Fee Review-notes | 6/17/2003 | 6/17/2003 | 6/17/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 8/29/2000 | 8/29/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/29/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8350 issued 8-29-00 to the Mellowdee Thornton Mobile Home Park community center bldg.
|
BLD-Final | 8/28/2000 | 8/28/2000 | 8/28/2000 | P | PASS |
Jim Storey
|
|
|
dave-- cell--###-#### final ok. 8/29/2000 7:55:59 AM
|
Temporary occupancy | | | 6/15/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4031 issued 6-15-00 to the Mellowdee Thorntoon MHP community center bldg.
|
FIRE-Final Inspection | 6/14/2000 | 6/14/2000 | 6/14/2000 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 6/14/2000 | 6/14/2000 | 6/14/2000 | P | PART |
Jim Storey
|
|
|
|
BLD-Conference | 6/12/2000 | 6/13/2000 | 6/13/2000 | A | FAIL |
Jim Storey
|
|
|
###-####
|
FIRE-Conference | 6/12/2000 | 6/13/2000 | 6/13/2000 | A | PART |
Rick Jackson
|
|
|
###-#### Exit signs; occupant load sign; emergency lighting and address are required for final. 6/13/00 2:42:47 PM
|
BLD-Conference | 6/12/2000 | 6/12/2000 | 6/12/2000 | P | NH |
Jim Storey
|
|
|
PLEASE CALL FIRST ###-####
|
FIRE-Conference | 6/12/2000 | 6/12/2000 | 6/12/2000 | P | NH |
Rick Jackson
|
|
|
###-#### WILL COORDINATE WITH JIM STORY Contractor not there 6/13/00 2:38:38 PM
|
BLD-Framing/Rough-in | 5/5/2000 | 5/8/2000 | 5/8/2000 | A | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 4/26/2000 | 4/27/2000 | 4/27/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/26/2000 at 17:11:34. Contact: ###-####. pending others and gyp truss brace wall detail. 4/27/00 4:37:45 PM
|
BLD-Conference | 4/19/2000 | 4/20/2000 | 4/20/2000 | A | PASS |
Jim Storey
|
|
|
shear wall insp we are planning on siding on friday jeff ###-#### exterior nailling ok. 4/20/00 3:13:48 PM
|
BLD-Foundation | 4/11/2000 | 4/11/2000 | 4/11/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/11/2000 at 10:06:54. Contact: ###-####. walls ok rebar and hold downs. 4/11/00
|
BLD-Foundation | 4/11/2000 | 4/11/2000 | 4/11/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/11/2000 at 10:06:54. Contact: ###-####. walls ok rebar and hold downs. 4/11/00
|
BLD-Footing | 4/10/2000 | 4/10/2000 | 4/10/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/10/2000 at 08:46:20. Contact: ###-####.
|
Inspection Record Card- Bld | | | 4/10/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/10/2000 | | DONE |
|
|
|
|
Additional plans submitted | | | 3/9/2000 | | DONE |
|
|
|
RECEIVED 2 COPPIES OF UTILITY EXTENSION PLANS, FORWARDED SAME TO LEE RICE FOR HIS APPROVAL. 3/8/00 DAR
|
Routing - PLUMBING | 3/9/2000 | | 3/9/2000 | | DONE |
|
|
|
UTILITY EXTENSION PLANS APPROVED BY LEE RICE. ONE SET RETURNTED TO QUADRANT ENGINEERING, NICK KRAUS FOR POSTING ON THE JOBSITE. SECOND SET SENT TO RECORDS. 3/9/00 DAR
|
Plan resubmittals received | | | 3/8/2000 | | DONE |
|
|
|
RECEIVED PLANS FOR LEE RICE, FORWARDED SAME TO LEE RICE.. 3/8/00 DAR
|
Receive PAYMENT IN FULL | | | 11/9/1999 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/30/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/29/1999 | | DONE |
|
|
|
|
Routing - PLANNING | 9/15/1999 | | 9/24/1999 | | DONE |
|
|
|
Plans approved 9-22-99 by Wayne Gibbs. Plans for the community center buildings are not related to pending Design Review Committee work session on 9-30-99 to finalize fencing plan and landscape material.
|
Print Occupancy Form | | | 9/23/1999 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/17/1999 | 9/17/1999 | 9/22/1999 | | DONE |
|
|
|
Sending to Tempra for follow up review.
|
Routing - PLAN CHECK | 9/22/1999 | 9/22/1999 | 9/22/1999 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/10/1999 | 9/10/1999 | 9/22/1999 | | DONE |
Mike Phillips
|
|
|
|
Pending Assignment by MYS | 9/10/1999 | | 9/22/1999 | | DONE |
Marlene Southard
|
|
|
|
Plan Reviewer's activity | | | 9/22/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/22/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/22/1999 | | DONE |
|
|
|
|
Routing - PLANNING | 9/22/1999 | | 9/22/1999 | | PASS |
|
|
|
routing for follow up review.
|
Plan Reviewer's activity | | | 9/21/1999 | | PEND |
|
|
|
Waiting for P & Z approval.
|
Plan resubmittals received | | | 9/17/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A1 THROUGH A5, SP3 & SP5 ROUTED TO MIKE PHILLIPS. KMM
|
Routing - FIRE | 9/17/1999 | | 9/17/1999 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 9/16/1999 | | FAIL |
|
|
|
Faxed commetns to Steve Trout requesting additional information to be submitted for follow up review.
|
Routing - PLAN CHECK | 9/16/1999 | | 9/16/1999 | | FAIL |
|
|
|
Faxed comments to Steve Trout waiting for reply. Routing to Fire for review.
|
Routing - PLUMBING | 9/15/1999 | | 9/16/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/10/1999 | | 9/15/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 9/10/1999 | 9/10/1999 | 9/10/1999 | | DONE |
Marlene Southard
|
|
|
|
Fee Review-notes | 9/10/1999 | 9/10/1999 | 9/10/1999 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/10/1999 | | |
|
|
|
|
Application received | | | 9/10/1999 | | |
|
|
|
|
Office Staff conference/action | | | | | OUT |
|
|
|
jeff has this set of plans.rad
|
Print Pending Permit.LaserJet4 | | | | | FAIL |
|
|
|
Requesting additional review.
|