Permit Information
Permit NumberBLD99-02545
StatusFinaled
Name HEWLETT PACKARD BLDG #27
Site Address 333 N SAILFISH PL
Project NameHP #27
Customer Number 
ePlanReviewNo
Description
(HEWLETT PACKARD BLDG #27) To finish the 90,276 sq.ft.Type III-N , one story shell and core building for offices, training rooms and a future cafeteria with full kitchen per approved plans on file. There is a 1-hr. occupancy separation between the B office and the future A2.1 cafeteria area. Construction in the future A2.1 cafeteria area will be Type III-1hr. NOTE: This building is fully fire sprinklered and has 60 foot open yards for unlimited area (P.C.#673-99) separate plans and permits are required to finish the kitchen\cafeteria area.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Code Occupancy Approval  7/11/2001 PASS
Verfiedc all is ok and meets compliance to release bond.
Fee Review-notes11/22/200011/22/20003/21/2001 DONE
Permanent occupancy  9/11/2000 DONE
Perm. Occ. Cert. #8365 issued 9-12-00 to Hewlett-Packard, Bldg. #27.
BLD-Final9/6/20009/7/20009/7/2000APASS
DetailsCarl Dependahl
MIKE ###-#### FN OCC, ok for c/o 9/7/2000 11:42:50 AM
Permanent Occupancy 9/7/20009/7/2000 DONE
Details
FIRE-Final Inspection9/5/20009/6/20009/6/2000APASS
DetailsJoe Tawney
mike-- ###-#### fire fn Reinsp OK for permanant occupancy 9/6/2000 12:17:26 PM
Temporary occupancy  6/15/2000 PART
Temp. Occ. Cert. #4026 issued 6-15-00 to Hewlett Packard Bldg., #27 for tenant.
BLD-Final6/13/20006/14/20006/14/2000PFAIL
DetailsJim Sly
Scheduled by a contractor via Hello! on 06/13/2000 at 10:38:07. Contact: ###-####. C/N..letter spec. insp. agency, firestop 1hr. mech. ok for temp. occ. 6/15/00 11:27:03 AM
FIRE-Final Inspection6/13/20006/14/20006/14/2000PPART
DetailsJoe Tawney
mike ###-#### Reinsp. ok for temp. occ. 6/15/00 11:35:11 AM
FIRE-Final Inspection6/12/20006/13/20006/13/2000PFAIL
DetailsJoe Tawney
mike ###-#### Final fail C/N issued. 6/14/00 8:59:56 AM
BLD-Framing/Rough-in5/19/20005/22/20005/22/2000PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/19/2000 at 16:24:00. Contact: ###-####. spoke w/cont. (Mike) need resub. for changes clg. ok area B..pend..HVAC 5/23/00 2:34:14 PM
BLD-Framing/Rough-in5/19/20005/19/20005/19/2000PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/19/2000 at 07:35:56. Contact: ###-####. Ceiling- need HVAC ok for duct hangers. 5/22/00 11:38:33 AM
BLD-Framing/Rough-in4/14/20004/17/20004/17/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/14/2000 at 13:39:50. Contact: ###-####. Grid @ area "A" ok, walls @ "C" ok (to occ. separation) keep C/N. 4/17/00 2:05:00 PM
BLD-Framing/Rough-in3/24/20003/24/20003/24/2000PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/24/2000 at 10:47:44. Contact: ###-####. C/N firestops 3/27/00 9:59:10 AM
BLD-Framing/Rough-in3/13/20003/14/20003/14/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/13/2000 at 17:19:19. Contact: ###-####. B section int. partitions ok; add braces @ wall tops as needed 3/16/00 11:08:49 AM
BLD-Framing/Rough-in2/21/20002/22/20002/22/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 02/21/2000 at 08:07:32. Contact: ###-####. To grid 5- North wing- ok to cover. 2/23/00 11:43:12 AM
Print Occupancy Form  9/23/1999 DONE
Telephone call  9/23/1999 DONE
called permit ready Jonathon Seel ###-####
Issue PAID IN FULL permit  9/23/1999 DONE
Issue PAID IN FULL permit  9/23/1999 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/22/1999 PASS
Plan assigned to (MLO)8/24/1999 9/22/1999 PASS
DetailsMike Otto
Routing - FIRE9/15/19999/15/19999/20/1999 PASS
FED EX PLANS TO FLOYD.
ROUTED OFFICE COPY BACK TO BILL A. KMM
Plan resubmittals received  9/14/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM LARSON ARCHITECTS, FORWARDED SAME TO MIKE OTTO. 9/14/99 DAR
Routing - PLAN CHECK9/14/1999 9/14/1999 PASS
Plan Review Completed(1st rev)  8/31/1999 FAIL
Routing - FIRE8/27/1999 8/31/1999 FAIL
Need sheet TA4 to review and UBC door swing issues.
Plan resubmittals requested  8/30/1999 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Routing - PLAN CHECK8/26/1999 8/27/1999 FAIL
Routing - PUBLIC WORKS8/24/1999 8/26/1999 PASS
Plan routing begun/TENANTS  8/24/1999
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  8/23/1999 PEND
REQUESTED ARCHITECT/ENGINEER OF RECORD FORM. 8/23/99 DAR
Application received  8/20/1999
Routing - PLAN CHECK9/21/19999/21/1999