Fee Review-notes | 9/13/1999 | | 5/16/2000 | | DONE |
|
|
|
|
Fee Review-notes | 2/18/2000 | 2/18/2000 | 5/10/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/15/2000 | 3/15/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/15/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8162 issued 3-15-00 to the Martin Rice Hangar addn.
|
BLD-Final | 3/1/2000 | 3/2/2000 | 3/2/2000 | A | PART |
Jim Storey
|
|
|
Mike Tracy ###-#### Temp. ok pend Ken Wickols pern. & MTI final letter. 3/2/00 4:46:48 PM
|
Code Occupancy Approval | | | 3/1/2000 | | PASS |
|
|
|
no conditions for this addition, final signed off.
|
FIRE-Final Inspection | 2/29/2000 | 2/29/2000 | 2/29/2000 | P | PASS |
Joe Tawney
|
|
|
mike ###-#### fn fire Reinsp. ok for per. occ. 3/1/00 11:18:50 AM
|
FIRE-Final Inspection | 2/28/2000 | 2/28/2000 | 2/28/2000 | P | FAIL |
Joe Tawney
|
|
|
Mike Tracy ###-#### Final fail mount fire extinguishers. 2/29/00 2:57:31 PM
|
BLD-Final | 2/23/2000 | 2/25/2000 | 2/25/2000 | P | FAIL |
Carl Dependahl
|
|
|
fn occ--mike ###-#### Need fire...called, left. msg. 2/28/00 2:46:29 PM
|
FIRE-Final Inspection | 2/24/2000 | 2/25/2000 | 2/25/2000 | A | PART |
Joe Tawney
|
|
|
###-#### Final ok on alarm & sprklr. system. bldg. final no yet scheduled. 2/25/00 3:12:50 PM
|
BLD-Conference | 12/13/1999 | 12/14/1999 | 12/14/1999 | P | PASS |
Jim Storey
|
|
|
MIKE TRACY ###-#### MID DAY IF POSSIBLE Conf. W/MTI & contractor to review turn of the nut method req. & spec. by metal bldg. Engineering.
|
Plan resubmittals received | | | 11/29/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS MP3 AND MP4. ROUTED TO BILL VANDERGRIFT KMM
|
BLD-Foundation | 11/24/1999 | 11/26/1999 | 11/26/1999 | A | PART |
Jim Storey
|
|
|
mike ###-#### Covered w/special insp.
|
BLD-Conference | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | FAIL |
Bill VanDegrift
|
|
|
Upgrade existing piping to materials approved for inside the building, secure plumbing permit for interceptor, install vents, test, call for inspection; extend vent from existing interceptor inside building thru roof.
|
Telephone call | | | 11/22/1999 | | DONE |
|
|
|
called Rick Shrum the check was written wrong so he will be in tommorrow morning.
|
Routing Off Site - A.C.H.D | 11/19/1999 | 11/19/1999 | 11/19/1999 | | DONE |
|
|
|
brought in a Impact fee certificate no fees due paper on file.
|
BLD-Footing | 11/19/1999 | 11/19/1999 | 11/19/1999 | P | PART |
Carl Dependahl
|
|
|
Rick Shrum ###-#### super job site Mike Tracy ###-#### Boise airport; met w/supt. & MTI. Ok to pour pending complete soils ok.
|
Issue PAID IN FULL permit | | | 11/19/1999 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 9/16/1999 | 9/16/1999 | 11/18/1999 | | DONE |
Mike Otto
|
|
|
|
Plan assigned to (MLO) | 9/14/1999 | 9/14/1999 | 11/18/1999 | | PASS |
Mike Otto
|
|
|
11/18/1999 10:33:19 MLO - activity updated through activity BLDA022 from case BLD99-02756.
|
Routing - PLUMBING | 11/17/1999 | | 11/18/1999 | | PASS |
|
|
|
vent seperation chamber and downstream of discharge dip tube seperatly
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/18/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/18/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/18/1999 | | DONE |
|
|
|
stan ###-####
|
Routing - FIRE | 11/17/1999 | 11/17/1999 | 11/17/1999 | | PASS |
|
|
|
design and concepts for drainage of interceptor accepted in accordance with agreements of meeting with contractor, architect owner and city staff (Dave Miller representing fire) on 11-16-99
|
Plan resubmittals received | | | 11/17/1999 | | PEND |
|
|
|
received revised mechanical drawings .
|
Plan resubmittals requested | | | 11/16/1999 | | PEND |
|
|
|
architect to provide corrected plans for drainage of sand and oil interceptor to sewer or request alternate design to storage tank. MLO
|
Meeting | | | 11/16/1999 | | PEND |
|
|
|
HAD MEETING WITH OWNER, ARCHITECT, CONTRACTOR CITY PLAN CHECK, PLUMBING AND BUILDING OFFICIAL CONCERNING PLAN REVIEW TIME AND FLOOR DRAINS. PLAN REVIEW TIME RESOLVED AND ARCHITECT TO CONTACT MECHANICAL ENGINEER REGARDING SAND AND OIL INTERCEPTOR BEING CONNECTED TO STORM DRAINS AS SHOWN ON PLANS OR TO 5000 GALLON CONTIANMENT TANK AS CLAIMED BY CONTRACTOR. REVISED PLANS FOR FLOOR DRAINS TO BE RESUBMITTED FOR REVIEW ALONG WITH A LETTER REQUESTING USE OF CONTIANMENT TANK INSTEAD OF CONNECTING TO SEWER FOR FLOOR DRAINS.
|
Routing - PLUMBING | 11/4/1999 | 11/4/1999 | 11/10/1999 | | FAIL |
|
|
|
upgrade sand and grease trap to oil and flammable liquids interceptor, trench drain outlets to be trapped and a upper end vent provided, address bill alexanders system design comments from 10/25/99 review
|
Application received | | | 11/10/1999 | | PEND |
|
|
|
|
Routing - FIRE | 11/2/1999 | 11/2/1999 | 11/4/1999 | | FAIL |
|
|
|
Sent to Floyds shipping box for final review of construction type information Per NFPA 220. 11/1/99 (jwa)
11/2/99 ROUTED OFFICE COPY TO FLOYD VIA FED EX. KMM
RECIEVED REVIEW COPY 11/4/1999 - MADE ADJUSTMENTS AND RETURNED SITE PLAN BACK TO DESK. JWA
11/9/99 RECEIVED OFFICE COPY BACK FROM FLOYD. ROUTED TO PLUMB TO PUT OFFICE COPY WITH ISSUE COPY. FAXED COPY OF PLAN REVIEW TO ARCH. PLANS NEED TO BE SIGNED OFF BY FIRE. KMM
Plan failed per varley. upgraded to approved and modified to eliminate non-adopted portitions of NFPA 409 from mandatory requirements to meet building code. 11-17-99. mlo
|
Plan resubmittals received | | | 10/29/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM COLE AND ASSOCIATES, FORWARDED SAME TO MIKE OTTO. 10/29/99 DAR PLANS INCLUDED STRUCTURAL REVISIONS AND ARCHITECTURAL CHANGES
|
Routing - PLAN CHECK | 10/29/1999 | | 10/29/1999 | | PASS |
|
|
|
revised plans approved .
|
Routing Off Site - STRUCTURAL | 10/12/1999 | | 10/28/1999 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
10-14-99 CONTACTED PDQ TO TAKE RESUBMITTED PRE-ENGINEERED BLDG. PLANS TO OUTSIDE ENG. KMM
|
Routing - FIRE | 10/14/1999 | 10/25/1999 | 10/25/1999 | | FAIL |
|
|
|
UFC FIRE PROTECTION ISSUES WITH FIRE PROTECTION. BUILDING FIRE RELATED ISSUES NOT ADDRESSED ABOVE THE REQUIRMENTS OF UBC.
|
Plan Review Completed(1st rev) | | | 10/25/1999 | | FAIL |
|
|
|
plans sent back to plan review.
|
Plan resubmittals received | | | 10/14/1999 | | DONE |
|
|
|
RECEIVED THREE COPIES OF PRE-ENGINEERED BLDG. MANUFACTURES PLANS. PUT TWO COPIES WITH PLANS AND ROUTED ONE COPY TO OUTSIDE ENG.
|
Received Certificate of Value | | | 10/14/1999 | | DONE |
|
|
|
RECEIVED REVISED CERT. OF VALUE FOR THE HANGAR. THIS REVISION OF $480,000 IS THE NEW PROJECT VALUE MINUS THE GRADING VALUE ($70,000) AND FOUNDATION VALUE ($59,000) THE OLD PROJECT VALUE WAS $609,000. PUT ONE COPY OF CERT. OF VALUE AND FOUND. APPLICATION IN FILE AND TWO COPIES WITH THE PLANS. KMM
|
Application received | | | 10/14/1999 | | DONE |
|
|
|
RECEIVED APPLICATION FOR THE FOUNDATION PERMIT. PUT TWO COPIES WITH PLANA AND ONE COPY WITH THE FILE. KMM
|
Routing - PLAN CHECK | 10/6/1999 | 10/6/1999 | 10/13/1999 | | PASS |
|
|
|
PLANS GIVEN TO MIKE OTTO. 10/6/99\\ MLO ON VACATION 10-4\ 10-12
10/12/99 PLANS ROUTED TO PLAN TECH. TO ADD INFORMATION. KMM
|
Routing - PLAN CHECK | 10/12/1999 | 10/12/1999 | 10/12/1999 | | FAIL |
|
|
|
FOUNDATION ONLY REQUEST - PLANS ROUTED TO MIKE OTTO. WITH EXTRA FOUNDATION SET FOR ON SITE FOUNDATION INSPECTIONS. WITH LETTER REQUESTING FOUNDATION. JEFF WILL FAX OVER CERT. OF VALUE. KMM BUILDING OFFICIALS POLICY DOES NOT PERMIT FOUNDATION PERMITS FOR ADDITIONS. MLO
|
Additional plans submitted | | | 10/12/1999 | | DONE |
|
|
|
RECEIVED THREE COPIES OF PRE-ENG. BLDG. PLANS, STAMPED AND SIGNED, WITH CALCS. ALSO RECEIVED AN ADDITIONAL SET OF FOUNDATION PLANS TO KEEP ON SITE FOR FOUNDATION INSPECTIONS FOR FOUNDATION PERMIT. RECEIVED ONE COPY OF LETTER ADDRESSED TO TIM HOGLAND FOR FOUNDATION PERMIT. I ALSO ASKED FOR A CERT. OF VALUE FOR THE FOUNDATION PERMIT, AND A REVISED CERT. OF VALUE FOR THE BUILDING MINUS THE GRADING AND DRAINAGE AND THE FOUNDATION. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 10/12/1999 | | DONE |
|
|
|
|
Routing - PLUMBING | 9/30/1999 | | 10/6/1999 | | PEND |
|
|
|
rout to fire for design to determine intercepter compliance
|
Routing - PUBLIC WORKS | 9/23/1999 | | 9/30/1999 | | PASS |
|
|
|
|
Routing - AIRPORT | 9/24/1999 | | 9/28/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 9/23/1999 | | 9/23/1999 | | PASS |
|
|
|
ROUTE BACK TO KATHY MILLER WHEN REVIEW IS COMPLETE. I AM WAITING FOR ENG. FOR THE PRE ENG. BUILIDNG. KMM
|
Plan routing begun/NEW & ADDTN | | | 9/16/1999 | | |
|
|
|
|
Received Certificate of Value | | | 9/16/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/1999 | | FAIL |
|
|
|
PRE ENGINEERED BUILDING PLANS NEED TO BE STAMPED AND SIGNED.
CALCS. ARE REQUIRED. REQUIRE THREE ADDITIONAL CIVIL DRAWINGS. CONTACTED RICK SHRUM AND STAN COLE OF THESE NEEDS. KMM
10/12/99 RECEIVED ABOVE ITEMS. KMM
10-12-99 RECEIVED TWO COPIES OF STAMPED AND SIGNED PRE-ENG. BUILDING PLANS. CONTACTED JEFF ULHORN TO LET HIM KNOW THAT I NEED ONE ADDITIONAL SET. HE ALSO STATED THAT THEY ARE AFTER A FOUNDATION PERMIT. I REQUESTED A LETTER TO TIM HOGLAND AND AN ADDITIONAL FOUNDATION COPY OF PLANS TO KEEP ON SITE. KMM
|
Application received | | | 9/13/1999 | | |
|
|
|
|
Pending Assignment by MYS | 9/13/1999 | | | | |
Marlene Southard
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Telephone call | | | | | FAIL |
|
|
|
CONTACTED STAN COLE 10/15/1999 CONCERNING TYPE OF HANGER ADDRESSED IN NFPA 409 AND SPECIAL REQUIRMENTS. INDICATED HE WOULD GET BACK WITH ADDRESSED ISSUES.
|
Case Summary (BLD) | | | | | |
|
|
|
|