Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD99-02756
StatusFinaled
Name MARTIN RICO HANGER
Site Address 4000 S ORCHARD ST
Project Name 
Customer Number 
ePlanReviewNo
Description
MARTIN RICE HANGAR ADDITION - TO CONSTRUCT A 15,200 SQ. FT. ONE STORY, TYPE II-N, FULLY FIRE SPRINKLERED AIRCRAFT HANGER ADDITION TO THE EXISTING HANGAR/OFFICE FACILITY. HANGAR TO BE SLAB ON GRADE W/PRE-ENGINEERED METAL BUILDING. ALTERNATE FOR FLOOR DRAINS TO DRAIN TO AN APPROVED SEPARATOR WHICH IS CONNECTED TO A 5000 GALLON UNDERGROUND CONTAINMENT TANK APPROVED PER T. HOGALND PER UBC SEC. 104.2.8. FIRE SPRINKLERS USED FOR AREA.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes9/13/1999 5/16/2000 DONE
Fee Review-notes2/18/20002/18/20005/10/2000 DONE
Permanent Occupancy 3/15/20003/15/2000 DONE
Details
Permanent occupancy UNPAID FEE  3/15/2000 DONE
Perm. Occ. Cert. #8162 issued 3-15-00 to the Martin Rice Hangar addn.
BLD-Final3/1/20003/2/20003/2/2000APART
DetailsJim Storey
Mike Tracy ###-#### Temp. ok pend Ken Wickols pern. & MTI final letter. 3/2/00 4:46:48 PM
Code Occupancy Approval  3/1/2000 PASS
no conditions for this addition, final signed off.
FIRE-Final Inspection2/29/20002/29/20002/29/2000PPASS
DetailsJoe Tawney
mike ###-#### fn fire Reinsp. ok for per. occ. 3/1/00 11:18:50 AM
FIRE-Final Inspection2/28/20002/28/20002/28/2000PFAIL
DetailsJoe Tawney
Mike Tracy ###-#### Final fail mount fire extinguishers. 2/29/00 2:57:31 PM
BLD-Final2/23/20002/25/20002/25/2000PFAIL
DetailsCarl Dependahl
fn occ--mike ###-#### Need fire...called, left. msg. 2/28/00 2:46:29 PM
FIRE-Final Inspection2/24/20002/25/20002/25/2000APART
DetailsJoe Tawney
###-#### Final ok on alarm & sprklr. system. bldg. final no yet scheduled. 2/25/00 3:12:50 PM
BLD-Conference12/13/199912/14/199912/14/1999PPASS
DetailsJim Storey
MIKE TRACY ###-#### MID DAY IF POSSIBLE Conf. W/MTI & contractor to review turn of the nut method req. & spec. by metal bldg. Engineering.
Plan resubmittals received  11/29/1999 DONE
RECEIVED TWO COPIES OF REVISED SHEETS MP3 AND MP4. ROUTED TO BILL VANDERGRIFT KMM
BLD-Foundation11/24/199911/26/199911/26/1999APART
DetailsJim Storey
mike ###-#### Covered w/special insp.
BLD-Conference11/24/199911/24/199911/24/1999PFAIL
DetailsBill VanDegrift
Upgrade existing piping to materials approved for inside the building, secure plumbing permit for interceptor, install vents, test, call for inspection; extend vent from existing interceptor inside building thru roof.
Telephone call  11/22/1999 DONE
called Rick Shrum the check was written wrong so he will be in tommorrow morning.
Routing Off Site - A.C.H.D11/19/199911/19/199911/19/1999 DONE
brought in a Impact fee certificate no fees due paper on file.
BLD-Footing11/19/199911/19/199911/19/1999PPART
DetailsCarl Dependahl
Rick Shrum ###-#### super job site Mike Tracy ###-#### Boise airport; met w/supt. & MTI. Ok to pour pending complete soils ok.
Issue PAID IN FULL permit  11/19/1999 DONE
Plan assigned to (MLO)9/16/19999/16/199911/18/1999 DONE
DetailsMike Otto
Plan assigned to (MLO)9/14/19999/14/199911/18/1999 PASS
DetailsMike Otto
11/18/1999 10:33:19 MLO - activity updated through activity BLDA022 from case BLD99-02756.
Routing - PLUMBING11/17/1999 11/18/1999 PASS
vent seperation chamber and downstream of discharge dip tube seperatly
PLANS/APPL TAKEN TO FRONT DESK  11/18/1999 DONE
Inspection Record Card- Bld  11/18/1999 DONE
Print Occupancy Form  11/18/1999 DONE
Telephone call  11/18/1999 DONE
stan ###-####
Routing - FIRE11/17/199911/17/199911/17/1999 PASS
design and concepts for drainage of interceptor accepted in accordance with agreements of meeting with contractor, architect owner and city staff (Dave Miller representing fire) on 11-16-99
Plan resubmittals received  11/17/1999 PEND
received revised mechanical drawings .
Plan resubmittals requested  11/16/1999 PEND
architect to provide corrected plans for drainage of sand and oil interceptor to sewer or request alternate design to storage tank. MLO
Meeting  11/16/1999 PEND
HAD MEETING WITH OWNER, ARCHITECT, CONTRACTOR CITY PLAN CHECK, PLUMBING AND BUILDING OFFICIAL CONCERNING PLAN REVIEW TIME AND FLOOR DRAINS. PLAN REVIEW TIME RESOLVED AND ARCHITECT TO CONTACT MECHANICAL ENGINEER REGARDING SAND AND OIL INTERCEPTOR BEING CONNECTED TO STORM DRAINS AS SHOWN ON PLANS OR TO 5000 GALLON CONTIANMENT TANK AS CLAIMED BY CONTRACTOR. REVISED PLANS FOR FLOOR DRAINS TO BE RESUBMITTED FOR REVIEW ALONG WITH A LETTER REQUESTING USE OF CONTIANMENT TANK INSTEAD OF CONNECTING TO SEWER FOR FLOOR DRAINS.
Routing - PLUMBING11/4/199911/4/199911/10/1999 FAIL
upgrade sand and grease trap to oil and flammable liquids interceptor, trench drain outlets to be trapped and a upper end vent provided, address bill alexanders system design comments from 10/25/99 review
Application received  11/10/1999 PEND
Routing - FIRE11/2/199911/2/199911/4/1999 FAIL
Sent to Floyds shipping box for final review of construction type information Per NFPA 220. 11/1/99 (jwa)
11/2/99 ROUTED OFFICE COPY TO FLOYD VIA FED EX. KMM
RECIEVED REVIEW COPY 11/4/1999 - MADE ADJUSTMENTS AND RETURNED SITE PLAN BACK TO DESK. JWA
11/9/99 RECEIVED OFFICE COPY BACK FROM FLOYD. ROUTED TO PLUMB TO PUT OFFICE COPY WITH ISSUE COPY. FAXED COPY OF PLAN REVIEW TO ARCH. PLANS NEED TO BE SIGNED OFF BY FIRE. KMM
Plan failed per varley. upgraded to approved and modified to eliminate non-adopted portitions of NFPA 409 from mandatory requirements to meet building code. 11-17-99. mlo
Plan resubmittals received  10/29/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM COLE AND ASSOCIATES, FORWARDED SAME TO MIKE OTTO. 10/29/99 DAR PLANS INCLUDED STRUCTURAL REVISIONS AND ARCHITECTURAL CHANGES
Routing - PLAN CHECK10/29/1999 10/29/1999 PASS
revised plans approved .
Routing Off Site - STRUCTURAL10/12/1999 10/28/1999 PASS
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
10-14-99 CONTACTED PDQ TO TAKE RESUBMITTED PRE-ENGINEERED BLDG. PLANS TO OUTSIDE ENG. KMM
Routing - FIRE10/14/199910/25/199910/25/1999 FAIL
UFC FIRE PROTECTION ISSUES WITH FIRE PROTECTION. BUILDING FIRE RELATED ISSUES NOT ADDRESSED ABOVE THE REQUIRMENTS OF UBC.
Plan Review Completed(1st rev)  10/25/1999 FAIL
plans sent back to plan review.
Plan resubmittals received  10/14/1999 DONE
RECEIVED THREE COPIES OF PRE-ENGINEERED BLDG. MANUFACTURES PLANS. PUT TWO COPIES WITH PLANS AND ROUTED ONE COPY TO OUTSIDE ENG.
Received Certificate of Value  10/14/1999 DONE
RECEIVED REVISED CERT. OF VALUE FOR THE HANGAR. THIS REVISION OF $480,000 IS THE NEW PROJECT VALUE MINUS THE GRADING VALUE ($70,000) AND FOUNDATION VALUE ($59,000) THE OLD PROJECT VALUE WAS $609,000. PUT ONE COPY OF CERT. OF VALUE AND FOUND. APPLICATION IN FILE AND TWO COPIES WITH THE PLANS. KMM
Application received  10/14/1999 DONE
RECEIVED APPLICATION FOR THE FOUNDATION PERMIT. PUT TWO COPIES WITH PLANA AND ONE COPY WITH THE FILE. KMM
Routing - PLAN CHECK10/6/199910/6/199910/13/1999 PASS
PLANS GIVEN TO MIKE OTTO. 10/6/99\\ MLO ON VACATION 10-4\ 10-12
10/12/99 PLANS ROUTED TO PLAN TECH. TO ADD INFORMATION. KMM
Routing - PLAN CHECK10/12/199910/12/199910/12/1999 FAIL
FOUNDATION ONLY REQUEST - PLANS ROUTED TO MIKE OTTO. WITH EXTRA FOUNDATION SET FOR ON SITE FOUNDATION INSPECTIONS. WITH LETTER REQUESTING FOUNDATION. JEFF WILL FAX OVER CERT. OF VALUE. KMM BUILDING OFFICIALS POLICY DOES NOT PERMIT FOUNDATION PERMITS FOR ADDITIONS. MLO
Additional plans submitted  10/12/1999 DONE
RECEIVED THREE COPIES OF PRE-ENG. BLDG. PLANS, STAMPED AND SIGNED, WITH CALCS. ALSO RECEIVED AN ADDITIONAL SET OF FOUNDATION PLANS TO KEEP ON SITE FOR FOUNDATION INSPECTIONS FOR FOUNDATION PERMIT. RECEIVED ONE COPY OF LETTER ADDRESSED TO TIM HOGLAND FOR FOUNDATION PERMIT. I ALSO ASKED FOR A CERT. OF VALUE FOR THE FOUNDATION PERMIT, AND A REVISED CERT. OF VALUE FOR THE BUILDING MINUS THE GRADING AND DRAINAGE AND THE FOUNDATION. KMM
Plans ACCEPTED BY PLAN TECH  10/12/1999 DONE
Routing - PLUMBING9/30/1999 10/6/1999 PEND
rout to fire for design to determine intercepter compliance
Routing - PUBLIC WORKS9/23/1999 9/30/1999 PASS
Routing - AIRPORT9/24/1999 9/28/1999 PASS
Routing - PLANNING9/23/1999 9/23/1999 PASS
ROUTE BACK TO KATHY MILLER WHEN REVIEW IS COMPLETE. I AM WAITING FOR ENG. FOR THE PRE ENG. BUILIDNG. KMM
Plan routing begun/NEW & ADDTN  9/16/1999  
Received Certificate of Value  9/16/1999  
Plans ACCEPTED BY PLAN TECH  9/13/1999 FAIL
PRE ENGINEERED BUILDING PLANS NEED TO BE STAMPED AND SIGNED.
CALCS. ARE REQUIRED. REQUIRE THREE ADDITIONAL CIVIL DRAWINGS. CONTACTED RICK SHRUM AND STAN COLE OF THESE NEEDS. KMM
10/12/99 RECEIVED ABOVE ITEMS. KMM
10-12-99 RECEIVED TWO COPIES OF STAMPED AND SIGNED PRE-ENG. BUILDING PLANS. CONTACTED JEFF ULHORN TO LET HIM KNOW THAT I NEED ONE ADDITIONAL SET. HE ALSO STATED THAT THEY ARE AFTER A FOUNDATION PERMIT. I REQUESTED A LETTER TO TIM HOGLAND AND AN ADDITIONAL FOUNDATION COPY OF PLANS TO KEEP ON SITE. KMM
Application received  9/13/1999  
Pending Assignment by MYS9/13/1999    
DetailsMarlene Southard
Case Summary (BLD)     
Telephone call    FAIL
CONTACTED STAN COLE 10/15/1999 CONCERNING TYPE OF HANGER ADDRESSED IN NFPA 409 AND SPECIAL REQUIRMENTS. INDICATED HE WOULD GET BACK WITH ADDRESSED ISSUES.
Case Summary (BLD)