Fee Review-notes | 8/16/1999 | | 5/9/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 10/26/1999 | | DONE |
|
|
|
Letter of Compliance #18164 issued 10-26-99.
|
FIRE-Final Inspection | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PASS |
Joe Tawney
|
|
|
carl ###-#### fn fire Reinsp. Ok for perm. Occ.
|
BLD-Final | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PASS |
Carl Dependahl
|
|
|
carl--- ###-#### fn occ
|
FIRE-Final Inspection | 10/13/1999 | 10/14/1999 | 10/14/1999 | A | FAIL |
Joe Tawney
|
|
|
asap------carl ###-#### fn fire Reinsp. Fail air handler did not shut down on test
|
BLD-Final | 10/14/1999 | 10/14/1999 | 10/14/1999 | P | FAIL |
Carl Dependahl
|
|
|
CARLL ###-#### FN OCC Fire final fail/ per 406
|
FIRE-Final Inspection | 10/12/1999 | 10/13/1999 | 10/13/1999 | A | FAIL |
Joe Tawney
|
|
|
Carl ###-#### Reinsp. Fail test smoke evac system
|
BLD-Final | 10/12/1999 | 10/13/1999 | 10/13/1999 | P | FAIL |
Carl Dependahl
|
|
|
Karl ###-#### Need fire etc.
|
FIRE-Final Inspection | 10/12/1999 | 10/12/1999 | 10/12/1999 | P | FAIL |
Joe Tawney
|
|
|
Carl ###-#### Final fail C/N issued
|
Plan resubmittals received | | | 9/9/1999 | | PEND |
|
|
|
RECEIVED ONE COPY OF REVISED SHEET A1.0. ROUTED TO RON H. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/1999 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 9/8/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/8/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/8/1999 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 8/18/1999 | | 9/8/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/3/1999 | | 9/8/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/3/1999 | | PASS |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ARMSTRONG ARCHITECTS, FORWARDED SAME TO RON HILL. 9/3/99 DAR
|
Routing - FIRE | 9/1/1999 | | 9/3/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/3/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/1/1999 | | FAIL |
|
|
|
faxed and mailed requirements to Architect. Will route to fire department.
|
Routing - PLAN CHECK | 8/20/1999 | | 9/1/1999 | | FAIL |
|
|
|
|
Routing - PLUMBING | 8/19/1999 | | 8/19/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/18/1999 | | 8/19/1999 | | PASS |
|
|
|
'
|
Plan routing begun/TENANTS | | | 8/18/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 8/16/1999 | | 8/18/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 8/17/1999 | | FAIL |
|
|
|
NEED 3RD SET OF PLANS STAMPED BY J.P. PRICE CO. ALSO NEED A ARCHITECT/ENGINEER OF RECORD FORM FOR PROJECT. NOTIFIED WILLIAM MARRICK VIA VOICE MAIL. 8/17/99 DAR
|
Recd Pcfee & Taken To Pln CK | | | 8/16/1999 | | |
|
|
|
|
Application received | | | 8/16/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | PASS |
|
|
|
|
Case Summary (BLD) | | | | | PASS |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
Need third set of resubmitted plans, called and talked to Architect 9-8.
|