Fee Review-notes | 8/30/1999 | | 3/21/2001 | | DONE |
|
|
|
|
DOC - Permit Finaled | 1/25/2001 | 1/25/2001 | 1/25/2001 | P | PASS |
Russ Owen
|
|
|
Added by Inspector: 407 On 1/25/2001 3:51:49 PM
|
BLD-Final | 8/18/2000 | 8/21/2000 | 8/21/2000 | A | PASS |
Carl Dependahl
|
|
|
###-####; Mech. & Plbg not applicable, roof drain not modifi 8/21/2000 11:05:03 AM ed 8/21/2000 11:05:07 AM
|
BLD-Final | 8/16/2000 | 8/17/2000 | 8/17/2000 | A | FAIL |
Carl Dependahl
|
|
|
Don ###-####; no card or plans, rec'd kleinfelder's report...ok spec inspe 8/17/2000 11:34:45 AM tion. warned contractor to be ready 8/17/2000 11:35:11 AM
|
BLD-Final | 8/15/2000 | 8/16/2000 | 8/16/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 14:39:50. Contact: ###-####.keep cn 8/16/2000 2:52:32 PM
|
Code Occupancy Approval | | | 8/1/2000 | | PASS |
|
|
|
Pass - mets compliance w/. CZC99-0107
|
BLD-Final | 7/10/2000 | 7/11/2000 | 7/11/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/10/2000 at 14:56:47. Contact: . Send insp. reports & verify P&Z ok. 7/12/00 10:30:14 AM
|
BLD-Conference | 7/11/2000 | 7/11/2000 | 7/11/2000 | A | PASS |
Carl Dependahl
|
|
|
spoke w/ Larry Hughes, job supt....need special insp reports & eng's ok in report form for final; recall when ready.
|
BLD-Final | 7/7/2000 | 7/10/2000 | 7/10/2000 | A | FAIL |
Carl Dependahl
|
|
|
larry ###-#### Called, no response. Left msg. 7/10/00 2:50:56 PM
|
BLD-Final | 5/23/2000 | 5/24/2000 | 5/24/2000 | A | FAIL |
Carl Dependahl
|
|
|
Larry ###-#### Need eng's letter, P&Z ok, etc. 5/25/00 11:46:17 AM
|
FIRE-Final Inspection | 5/19/2000 | 5/19/2000 | 5/19/2000 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/19/2000 at 09:18:01. Contact: ###-####. Final ok on sprinkler protection in & under front canopy. 5/22/00 10:49:01 AM
|
Code Occupancy Approval | | | 5/12/2000 | | FAIL |
|
|
|
Not done - needs painting to match the rest of the project.
|
BLD-Framing/Rough-in | 5/4/2000 | 5/5/2000 | 5/5/2000 | A | PART |
Carl Dependahl
|
|
|
Larry ###-#### Need spec. insp. reports & sprinkler R/I @ front WIP 5/8/00 9:36:30 AM
|
BLD-Concrete | 4/21/2000 | 4/24/2000 | 4/24/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Kleinfelder onsite 4/28/00 8:35:35 AM
|
BLD-Concrete | 4/20/2000 | 4/21/2000 | 4/21/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Larry Hughes Kleinfelder; work in progress (nites). 4/24/00 10:58:31 AM
|
BLD-Concrete | 4/19/2000 | 4/20/2000 | 4/20/2000 | A | PART |
Carl Dependahl
|
|
|
COSTCO\\###-#### LARRY Kleindfelder onsite. 4/21/00 9:26:27 AM
|
BLD-Footing | 4/3/2000 | 4/3/2000 | 4/3/2000 | P | PART |
Carl Dependahl
|
|
|
###-#### Costco Col. Ftg's Kleindelder onsite, pending report. 4/4/00 9:34:41 AM
|
Issue PAID IN FULL permit | | | 3/27/2000 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/16/2000 | | 3/20/2000 | | PEND |
|
|
|
plan modification. waiting for struct. calcs. before sending out to eng.. contacted pdq to take outside eng. 3/16/2000 RECEIVED STRUC. CALCS. KMM
|
Routing - PLAN CHECK | 3/15/2000 | | 3/20/2000 | | PASS |
Ron Hill
|
|
|
plan modification. 3/16/2000 RECEIVED CALC. ROUTED TO RON H. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2000 | | PASS |
Ron Hill
|
|
|
PLAN MODIFICATION APPR0VED.
|
Print Occupancy Form | | | 3/20/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2000 | | DONE |
|
|
|
called leticia 1-###-#### left message
|
Plan assigned to (R_H) | 3/10/2000 | | 3/20/2000 | | PASS |
|
|
|
3/20/2000 14:16:23 RMH - activity updated through activity BLDA022 from case BLD99-02613.
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2000 | | DONE |
|
|
|
plan modification. Plans routing with original set of plans. kmm
|
Routing - PLANNING | 3/15/2000 | | 3/15/2000 | | PASS |
|
|
|
plan modification. kmm
|
Plan Modification Accepted | | | 3/10/2000 | | PEND |
|
|
|
PLAN MODIFICATION FILED AND WAS INCOMPLETE. ADDITIONAL STRUCTURAL INFORMATION REQUESTED BY RON HILL. ONCE RECEIVED PLANS WILL NEED TO CIRCULATE TO OFF SITE STRUCTURAL ENGINEER, PLANNING AND PLAN CHECK. CONTACT IS RON HILL.
|
CHANGE STATUS TO (P) | | | 3/10/2000 | | PEND |
Ron Hill
|
|
|
PLAN MODIFICATION PENDING
|
Inspection Record Card- Bld | | | 2/29/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/29/2000 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 11/22/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/20/1999 | | DONE |
|
|
|
I sent a copy of the revised fees over to Matthew Golezer
|
Inspection Record Card- Bld | | | 10/19/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/19/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/19/1999 | | DONE |
|
|
|
called Matthew ###-####
|
Routing - PLAN CHECK | 10/15/1999 | 10/15/1999 | 10/15/1999 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/1999 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 9/1/1999 | | 10/15/1999 | | PASS |
|
|
|
10/15/1999 12:14:01 RMH - activity updated through activity BLDA022 from case BLD99-02613.
|
Routing - FIRE | 10/8/1999 | 10/13/1999 | 10/13/1999 | | PASS |
|
|
|
Received review 10/13/99/jwa FED EXED PLANS TO FLOYD. KMM
10/15/99 RECEIVED PLANS BACK FROM FLOYD. ROUTED OFFICE COPY BACK TO BILL A. KMM
|
Plan Review Completed(1st rev) | | | 10/13/1999 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/30/1999 | 9/30/1999 | 10/5/1999 | | PEND |
|
|
|
CONTACTED PDQ TO TAKE RESUBMITTED PLANS FROM 9-29-99 TO OUTSIDE ENG. KMM
|
Routing - PLAN CHECK | 9/2/1999 | | 10/5/1999 | | PASS |
Ron Hill
|
|
|
route to fire department
|
Plan resubmittals received | | | 9/29/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM MULVANNY ARCHITECTS, FORWARDED SAME RON HILL. 9/29/99 DAR
|
Plan Reviewer's activity | | | 9/16/1999 | | FAIL |
Ron Hill
|
|
|
Sent Structual plan check items to architect.
|
Routing Off Site - STRUCTURAL | 9/2/1999 | | 9/16/1999 | | FAIL |
Ron Hill
|
|
|
Sent plans for structural engineering review to engineering consultant. 9/02/99 DAR, Structural review failed requested furter review of resubmitted items.
|
Routing - PLUMBING | 9/1/1999 | | 9/2/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 9/2/1999 | | 9/2/1999 | | PASS |
|
|
|
czc99-0107
|
Plan assigned to (MYS) | 8/30/1999 | | 9/1/1999 | | |
Marlene Southard
|
|
|
|
Routing - PUBLIC WORKS | 9/1/1999 | | 9/1/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 9/1/1999 | | |
|
|
|
Route to PUBLIC WORKS (BRIAN MURPHY), PLANNING, PLAN CHECK and FIRE.
|
Application received | | | 8/30/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/30/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | | | |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
Ron Hill
|
|
|
PLAN MODIFICATIONS WERE SUBMITTED WITHOUT ENGINEERING CALCULATIONS. CALLED ARCHITECT ON 3-13-00 & 3-14-00, RETURNED MY CALL ON 3-14-00 LEFT MESSAGE STATING THAT ENGINEERING CALCULATIONS WOULD BE SUBMITTED SOME TIME THIS WEEK. *rmh*
|
Case Summary (BLD) | | | | | |
|
|
|
|