Case Summary (BLD) | | | 6/28/2010 | | DONE |
|
|
|
|
Fee Review-notes | 8/23/1999 | | 5/10/2000 | | DONE |
|
|
|
|
BLD-Final | 11/16/1999 | 11/17/1999 | 11/17/1999 | P | PASS |
Carl Dependahl
|
|
|
###-####-SAUL FN OCC Card to owner.
|
Permanent occupancy UNPAID FEE | | | 11/17/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8012 issued 11-17-99 to the Chef Express.
|
FIRE-Final Inspection | 11/15/1999 | 11/16/1999 | 11/16/1999 | A | PASS |
Joe Tawney
|
|
|
###-#### FN FIRE-- SAUL Occ. Approved.
|
Permanent Occupancy | | 11/15/1999 | 11/15/1999 | | DONE |
|
|
|
|
BLD-Final | 11/10/1999 | 11/12/1999 | 11/12/1999 | P | CANC |
Jim Storey
|
|
|
saul ###-#### fn occ last one??????
|
BLD-Final | 10/8/1999 | 10/11/1999 | 10/11/1999 | A | PART |
Carl Dependahl
|
|
|
Kainoa ###-#### shaft int. ok ; need to relocate lav. @ bath or resubmit
|
BLD-Framing/Rough-in | 10/7/1999 | 10/8/1999 | 10/8/1999 | P | PART |
Carl Dependahl
|
|
|
KAINOA--- ###-#### R/I INSP shaft; one side ok modify to T 7 B , ubc for construction
|
(F) Reprint permit | | | 10/1/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/29/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/29/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/23/1999 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/22/1999 | 9/22/1999 | 9/22/1999 | | PASS |
|
|
|
Attached resubmittal design data from architect to plans. Processing for permit issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/1999 | | PASS |
|
|
|
Plans approved w/ conditions attached to approved plans. Routing for issuance of permit.
|
Plan assigned to (JCB) | 8/24/1999 | | 9/22/1999 | | PASS |
Jason Blais
|
|
|
9/22/1999 15:51:25 DRS - activity updated through activity BLDA022 from case BLD99-02554.
|
Routing - FIRE | 9/15/1999 | | 9/20/1999 | | PASS |
|
|
|
FED EXED PLANS TO FLOYD. KMM
9/21/99 RECEIVED OFFICE COPY BACK FROM FLOYD. FAXED JOHN COOK RESPONSE. ROUTED TO BILL A. KMM
|
Plan Review Completed(1st rev) | | | 9/20/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 9/14/1999 | | PASS |
|
|
|
Per instructions from Jason Blais, attached required design criteria sheet to each set of plans, verified fire code review approval and will process for issuance of a permit.
|
Plan resubmittals requested | | | 9/14/1999 | | PEND |
|
|
|
One addendum sheet needs to be submitted and attached to plans.
|
Case Summary (BLD) | | | 9/14/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 8/30/1999 | | 9/14/1999 | | PEND |
|
|
|
Plan review report sent and faxed to architect. One addendum sheet required to be submitted for attachment to plans. Plans routed to fire dept.
|
Routing - PLUMBING | 8/26/1999 | | 8/30/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/25/1999 | | 8/26/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | 8/25/1999 | | 8/25/1999 | | |
|
|
|
|
Plan routing begun/TENANTS | | | 8/24/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE. Plans previously signed by Robert Mayer, Central District Health
|
Routing Off Site - C.D.H | 8/23/1999 | | 8/24/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 8/23/1999 | | 8/24/1999 | | |
Marlene Southard
|
|
|
|
Application received | | | 8/23/1999 | | |
|
|
|
|