ready for insp and occ req not signed , did not go onto jobsite 5/19/00 8:58:06 AM
FIRE-Final Inspection5/17/20005/17/20005/17/2000PFAIL
DetailsRick Jackson
###-#### Not complete per plans. 5/18/00 3:11:30 PM
FIRE-Final Inspection5/4/20005/5/20005/5/2000AFAIL
DetailsRick Jackson
matt ###-#### Sprinkler final- C/N issued. 5/11/00 10:50:40 AM
FIRE-Supply Line Flush4/25/20004/26/20004/26/2000PPASS
DetailsRick Jackson
###-#### Flush ok 4/28/00 8:49:37 AM
BLD-Framing/Rough-in4/20/20004/20/20004/20/2000PPART
Details
###-#### with 409, and contractor super on the placement of exit signage and stair enclosure drywall framing 04/21/2000 8:13:19 AM
FIRE-Conference4/20/20004/20/20004/20/2000PPART
DetailsRick Jackson
###-#### Discussed with skip and Perry exit signs and locations. 4/21/00 9:14:39 AM
BLD-Framing/Rough-in4/12/20004/12/20004/12/2000PPART
Details
###-#### ok to cover restrooms main level 04/12/2000 04/12/2000
FIRE-Sprinkler Rough-in4/10/20004/11/20004/11/2000PFAIL
DetailsRick Jackson
first floor Matt ###-#### at 2pm Obstructions in hallway 4/17/00 1:54:55 PM
BLD-Conference4/7/20004/10/20004/10/2000PCANC
Details
###-####. rescheduled by 325.
BLD-Framing/Rough-in3/3/20003/6/20003/6/2000APART
Details
Scheduled by a contractor via Hello! on 03/03/2000 at 14:23:01. Contact: ###-####. strapping complete for the roof diaphram ok to deck 3/6/00 10:44:05 AM
BLD-Conference3/2/20003/3/20003/3/2000APART
Details
skip ###-#### installing shear bolting for roof diaphram per plans 3/6/00 10:26:22 AM
BLD-Framing/Rough-in2/21/20002/23/20002/23/2000APART
Details
Scheduled by a contractor via Hello! on 02/21/2000 at 14:54:43. Contact: ###-####. strapping in the new mez floor 2/23/00 11:01:27 AM
BLD-Conference2/16/20002/16/20002/16/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/16/2000 at 09:21:40. Contact: ###-####. basement sprinkler piping height acceptable meets 7ft. elv. in most areas in exit corridor. 6" worse case at side wall location. Thrust block need revised to maintain greatest width possible. 2/17/00 10:08:21 AM
BLD-Framing/Rough-in2/8/20002/9/20002/9/2000APART
Details
Scheduled by a contractor via Hello! on 02/08/2000 at 11:58:50. Contact: ###-####. ok to cover basement hallway 2/10/00 10:23:50 AM
BLD-Foundation1/24/20001/25/20001/25/2000APART
Details
Scheduled by a contractor via Hello! on 01/24/2000 at 14:52:24. Contact: ###-####. pending sp insp approvals 1/26/00 7:57:11 AM
FIRE-Sprinkler Rough-in1/24/20001/25/20001/25/2000AFAIL
DetailsRick Jackson
per rick 11:00 ????--tracy ###-####--- 200 lbs for 2 hrs Not complete or ready for test. 1/25/00 1:35:00 PM
Issue PAID IN FULL permit  12/9/1999 DONE
Routing - PLAN CHECK12/7/1999 12/8/1999 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/8/1999 PASS
Print Occupancy Form  12/8/1999 DONE
Inspection Record Card- Bld  12/8/1999 DONE
Telephone call  12/8/1999 DONE
called Skip Jones at ###-####. Permit ready and fees due, ACHD.
Plan assigned to (CJW)8/16/1999 12/8/1999 PASS
DetailsCarl Westfall
12/8/99 10:05:24 CJW - activity updated through activity BLDA022 from case BLD99-02437.
Routing - PLANNING12/3/1999 12/7/1999 PASS
Historic Design Review modification approved for change to concrete block elevator tower.
Routing - PLAN CHECK10/13/1999 12/2/1999  
Plan resubmittals received  12/1/1999 DONE
RECEIVED TWO COPIES OF REVISED SHEETS 1 OF 1 AND 2 OF 2 FROM QUADRANT. DATED 11-29-99. TWO COPIES OF TEMP. LICENSE AGREEMENT PM#1###-####. TWO COPIES OF LETTER FROM ADA COUNTY HIGHWAY DISTRICT. ROUTED TO CARL W. KMM
Plan Reviewer's activity  11/5/1999 PEND
Waiting for license agreement from ACHD.
Routing Off Site - STRUCTURAL10/27/1999 11/4/1999  
CONTACTED PDQ TO TAKE RESUBMITTAL DATED 10/26/99 TO OUTSIDE ENG. KMM 11/4/99 RECEIVED STRUCT. REVIEW LETTER AND STAMPED AND SIGNED SUPPLEMENTAL STRUCT. CALCS. BACK FROM OUTSIDE ENG. ROUTED TO CARL WESTFALL. KMM
BLD-Concrete10/26/199910/26/199910/26/1999APART
Details
With super. on work going on w/o permits at 516 S. 9th
Plan resubmittals received  10/26/1999 PEND
Receilved plan resubmittals from Armstrong Architects, Margie Kennedy, forwarded same to Carl Westfall. 10/27/99 DAR
Plan resubmittals received  10/19/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM ARMSTRONG ARCHITECTS, MARGIE KENNEDY, FORWARDED SAME TO CARL WESTFALL.. 10/19/99 DAR
Plan Review Completed(1st rev)  10/9/1999 PEND
Routing - FIRE10/4/1999 10/9/1999 PASS
Review received 10/11/99./jwa FED EXED OFFICE COPY TO FLOYD. KMM
Routing - PLAN CHECK8/31/1999 10/4/1999  
Routing - PUBLIC WORKS9/28/1999 9/29/1999 PASS
Routing - PLANNING9/29/1999 9/29/1999  
HISTORICAL REVIEW OF DESIGN REVIEW IS SCHEDULED FOR OCTOBER 18TH, 1999. 9/29/99 DAR
Plan resubmittals received  9/22/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM MARGIE KENNEDY OF ARMSTRONG ARCHITECTS, FORWARDED SAME TO CARL WESTFALL. 9/22/99 DAR
Plan resubmittals received  9/14/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM MARGIE KENNEDY OF ARMSTRONG ARCHITECTS, FORWARDED SAME TO CARL WESTFALL. 9/14/99 DAR
Plan resubmittals requested  9/8/1999  
Marjie Kennedy, architect's rep., was contacted Sept. 8, 1999 and told that the City never received structural drawings in the original submittal. Before a structural review can be done the drawings must be submitted.
Plan Reviewer's activity  9/3/1999  
UBC plan review started September 3, 1999 and finished October 4, 1999. Completion of the review was delayed because structural sheets were not available. A response from the architect is required. See the conditions list.
Routing - PLUMBING8/26/1999 8/31/1999 PASS
Routing - PUBLIC WORKS8/20/1999 8/26/1999  
ARCHITECT TO FURNISH FIXTURE DRAWINGS PER LOUISE WALDORF. 8/26/99 DAR
Routing - PLANNING8/20/1999 8/20/1999 FAIL
Concrete block elevator not approved by Historic Commission.
Routing - PLANNING8/16/1999 8/20/1999 PEND
Pending approval of Historic Design Review.
Plan assigned to (MYS)8/11/1999 8/16/1999
DetailsMarlene Southard
Plan routing begun/TENANTS  8/16/1999
Route to PLANNING (Dave Abo/Tempra Wilson), PUBLIC WORKS, PLUMBING, PLAN CHECK, and FIRE.
Plans ACCEPTED BY PLAN TECH  8/12/1999 PEND
Application received  8/11/1999
Routing Off Site - C.D.H8/17/1999 8/1/1979 PASS
Case Summary (BLD)     
Plan Review Report     
Routing Off Site - STRUCTURAL8/12/1999    
SENT A SET OF PLANS TO CONSULTANTING ENGINEER VIA PDQ.8/12/99 DAR
Routing Off Site - STRUCTURAL9/14/1999   PEND
SENT RESUBMITTALS TO STRUCTURAL ENGINEERING CONSULANT. 9/14/99 DAR
Routing Off Site - STRUCTURAL11/5/1999   PASS
Recieved notice from Howie Henrickson, consultant engineer, that all his concerns were resolved.