Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberBLD99-02753
StatusFinaled
Name DR DIGRAZIA
Site Address 900 N LIBERTY ST
Project NameST ALS OFFICE #5-2ND FLR
Customer Number 
ePlanReviewNo
Description
Construction of a new 2,810 sq. ft. dentist office tenant space on second floor in shell building. Work to include constructing new accessible restrooms, constructing a one-hour rated tenant demising wall and one-hour rated medical gas closet, new rated doors and rated windows in existing rated corridor, new interior walls with doors and windows, interior finish, new suspended ceiling, fire sprinkler work, new mechanical, new plumbing, and new electrical work. NOTE: This building is fully fire sprinklered. (PC#727-99) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/17/20036/17/20036/17/2003 DONE
Permanent Occupancy 1/7/20001/7/2000 DONE
Details
Permanent occupancy  1/7/2000 DONE
Perm. Occ. Cert. #8073 issued 1-7-00 to Dr. Digrazia on the 2nd floor of St. Al's Ofc. Bldg.
BLD-Final1/6/20001/6/20001/6/2000PPASS
DetailsCarl Dependahl
cecil ###-#### pager. Card to contractor.
FIRE-Final Inspection1/3/20001/3/20001/3/2000PPASS
DetailsJoe Tawney
cecil ###-#### fn. Reinsp. ok for permanent occupancy.
FIRE-Final Inspection12/21/199912/23/199912/23/1999AFAIL
DetailsJoe Tawney
cecil. Final fail C/N issued.
BLD-Final12/20/199912/21/199912/21/1999AFAIL
DetailsAlan Hauser
Lane- ###-####. Wanted plbg. final.
BLD-Framing/Rough-in11/10/199911/10/199911/10/1999PPART
DetailsCarl Dependahl
cecil ###-#### Walls ok.
Inspection Record Card- Bld  11/10/1999 DONE
Print Occupancy Form  11/10/1999 DONE
Telephone call  11/10/1999 DONE
called Erin Muggli at ###-####. Permit ready and fees due.
Issue PAID IN FULL permit  11/10/1999 DONE
Routing - PLAN CHECK11/9/199911/9/199911/9/1999 PASS
Plans approved and taken to front desk.
Routing - FIRE11/4/199911/4/199911/9/1999 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/9/1999  
Print Pending Permit.LaserJet4  11/9/1999  
Case Summary (BLD)  11/9/1999  
Plan assigned to (JCB)9/22/1999 11/9/1999 PASS
DetailsJason Blais
Routing - PLAN CHECK10/26/199910/26/199911/4/1999 FAIL
One accessibility issue needs to be addressed by addendum. Plans routed to fire dept. again.
Plan resubmittals requested  11/4/1999 PEND
One resubmittal addendum needed for quick review.
Plan resubmittals received  11/2/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM SAM BURROWS, LOMBARD CONRAD ARCHITECTS, FORWARDED SAME TO JASSON BLAISE. 11/2/99 DAR
Routing - FIRE10/21/199910/25/199910/25/1999 FAIL
VERIFICATION REQUIRED FOR MEDICAL GAS STORAGE, LIMITS, ETC.
Plan Review Completed(1st rev)  10/25/1999 FAIL
Routing - PLAN CHECK9/23/19999/23/199910/20/1999 FAIL
Plan review report sent and faxed to architect. Resubmittals and response required. Plans routed to fire dept.
Plan resubmittals requested  10/20/1999 PEND
Resubmittal drawings and response required for further review.
Case Summary (BLD)  10/20/1999  
Routing - PLUMBING10/4/1999 10/14/1999 PASS
Plan Reviewer's activity  9/23/1999 DONE
ISSUED PARTIAL PERMIT AT THE REQUEST OF THE CONTRACTOR.
Routing - PUBLIC WORKS9/14/19999/14/19999/15/1999 PASS
Received Certificate of Value  9/14/1999 DONE
Fee Review-notes9/13/19999/13/19999/13/1999 DONE
Plan assigned to (MYS)9/13/19999/13/19999/13/1999 DONE
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  9/13/1999 DONE
Application received  9/13/1999  
Plan routing begun/TENANTS  9/13/1999 DONE
This plan routes to PUBLIC WORKS, PLUMBING, PLAN CHECK AND FIRE.
Plans ACCEPTED BY PLAN TECH    PASS
PLANS STATE THE USE OF THE 94 CODE. REQUESTED REFERENCE THE 97 CODE FROM ERIN MUGGLI. KMM
9-15-99 RECEIVED LETTER FROM SAM ABOUT THE 97 CODE. I MISREAD THE STATEMENT. THE 94 CODE WAS USED FOR THE SHELL AND CORE. KMM
Pending Assignment by MYS9/13/1999    
DetailsMarlene Southard