DOC - Permit Finaled | 1/30/2001 | 1/30/2001 | 1/30/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 1/30/2001 5:03:42 PM
|
BLD-Final | 1/7/2000 | 1/7/2000 | 1/7/2000 | P | PASS |
Jim Sly
|
|
|
###-####. C/C #17356.
|
BLD-Framing/Rough-in | 10/28/1999 | 10/29/1999 | 10/29/1999 | P | PART |
Tom Arcoraci
|
|
|
###-#### --ERNIE Ok to cover per Jim Sly
|
BLD-Framing/Rough-in | 10/26/1999 | 10/27/1999 | 10/27/1999 | P | FAIL |
Jim Sly
|
|
|
ernie ###-#### Need mech approval- do not cover
|
BLD-Framing/Rough-in | 10/25/1999 | 10/25/1999 | 10/25/1999 | P | FAIL |
Jim Sly
|
|
|
ernie ###-#### C/N truss corr.
|
BLD-Framing/Rough-in | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | PART |
Jim Sly
|
|
|
Ernie ###-####//shear wall ok
|
BLD-Framing/Rough-in | 10/5/1999 | 10/6/1999 | 10/6/1999 | A | FAIL |
Jim Sly
|
|
|
ERNIE ###-#### SHEAR WALL INSP not ready
|
INSP - Foundation | 8/27/1999 | 8/30/1999 | 8/30/1999 | A | PART |
Jim Sly
|
|
|
08/30/99 316 - Foot and rebar sppears OK
|
Issue PAID IN FULL permit | | | 8/26/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/23/1999 | | PEND |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/1999 | | |
|
|
|
|
Plan assigned to (SAM) | 8/21/1999 | | 8/23/1999 | | PASS |
Steve Munroe
|
|
|
08/23/99 09:22:30 SAM - this action updated by action script from <<>> in Case No. BLD99-2451
|
Plan assigned to (DJO) | 8/13/1999 | | 8/21/1999 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 8/13/1999 | | 8/17/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/13/1999 | | 8/17/1999 | | PASS |
|
|
|
|
Application received | | | 8/13/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 8/17/1999 | | | | PEND |
|
|
|
|