Permit Information
Permit NumberBLD99-02658
StatusFinaled
Name JOHNNY CARINO'S RESTAURANT
Site Address 1700 S ENTERTAINMENT AVE
Project NameJOHNNY CARINO'S
Customer Number 
ePlanReviewNo
Description
JOHNNY CARINO'S COUNTRY ITALIAN * TO CONSTRUCT A SINGLE STORY, WOOD FRAMED, TYPE V NONRATED, FULLY SPRINKLERED, 6,474 SQ. FT. RESTAURANT. FIRE SPRINKLERS ARE BEING INSTALLED TO MEET UBC SECTION 904.2.3.1 AND HAS NOT BEEN SPECIFIED FOR ANY OTHER CODE REQUIREMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. REFER TO BLD99-03031 FOR FOUNDATION INSPECTIONS. DRH99-0125 PC#700-99 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Fee Review-notes11/3/199911/3/19997/21/2000 DONE
Fee Review-notes9/3/1999 7/21/2000 DONE
Permanent occupancy  6/8/2000 DONE
Perm. Occ. Cert. #8253 issued 6-8-00 to Johnny Carino's Italian Restaurant.
Permanent Occupancy 6/6/20006/6/2000 DONE
Details
FIRE-Final Inspection5/25/20005/26/20005/26/2000APASS
DetailsRick Jackson
don -###-#### fn fire
BLD-Final5/26/20005/26/20005/26/2000PPASS
DetailsCarl Dependahl
Struct ok for C/N. 5/31/00 9:19:35 AM
Code Occupancy Approval  3/30/2000 PASS
Meets compliance with DRH99-0125 - Pass
BLD-Final3/29/20003/29/20003/29/2000PPART
DetailsCarl Dependahl
JJulio ###-#### C/N- rear exit & gate (disabled), eng's letter ok for T/O. 3/30/00 10:49:47 AM
Print Occupancy Form  3/29/2000 DONE
Temporary occupancy  3/29/2000 PART
Temp. Occ. Cert. #4000 issued 3-29-00 to Johnny Carino's Restaurant.
BLD-Final3/28/20003/28/20003/28/2000PFAIL
DetailsCarl Dependahl
late pm temp occ\\###-#### Still need fire 3/29/00 10:03:13 AM
FIRE-Hydro test above ground3/27/20003/27/20003/27/2000PPART
DetailsJoe Tawney
Ok on above & underground hydro tests. Require hydro test on FDC piping.
FIRE-Final Inspection3/24/20003/27/20003/27/2000AFAIL
DetailsJoe Tawney
julio ###-#### final fail not ready for inspection/ 3/27/00 4:21:57 PM
BLD-Final3/24/20003/27/20003/27/2000PFAIL
DetailsCarl Dependahl
julio ###-#### Need other finals. 3/28/00 9:18:53 AM
BLD-Final3/23/20003/24/20003/24/2000PFAIL
DetailsCarl Dependahl
late pm ###-#### Julio Need all finals, door hdwr. 3/27/00 9:59:47 AM
BLD-Final3/23/20003/24/20003/24/2000ACANC
DetailsAlan Hauser
Scheduled by a contractor via Hello! on 03/23/2000 at 11:41:30. Contact: ###-####. wrong inspection 3/27/00 10:04:45 AM
BLD-Framing/Rough-in3/16/20003/17/20003/17/2000APART
DetailsCarl Dependahl
Julio ###-#### Keep C/N- ceiling grid ok. 3/20/00 10:17:33 AM
FIRE-Conference3/8/20003/9/20003/9/2000APART
DetailsJoe Tawney
julio ###-#### Conf. with Julio on sprnklr. & life safety issued. 3/9/00 2:16:24 PM
BLD-Conference3/3/20003/6/20003/6/2000AFAIL
DetailsCarl Dependahl
julio ###-#### C/N: remove face paper, complete htg. R/I etc. 3/7/00 9:20:07 AM
BLD-Framing/Rough-in2/1/20002/2/20002/2/2000APART
DetailsCarl Dependahl
Julio- ###-####. ok to begin cover at false cols etc at int keep c\n re shaft detail and wall 2/3/00 8:12:58 AM
BLD-Framing/Rough-in1/28/20001/31/20001/31/2000AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/28/2000 at 13:09:48. Contact: ###-####. c\n need engs detail for shear walls windows, fire blocks etc ok to insul ext wall pending elec 2/1/00 9:02:46 AM
BLD-Framing/Rough-in1/11/20001/11/20001/11/2000PPART
DetailsCarl Dependahl
###-#### . Roof nailing ok.
BLD-Framing/Rough-in1/10/20001/10/20001/10/2000PFAIL
DetailsCarl Dependahl
julio ###-####. Need others R/I's- will recall.
BLD-Footing1/10/20001/10/20001/7/2000APART
DetailsCarl Dependahl
spec insps performed for foundation; pending reports
Case Summary (BLD)  12/29/1999 DONE
PRINT ACTIONS  12/29/1999 DONE
Case Summary (BLD)  12/29/1999 DONE
MISC ACTIONS  12/29/1999 DONE
BLD-Concrete12/2/199912/3/199912/3/1999APART
DetailsTom Arcoraci
slab/ rebar inspection Julio ###-#### Spec. insp. On site.
(F) Reprint permit  11/19/1999 DONE
Routing Off Site - A.C.H.D11/18/199911/18/199911/18/1999 DONE
Spoke with Joyce at Ada County Highway District Planning Services they have paid.
Issue PAID IN FULL permit  11/18/1999 DONE
Inspection Record Card- Bld  11/3/1999 DONE
Print Occupancy Form  11/3/1999 DONE
Telephone call  11/3/1999 DONE
brian ###-####
Case Summary (BLD)  11/3/1999 DONE
Routing - PLAN CHECK11/2/199911/2/199911/2/1999 PEND
Plan Reviewer's activity  11/2/1999 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/2/1999 DONE
Print Pending Permit.LaserJet4  11/2/1999 DONE
Routing - PUBLIC WORKS11/2/1999 11/2/1999 PASS
Plan assigned to (M_P)9/3/1999 11/2/1999 PASS
DetailsMike Phillips
11/2/1999 16:55:43 M_P - activity updated through activity BLDA022 from case BLD99-02658.
Routing - PLAN CHECK10/20/199910/20/199910/29/1999 PEND
Routing to P.W. for final Approval.
Plan Reviewer's activity  10/29/1999 PEND
Routing to P.W. for final approval.
Routing - FIRE10/8/199910/20/199910/20/1999 PASS
FED EXED PLANS TO FLOYD. KMM. Returned review notes 10/20/99 (jwa)
Plan resubmittals received  10/20/1999 DONE
RECEIVED TWO COPIES OF REVISED PLANS. ONE RESPPONSE LETTER AND ONE BUILDING REVIEW COMMENTS. ROUTED TO MIKE P. KMM
Plan Review Completed(1st rev)  10/20/1999 PEND
Plan Reviewer's activity  10/8/1999 FAIL
ADDITIONAL INFORMATION IS REQUIRED TO BE SUBMITTED FOR FURTHER REVIEW PRIOR TO ISUANCE OF BUILDING PERMIT.
Plan resubmittals requested  10/8/1999  
Print Pending Permit.LaserJet4  10/8/1999 FAIL
ADDITIONAL INFORMATION REQUESTED FOR FURTHER REVIEW.
Routing - PLAN CHECK9/20/1999 10/8/1999 FAIL
ROUTING TO FIRE DEPARTMENT FOR REVIEW.
Plan resubmittals received  10/7/1999 DONE
RECEIVED TWO COPIES OF REVISED SHEETS ME-1, S-1, S-2, S-3, S-4, S-5, S-6, AND ONE COPY OF RESPONSE LETTER. ROUTED TO MIKE P. KMM
Additional plans submitted  10/7/1999 DONE
RECEIVED TWO COPIES OF STRUCT. SHEETS AND A CERT. OF VALUE FOR A FOUNDATION PERMIT. ROUTED TO MIKE P. KMM
Additional plans submitted  10/7/1999 DONE
RECEIVED TWO COPIES OF ELEC. PLUMB. AND CIVIL SHEET C-2. ROUTED TO MIKE P. KMM
Routing Off Site - STRUCTURAL9/27/19999/27/19999/29/1999 DONE
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM

9/29/99 PLANS RETURNED FROM AHJ. ROUTED TO MIKE P. KMM
Plan resubmittals received  9/23/1999  
RECEIVED ONE COPY OF REVISED SHEETS S-6, S-5, S-4, S-3, S-1 WITH REVIEW COMMENTS ROUTED TO MIKE P. KMM
Routing - PLUMBING9/15/1999 9/20/1999 PASS
Routing Off Site - STRUCTURAL9/3/1999 9/20/1999 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
Faxed strucural comments to architect for review and resubmit. Second review wants to be looked at by our outside engineering firm. MJP 09/20/99

Routing - PUBLIC WORKS9/3/1999 9/13/1999 FAIL
REQUIRES LARGER GREASE INTERCEPTOR.9//13/99 DAR
Routing - PLANNING9/13/1999 9/13/1999 DONE
approved per DRH99-0125 and as noted on plans (see letter in DRH99-0125 file to Brian Huffaker, dated September 15,1999).
Received Certificate of Value  9/3/1999 PASS
Plans ACCEPTED BY PLAN TECH  9/3/1999 PASS
Plan routing begun/NEW & ADDTN9/3/1999 9/3/1999
Recd Pcfee & Taken To Pln CK  9/3/1999
Plan assigned to (MYS)9/3/1999 9/3/1999
DetailsMarlene Southard
Application received  9/3/1999
Routing Off Site - C.D.H8/27/1999 8/27/1999 PASS