Permit Information
Permit NumberBLD99-02745
StatusFinaled
Name STEVE BEST
Site Address 911 S COLE RD
Project NameCALVARY SOUTHERN BAP
Customer Number 
ePlanReviewNo
Description
CALVARY SOUTHERN BAPTIST CHURCH * TO ADD APPROXIMATELY 2,900 SQ. FT. TO THE EXISTING TYPE V ONE-HOUR CHURCH AND CLASS ROOM STRUCTURE. NEW SQUARE FOOTAGE WILL BE USED FOR NEW OFFICE SPACE, CLASS ROOMS, HALL, ENTRY LOBBY AND ACCESSIBLE RESTROOMS. PERMIT TO INCLUDE REMODEL AND CHANGE SLOPES FOR NEW ADDITIONS AND REMODEL INTERION OFFICES AND CLASS ROOMS. LETTER IN FILE STATING THIS STRUCTURE WILL NOT BE USED AS A FULL TIME SCHOOL AND DOES NOT MEET THE REQUIREMENTS FOR AN GROUP "E" OCCUPANCY PER THE UBC. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. CUP99-0092 PC#725-99 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Permanent Occupancy 12/5/200112/5/2001 DONE
Details
BLD-Final12/4/200112/5/200112/5/2001PPASS
DetailsRuss Owen
###-#### MARK CALL FIRST . ok for perm oc, framing has been approved prior. 12/6/2001 9:57:28 AM
Permanent occupancy  12/5/2001 DONE
Perm. Occ. Cert. #8933 issued 12-5-01 to the Calvary Southern Baptist Church.
BLD-Final11/13/200111/13/200111/13/2001PCANC
DetailsDave Hannah
###-####
BLD-Final11/5/200111/5/200111/5/2001PPART
DetailsRuss Owen
###-#### MARK . All signatures on card, no temp oc has ever been issued for this job, no structural signature on card for temp oc, north area walls and doors not per plan at the 1 hr occupancy area need to know if this has been approved will check with 340. 11/5/2001 1:23:45 PM
Code Occupancy Approval  10/30/2001 PASS
ALL IN AS REQUIRED FINAL OCCUPANCY SIGNED OFF.
FIRE-Final Inspection3/26/20013/26/20013/26/2001PPASS
DetailsJoe Tawney
Mark ###-#### Reinsp OK FOR CETIFICATE OF COMPLETION 3/27/2001 8:21:12 AM
FIRE-Final Inspection3/26/20013/26/20013/26/2001PPASS
DetailsJoe Tawney
Mark ###-#### Reinsp OK FOR CETIFICATE OF COMPLETION 3/27/2001 8:21:12 AM
FIRE-Final Inspection3/22/20013/22/20013/22/2001PFAIL
DetailsJoe Tawney
###-#### Reinsp Fail not all c/N items complete 3/23/2001 8:17:21 AM
Extend Permit 180 days 11/9/200011/9/2000 DONE
BLD-Conference10/19/200010/20/200010/20/2000APART
DetailsCarl Dependahl
mark ###-#### for conf, refire 10/20/2000 3:53:02 PM c/n 10/20/2000 3:53:06 PM
BLD-Final10/17/200010/18/200010/18/2000ANR
DetailsTom Arcoraci
MARK ###-#### FN OCC no sigs on card 10/18/2000 11:07:21 AM
FIRE-Final Inspection10/18/200010/18/200010/18/2000PFAIL
DetailsJoe Tawney
Robert ###-#### OK on alarm test. Fail on final. C/N issued 10/19/2000 7:46:54 AM
BLD-Framing/Rough-in6/6/20006/6/20006/6/2000PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/06/2000 at 09:00:56. Contact: . Gyp @ "foyer" lid ok; need continuous membrane at walls (alarm box, etc.) 6/7/00 10:02:33 AM
BLD-Framing/Rough-in6/2/20006/2/20006/2/2000PPART
DetailsCarl Dependahl
Estap ###-#### Foyer area, shear walls ok to cover 6/5/00 10:47:23 AM
BLD-Framing/Rough-in6/1/20006/1/20006/1/2000PFAIL
DetailsCarl Dependahl
###-#### Recall when arch's detail ready. 6/5/00 10:33:29 AM
BLD-Framing/Rough-in5/31/20005/31/20005/31/2000PFAIL
DetailsCarl Dependahl
Mark Estep ###-#### Foyer area @ front: C/N, need arch's clarification re: shear panel locations. 6/1/00 2:30:48 PM
BLD-Framing/Rough-in5/30/20005/30/20005/30/2000PFAIL
DetailsJim Sly
Estepp ###-#### NR 5/31/00 4:27:09 PM
BLD-Framing/Rough-in5/16/20005/16/20005/16/2000PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/16/2000 at 09:48:37. Contact: ###-####. Unable to contact bldr...recall. 5/17/00 1:57:20 PM
BLD-Framing/Rough-in5/9/20005/10/20005/10/2000PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/09/2000 at 15:13:03. Contact: ###-####. Existing int. rooms ok to cover. 5/11/00 11:37:04 AM
BLD-Framing/Rough-in3/30/20003/31/20003/31/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/30/2000 at 12:01:16. Contact: ###-####. Rear class room C/N ok; ok to continue 1hr lid 4/3/00 8:52:08 AM
BLD-Energy code compliance3/30/20003/31/20003/31/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/30/2000 at 12:01:59. Contact: ###-####. Ok to continue cover @ rear class rms 4/3/00 8:52:23 AM
BLD-Framing/Rough-in3/22/20003/22/20003/22/2000PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/22/2000 at 07:33:49. Contact: ###-####. 2nd- C/N- ok to continue 1st layer lid. 3/23/00 9:07:20 AM
BLD-Framing/Rough-in3/16/20003/17/20003/17/2000PFAIL
DetailsCarl Dependahl
###-#### C/N; need htg. r/I. 3/20/00 10:18:19 AM
BLD-Footing2/2/20002/3/20002/3/2000APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 02/02/2000 at 16:56:47. Contact: ###-####. FTG's & pads @ "front". 2/4/00 11:50:20 AM
BLD-Footing1/19/20001/19/20001/19/2000PPART
DetailsCarl Dependahl
###-#### Jerry Estep Ext. ftg. @ rear add'n.. no rebar noted on plans. 1/20/00 8:56:56 AM
BLD-Framing/Rough-in1/11/20001/11/20001/11/2000PPART
DetailsCarl Dependahl
jerry-- ###-#### fr insp. Office area only ok to cover, need Add'l fasteners at lid per ICBO T-7-C.
BLD-Framing/Rough-in1/4/20001/5/20001/5/2000AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/04/2000 at 13:35:18. Contact: ###-####. Need firestopping @ ceiling lines..."strap" extended studs. Ok to 1st layer lid @ office area only.
Routing Off Site - A.C.H.D12/20/199912/20/199912/20/1999 DONE
brought in the impact fee cert on 12-20-99
Issue PAID IN FULL permit  12/20/1999 DONE
Plan assigned to (M_P)9/14/19999/14/199912/9/1999 PASS
DetailsMike Phillips
12/9/1999 09:27:40 M_P - activity updated through activity BLDA022 from case BLD99-02745.
Routing - PLAN CHECK11/26/1999 12/9/1999  
Waiting for letter from owner about class room use and time periods.
Plan Reviewer's activity  12/9/1999 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/9/1999 DONE
Print Pending Permit.LaserJet4  12/9/1999 DONE
Case Summary (BLD)  12/9/1999 DONE
Print Occupancy Form  12/9/1999 DONE
Inspection Record Card- Bld  12/9/1999 DONE
Telephone call  12/9/1999 DONE
called ###-#### gave permit fee will be in today to pick it up.
Plan Reviewer's activity  12/8/1999 PEND
Waiting for letter from owner about use of classrooms.
Plan resubmittals received  12/6/1999 DONE
RECEIVED ONE COPY OF ITEM COMMENT RESPONSES DATED DECEMBER 2, 1999. ROUTED TO MIKE P. KMM
Routing Off Site - STRUCTURAL11/23/199911/23/199912/1/1999 DONE
CONTACTED PDQ TO TAKE REVISED PLANS TO OUTSIDE ENG. KMM
Second plan review completed and approved. MJP 12/1/99
Routing - FIRE11/23/199911/23/199911/24/1999 PASS
ROUTED PLANS TO PLAN CHECK. KMM
Routing - PLAN CHECK10/18/199910/18/199911/23/1999 PEND
Plan resubmittals received  11/15/1999 PEND
PLAN RESUBMITTALS RECEIVED FROM JERRRIE WOLFE'S OFFICE, FORWARDED SAME TO MARLENE SOUTHARD. 11/15/99 DAR
Routing - FIRE10/13/199910/13/199910/18/1999 FAIL
Need clarification on seperation, smoke/fire dampers activation, return air info, door hardware, existing FDC, etc.
Plan Review Completed(1st rev)  10/18/1999 FAIL
Routing - PLAN CHECK10/6/199910/6/199910/13/1999 FAIL
ROUTING TO FIRE FOR REVIEW
Plan resubmittals requested  10/13/1999 FAIL
Sent correction report to architect along with outside engineers comments. Waiting for architect response.
Print Pending Permit.LaserJet4  10/13/1999 FAIL
Follow up review required.
Routing - PLUMBING10/6/199910/6/199910/6/1999 PASS
per resubmitted plans dated 10/1/99 and 97 upc
Routing Off Site - STRUCTURAL9/16/19999/16/199910/5/1999 FAIL
contacted pdq to take plans to outside eng. kmm
Second review required by outside engineering firm 10/13/99 mjp
Routing - PLAN CHECK9/27/19999/27/199910/1/1999  
ROUTING TO PLUMBING.
Plan resubmittals received  10/1/1999 DONE
RECEIVED THREE COPIES OF REVISED SHEETS P-1 WITH PLUMBING COMMENTS BY LEE RICE. ROUTED TO MIKE P. KMM
Routing - PLUMBING9/22/19999/22/19999/27/1999 FAIL
Routing - PUBLIC WORKS9/21/19999/21/19999/22/1999 PASS
Routing - PLAN CHECK9/20/19999/20/19999/21/1999  
Routing - PLUMBING9/17/1999 9/20/1999 FAIL
Routing - PLANNING9/17/1999 9/17/1999 DONE
as per CUP99-0092
Routing - PUBLIC WORKS9/16/19999/16/19999/17/1999 FAIL
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY.
Plans ACCEPTED BY PLAN TECH  9/16/1999  
Received Certificate of Value  9/16/1999  
Plan routing begun/NEW & ADDTN  9/16/1999  
Plans ACCEPTED BY PLAN TECH  9/16/1999  
Case Summary (BLD)  9/16/1999 DONE
Fee Review-notes9/13/19999/13/19999/13/1999 DONE
Application received  9/13/1999  
Recd Pcfee & Taken To Pln CK  9/13/1999 DONE
ISSUE ACTIONS