Permanent Occupancy | | 11/8/1999 | 11/8/1999 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/8/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8000 issued 11-8-99 to the Tutoring Club.
|
FIRE-Final Inspection | 11/4/1999 | 11/5/1999 | 11/5/1999 | A | PASS |
Joe Tawney
|
|
|
FIRE FN --###-####--DENNIS Reinsp. Ok for perm. Occ.
|
BLD-Final | 11/4/1999 | 11/5/1999 | 11/5/1999 | P | PASS |
Jim Sly
|
|
|
DENNIS -FN OCC ###-#### Ok for perm. Occ.
|
FIRE-Final Inspection | 11/4/1999 | 11/4/1999 | 11/4/1999 | P | FAIL |
Joe Tawney
|
|
|
DENNIS ###-#### Reinsp. Fail tag fire ext. provide door hardware on rear ext. door.
|
FIRE-Final Inspection | 11/1/1999 | 11/2/1999 | 11/2/1999 | P | FAIL |
Joe Tawney
|
|
|
DENNIS HARMON ###-#### Final fail C/N issued
|
BLD-Framing/Rough-in | 10/29/1999 | 10/29/1999 | 10/29/1999 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/29/1999 at 08:43:47. Contact: ###-####. Int. wall conf.
|
BLD-Framing/Rough-in | 10/27/1999 | 10/27/1999 | 10/27/1999 | P | PART |
Carl Dependahl
|
|
|
ceiling grid ###-#### Ceiling and walls ok
|
BLD-Framing/Rough-in | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PART |
Tom Arcoraci
|
|
|
TOM-- ###-#### CELL FR INSP Ok to cover walls
|
Inspection Record Card- Bld | | | 10/7/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/7/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/7/1999 | | DONE |
|
|
|
scott###-####
|
Issue PAID IN FULL permit | | | 10/7/1999 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/5/1999 | 10/5/1999 | 10/6/1999 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
Plan resubmittals received | | | 10/6/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A1.1, AND TWO RESPONSE LETTERS. ONE FROM WAYNE SCHULTZ OF THE TUTORING CLUB, AND ONE FROM TRENT KOCI ARCH. ROUTED TO JASON B. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/6/1999 | | |
|
|
|
|
Case Summary (BLD) | | | 10/6/1999 | | |
|
|
|
|
Plan assigned to (JCB) | 9/10/1999 | | 10/6/1999 | | PASS |
Jason Blais
|
|
|
|
Routing - FIRE | 10/4/1999 | 10/4/1999 | 10/4/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/13/1999 | | 10/4/1999 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Resubmittal and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 10/4/1999 | | PEND |
|
|
|
Resubmittals and response needed for further review.
|
Case Summary (BLD) | | | 10/4/1999 | | |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/4/1999 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 9/10/1999 | 9/10/1999 | 9/13/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 9/10/1999 | | 9/10/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 9/10/1999 | | PASS |
|
|
|
9/1/99-PLANS CANNOT BE ACCEPTED AS DRAWN AND CANNOT BE ROUTED. SEE LETTER SENT TO TRENT KOCI (BRS ARCHITECTS) AND SCOTT MARTIN (DBSI) DATED 9/1/99. PLANS ON HOLD BY MARLENE'S DESK.
9/10/99-Plans resubmitted are acceptable so routing started.
|
Plan resubmittals received | | | 9/9/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED DRAWINGS A1.1, AND A1.2. ROUTED TO MARLENE. KMM
|
Received Certificate of Value | | | 8/30/1999 | | DONE |
|
|
|
|
Application received | | | 8/30/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/30/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | | | |
|
|
|
Route to PLANNING, PUBLIC WORKS, PLAN CHECK and FIRE.
|