Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-02613
StatusFinaled
Name COSTCO
Site Address 8109 W FRANKLIN RD
Project NameCOSTCO
Customer Number 
ePlanReviewNo
Description
To remodel the existing front exterior of the building by constructing 66 lineal ft. of new extension to the existing roofline to cover the walkway per approved plans on file. Construction to be wood framing with block face and block columns. NOTE: This building is fully fire sprinklered for area increase. Sprinkler system to be installed in new roofline extension in accordance with NFPA 13 as regulated by the Fire Department. (P.C.#689-99) CZC99-0107 PLAN MODIFICATION SUBMITTED FOR REDUCING THE SIZE OF THE EXTERIOR COLUMNS PER APPROVED PLANS AND ENGINEERING. 3-20-00. *RMH*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes8/30/1999 3/21/2001 DONE
DOC - Permit Finaled1/25/20011/25/20011/25/2001PPASS
DetailsRuss Owen
Added by Inspector: 407 On 1/25/2001 3:51:49 PM
BLD-Final8/18/20008/21/20008/21/2000APASS
DetailsCarl Dependahl
###-####; Mech. & Plbg not applicable, roof drain not modifi 8/21/2000 11:05:03 AM ed 8/21/2000 11:05:07 AM
BLD-Final8/16/20008/17/20008/17/2000AFAIL
DetailsCarl Dependahl
Don ###-####; no card or plans, rec'd kleinfelder's report...ok spec inspe 8/17/2000 11:34:45 AM tion. warned contractor to be ready 8/17/2000 11:35:11 AM
BLD-Final8/15/20008/16/20008/16/2000PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/15/2000 at 14:39:50. Contact: ###-####.keep cn 8/16/2000 2:52:32 PM
Code Occupancy Approval  8/1/2000 PASS
Pass - mets compliance w/. CZC99-0107
BLD-Final7/10/20007/11/20007/11/2000AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 07/10/2000 at 14:56:47. Contact: . Send insp. reports & verify P&Z ok. 7/12/00 10:30:14 AM
BLD-Conference7/11/20007/11/20007/11/2000APASS
DetailsCarl Dependahl
spoke w/ Larry Hughes, job supt....need special insp reports & eng's ok in report form for final; recall when ready.
BLD-Final7/7/20007/10/20007/10/2000AFAIL
DetailsCarl Dependahl
larry ###-#### Called, no response. Left msg. 7/10/00 2:50:56 PM
BLD-Final5/23/20005/24/20005/24/2000AFAIL
DetailsCarl Dependahl
Larry ###-#### Need eng's letter, P&Z ok, etc. 5/25/00 11:46:17 AM
FIRE-Final Inspection5/19/20005/19/20005/19/2000PPASS
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 05/19/2000 at 09:18:01. Contact: ###-####. Final ok on sprinkler protection in & under front canopy. 5/22/00 10:49:01 AM
Code Occupancy Approval  5/12/2000 FAIL
Not done - needs painting to match the rest of the project.
BLD-Framing/Rough-in5/4/20005/5/20005/5/2000APART
DetailsCarl Dependahl
Larry ###-#### Need spec. insp. reports & sprinkler R/I @ front WIP 5/8/00 9:36:30 AM
BLD-Concrete4/21/20004/24/20004/24/2000APART
DetailsCarl Dependahl
###-#### Kleinfelder onsite 4/28/00 8:35:35 AM
BLD-Concrete4/20/20004/21/20004/21/2000APART
DetailsCarl Dependahl
###-#### Larry Hughes Kleinfelder; work in progress (nites). 4/24/00 10:58:31 AM
BLD-Concrete4/19/20004/20/20004/20/2000APART
DetailsCarl Dependahl
COSTCO\\###-#### LARRY Kleindfelder onsite. 4/21/00 9:26:27 AM
BLD-Footing4/3/20004/3/20004/3/2000PPART
DetailsCarl Dependahl
###-#### Costco Col. Ftg's Kleindelder onsite, pending report. 4/4/00 9:34:41 AM
Issue PAID IN FULL permit  3/27/2000 DONE
Routing Off Site - STRUCTURAL3/16/2000 3/20/2000 PEND
plan modification. waiting for struct. calcs. before sending out to eng.. contacted pdq to take outside eng. 3/16/2000 RECEIVED STRUC. CALCS. KMM
Routing - PLAN CHECK3/15/2000 3/20/2000 PASS
DetailsRon Hill
plan modification. 3/16/2000 RECEIVED CALC. ROUTED TO RON H. KMM
PLANS/APPL TAKEN TO FRONT DESK  3/20/2000 PASS
DetailsRon Hill
PLAN MODIFICATION APPR0VED.
Print Occupancy Form  3/20/2000 DONE
Inspection Record Card- Bld  3/20/2000 DONE
Telephone call  3/20/2000 DONE
called leticia 1-###-#### left message
Plan assigned to (R_H)3/10/2000 3/20/2000 PASS
Details
3/20/2000 14:16:23 RMH - activity updated through activity BLDA022 from case BLD99-02613.
Plans ACCEPTED BY PLAN TECH  3/15/2000 DONE
plan modification. Plans routing with original set of plans. kmm
Routing - PLANNING3/15/2000 3/15/2000 PASS
plan modification. kmm
Plan Modification Accepted  3/10/2000 PEND
PLAN MODIFICATION FILED AND WAS INCOMPLETE. ADDITIONAL STRUCTURAL INFORMATION REQUESTED BY RON HILL. ONCE RECEIVED PLANS WILL NEED TO CIRCULATE TO OFF SITE STRUCTURAL ENGINEER, PLANNING AND PLAN CHECK. CONTACT IS RON HILL.
CHANGE STATUS TO (P)  3/10/2000 PEND
DetailsRon Hill
PLAN MODIFICATION PENDING
Inspection Record Card- Bld  2/29/2000 DONE
Print Occupancy Form  2/29/2000 DONE
Receive PAYMENT IN FULL  11/22/1999 DONE
Telephone call  10/20/1999 DONE
I sent a copy of the revised fees over to Matthew Golezer
Inspection Record Card- Bld  10/19/1999 DONE
Print Occupancy Form  10/19/1999 DONE
Telephone call  10/19/1999 DONE
called Matthew ###-####
Routing - PLAN CHECK10/15/199910/15/199910/15/1999 PASS
DetailsRon Hill
PLANS/APPL TAKEN TO FRONT DESK  10/15/1999 PASS
DetailsRon Hill
Plan assigned to (R_H)9/1/1999 10/15/1999 PASS
Details
10/15/1999 12:14:01 RMH - activity updated through activity BLDA022 from case BLD99-02613.
Routing - FIRE10/8/199910/13/199910/13/1999 PASS
Received review 10/13/99/jwa FED EXED PLANS TO FLOYD. KMM
10/15/99 RECEIVED PLANS BACK FROM FLOYD. ROUTED OFFICE COPY BACK TO BILL A. KMM
Plan Review Completed(1st rev)  10/13/1999 PEND
Routing Off Site - STRUCTURAL9/30/19999/30/199910/5/1999 PEND
CONTACTED PDQ TO TAKE RESUBMITTED PLANS FROM 9-29-99 TO OUTSIDE ENG. KMM
Routing - PLAN CHECK9/2/1999 10/5/1999 PASS
DetailsRon Hill
route to fire department
Plan resubmittals received  9/29/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM MULVANNY ARCHITECTS, FORWARDED SAME RON HILL. 9/29/99 DAR
Plan Reviewer's activity  9/16/1999 FAIL
DetailsRon Hill
Sent Structual plan check items to architect.
Routing Off Site - STRUCTURAL9/2/1999 9/16/1999 FAIL
DetailsRon Hill
Sent plans for structural engineering review to engineering consultant. 9/02/99 DAR, Structural review failed requested furter review of resubmitted items.
Routing - PLUMBING9/1/1999 9/2/1999 PASS
Routing - PLANNING9/2/1999 9/2/1999 PASS
czc99-0107
Plan assigned to (MYS)8/30/1999 9/1/1999
DetailsMarlene Southard
Routing - PUBLIC WORKS9/1/1999 9/1/1999 PASS
Plan routing begun/TENANTS  9/1/1999
Route to PUBLIC WORKS (BRIAN MURPHY), PLANNING, PLAN CHECK and FIRE.
Application received  8/30/1999
Recd Pcfee & Taken To Pln CK  8/30/1999
Issue PAID IN FULL permit     
Plan Reviewer's activity    PEND
DetailsRon Hill
PLAN MODIFICATIONS WERE SUBMITTED WITHOUT ENGINEERING CALCULATIONS. CALLED ARCHITECT ON 3-13-00 & 3-14-00, RETURNED MY CALL ON 3-14-00 LEFT MESSAGE STATING THAT ENGINEERING CALCULATIONS WOULD BE SUBMITTED SOME TIME THIS WEEK. *rmh*
Case Summary (BLD)