BLD-Final | 6/13/2000 | 6/14/2000 | 6/14/2000 | A | PASS |
Russ Owen
|
|
|
###-#### Guardrails for front & rear on order, doors keylocked. 6/14/00 3:35:11 PM
|
FIRE-Final Inspection | 6/12/2000 | 6/13/2000 | 6/13/2000 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/12/2000 at 13:32:48. Contact: ###-####. Unable to do 6/14/00 8:52:45 AM
|
BLD-Final | 6/6/2000 | 6/7/2000 | 6/7/2000 | P | NR |
Russ Owen
|
|
|
john ###-####\\needs terry records approval prior to inspecton
|
BLD-Grading Inspection | 6/7/2000 | 6/7/2000 | 6/7/2000 | | BOND |
Rita DeYoung
|
|
|
Grading is complete but revegetation is not. For this the engineer has recommended a $400.00 bond. Upon receipt of this bond the grading is conditionally approved.
|
BLD-Final | 6/5/2000 | 6/6/2000 | 6/6/2000 | P | NR |
Russ Owen
|
|
|
john ###-####
|
BLD-Framing/Rough-in | 3/31/2000 | 3/31/2000 | 3/31/2000 | P | PASS |
Tom Arcoraci
|
|
|
###-#### S/W ok 4/3/00 8:48:12 AM
|
BLD-Framing/Rough-in | 3/29/2000 | 3/30/2000 | 3/30/2000 | A | FAIL |
Wes Worcester
|
|
|
interior sheer ###-#### Interior shear @ dining rm not done. 3/31/00 8:53:23 AM
|
BLD-Framing/Rough-in | 3/20/2000 | 3/21/2000 | 3/21/2000 | A | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/17/2000 | 3/20/2000 | 3/20/2000 | A | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 03/17/2000 at 15:45:36. Contact: ###-####. Not ready 3/22/00 9:15:18 AM
|
BLD-Framing/Rough-in | 3/16/2000 | 3/17/2000 | 3/17/2000 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### See C/N 3/20/00 10:24:47 AM
|
BLD-Framing/Rough-in | 3/15/2000 | 3/16/2000 | 3/16/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-#### C/N fireblocks, 1st fl. shear panels (bsmnt.) ok to insul. 3/17/00 10:25:39 AM
|
BLD-Framing/Rough-in | 3/14/2000 | 3/15/2000 | 3/15/2000 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/14/2000 at 15:39:37. Contact: . Bob to re-sched. 3/16/00 1:29:00 PM
|
BLD-Framing/Rough-in | 3/10/2000 | 3/14/2000 | 3/14/2000 | A | PART |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 03/10/2000 at 12:09:23. Contact: ###-####. please do first thing Shear inspection only- no truss engineering- shear ok. 3/16/00 11:28:38 AM
|
BLD-Framing/Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 | P | PART |
Wes Worcester
|
|
|
|
BLD-Wall cover | 3/3/2000 | 3/6/2000 | 3/6/2000 | A | PART |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 12:48:12. Contact: ###-####. #2-3 & 6 not done- do per other & recall. 3/7/00 9:23:05 AM
|
BLD-Framing/Rough-in | 2/25/2000 | 2/28/2000 | 2/28/2000 | A | FAIL |
Wes Worcester
|
|
|
sheer inspection john ###-#### Shear nailing not to plan in 1 & 3 area need staple conversion from engineer check per. plan. 2/28/00 2:38:15 PM
|
BLD-Framing/Rough-in | 2/23/2000 | 2/24/2000 | 2/24/2000 | A | FAIL |
Russ Owen
|
|
|
###-#### No approved plans on site. 2/24/00 1:39:22 PM
|
BLD-Foundation | 11/15/1999 | 11/16/1999 | 11/16/1999 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/15/1999 at 17:17:17. Contact: ###-####. Garage walls.
|
BLD-Foundation | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 08:45:41. Contact: ###-####. Walls ok.
|
BLD-Footing | 10/28/1999 | 10/29/1999 | 10/29/1999 | A | PART |
Wes Worcester
|
|
|
john ###-#### need engineers letter still
|
BLD-Footing | 10/27/1999 | 10/28/1999 | 10/28/1999 | A | FAIL |
Wes Worcester
|
|
|
john ###-#### Need Eng's letter
|
Issue PAID IN FULL permit | | | 10/15/1999 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/14/1999 | | DONE |
|
|
|
revised plans were submitted 10-13-99. wall areas that previously needed engineering were modified to provide alternate brace wall panels. plans have been in system since august 16, 1999. contractor and architect have really drug their feet on this one.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/14/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/14/1999 | | DONE |
|
|
|
Called Seidl ###-####
|
Plan assigned to (DJO) | 8/16/1999 | | 10/14/1999 | | PASS |
Dan Overy
|
|
|
10/14/99 11:08:53 DJO - activity updated through activity BLDA022 from case BLD99-02462.
|
Plan Reviewer's activity | | | 10/1/1999 | | DONE |
|
|
|
Terry records needs revised grading info. Interior shear wall at rec. room patio area, deck floor joist off bed #3, engineering for great room/nook area, addendums for ftm49w straps, m/e sheets, etc. This information was requested from Glancey weeks ago. 09-19-99.No responce.
|
Plans ACCEPTED BY PLAN CHECK | | | 9/16/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/16/1999 | | 8/25/1999 | | PASS |
|
|
|
took to terry records
|
Routing - PUBLIC WORKS GRADING | 8/23/1999 | | 8/23/1999 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 1. Cat 1 because of 10 foot deep fill in front, being done to build drriveway.
|
Application received | | | 8/16/1999 | | |
|
|
|
|
Pending Assignment by DJO | 9/16/1999 | | | | |
Dan Overy
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
plans can be permitted as soon as appeal period is signed off by zoning and revised grading plan is approved by Terry Records. additional information req. from architect along with stamped engineering for lateral at nook.
|
Plan Review Report | | | | | |
|
|
|
|
Routing - PLANNING | 8/25/1999 | | | | PEND |
|
|
|
|