Constructing an additional 2,272 sq. ft. to existing office space for use as warehouse storage per approved plans on file. A new tenant is moving into the space. Total square footage of tenant space is now 4,578 sq. ft. Work to include new one-hour fire rated tenant demising wall, extending existing electrical room walls to roof deck, one full height interior wall in warehouse, possible fire sprinkler adjustments, and some electrical work. NOTE: Building is fully fire sprinklered. (PC# 701-99) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Fee Review-notes9/2/1999 7/24/2000 DONE
BLD-Final2/15/20002/16/20002/16/2000APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 02/15/2000 at 12:08:46. Contact: ###-####. Ok for perm. occ. 2/16/00 1:28:16 PM
Permanent Occupancy 2/16/20002/16/2000 DONE
Details
Permanent occupancy  2/16/2000 DONE
Perm. Occ. Cert. #8138 issued 2-16-00 to the Etailgroup. Com.
BLD-Final1/12/20001/12/20001/12/2000PFAIL
DetailsJim Sly
###-####. C/N..prior details for firestopping per. Prev. corr. Notice not authorized to occupy.
FIRE-Final Inspection1/10/20001/11/20001/11/2000APASS
DetailsJoe Tawney
Dave ###-####. Reinsp. Ok for perm. Occ.
FIRE-Final Inspection10/25/199910/26/199910/26/1999AFAIL
DetailsJoe Tawney
Harry ###-#### Final fail, sprinklers, fire ext, exit signs and door hardware
BLD-Framing/Rough-in10/14/199910/14/199910/14/1999PPASS
DetailsJim Sly
rory ###-####
BLD-Framing/Rough-in10/13/199910/13/199910/13/1999PFAIL
DetailsJim Sly
ele is scheduled for pm also Rory ###-#### No access left note.
Issue PAID IN FULL permit  10/13/1999 DONE
Routing - PLAN CHECK  10/12/1999 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  10/12/1999  
Print Pending Permit.LaserJet4  10/12/1999  
Case Summary (BLD)  10/12/1999  
Telephone call  10/12/1999 DONE
called Matt Rhees to let him know that the permit was ready at ###-####
Inspection Record Card- Bld  10/12/1999 DONE
Print Occupancy Form  10/12/1999 DONE
Plan assigned to (JCB)9/27/1999 10/12/1999 PASS
DetailsJason Blais
Routing - FIRE10/6/199910/11/199910/11/1999 PASS
Plan resubmittals received  10/11/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM COLE ARCHITECTS, FORWARDED SAME TO JASON BLAIS. 10/12/99
Plan Review Completed(1st rev)  10/11/1999 PEND
Plan resubmittals received  10/8/1999 PEND
RECEIVED PLAN CHECK RESUBMITTALS FROM COLE AND ASSOCIATES, MATTHEW RHEES, ONLY RECEIVED ONE SET OF PLANS. FORWARDED SAME TO JASON BLAIS. 10/8/99 DAR
Routing - PLAN CHECK  10/6/1999 FAIL
Plan review report sent and faxed to architect. Response and one resubmittal drawing needed. One copy of submitted drawings is not readable. Plans routed to fire dept.
Plan resubmittals requested  10/6/1999 PEND
One copy of plan needs to be submitted. One in office not readable. Response letter needed for clarification of one item.
Case Summary (BLD)  10/6/1999  
Plan routing begun/TENANTS  9/27/1999 DONE
Route to PLAN CHECK and FIRE.
Plan Reviewer's activity  9/24/1999 DONE
Sent a FAX to Stan Cole informing him that dimensions were lacking along with other info based on a previous permit issued for this space. (see file). We cannot proceed with routing until resubmittals with dimensions are received.
Plan resubmittals received  9/24/1999 DONE
Received revised sheets with full dimensions.
Plan assigned to (MYS)9/2/1999 9/3/1999 HOLD
DetailsMarlene Southard
THESE PLANS ARE PUT ON HOLD. NO DIMENSIONS AND CANNOT PLAN REVIEW. ONCE COMPLYING RESUBMITTALS ARE RECEIVED I WILL BEGIN TO ROUTE.
Plans ACCEPTED BY PLAN TECH  9/2/1999 PEND
PLANS REQUIRE COMPLETE DIMENSIONS, AND COMPLETED APPLICATION. CONTACTED MATT RHEESE OF THESE NEEDS. KMM
Recd Pcfee & Taken To Pln CK  9/2/1999
Received Certificate of Value  9/2/1999 PASS
Application received  9/2/1999