Plan resubmittals received | | | 7/10/2002 | | DONE |
|
|
|
|
Fee Review-notes | 3/30/2000 | 3/30/2000 | 10/24/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 10/9/2000 | | DONE |
|
|
|
Letter of Compliance #19945 issued.
|
FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 07:41:06. Contact: ###-####.
|
BLD-Final | 9/20/2000 | 9/21/2000 | 9/21/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 07:41:40. Contact: ###-####.
|
FIRE-Final Inspection | 8/23/2000 | 8/28/2000 | 8/28/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 07:42:13. Contact: ###-####.
|
Print Occupancy Form | | | 7/28/2000 | | DONE |
|
|
|
|
BLD-Conference | 7/11/2000 | 7/12/2000 | 7/12/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 12:11:39. Contact: ###-####.10 00 am appt. w/wyane. 7/11/00 12:44:41 PM
|
BLD-Conference | 7/11/2000 | 7/12/2000 | 7/12/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 12:11:39. Contact: ###-####.10 00 am appt. w/wyane. 7/11/00 12:44:41 PM
|
BLD-Wall cover | 6/16/2000 | 6/16/2000 | 6/16/2000 | P | PART |
Jim Storey
|
|
|
###-#### stair and restaroom area south first floor ok. 6/19/00 12:26:11 PM
|
FIRE-Final Inspection | 6/6/2000 | 6/6/2000 | 6/7/2000 | P | FAIL |
Rick Jackson
|
|
|
wayne ###-#### Corridor door and smoke detectors....
|
BLD-Final | 6/5/2000 | 6/6/2000 | 6/6/2000 | P | PART |
Jim Storey
|
|
|
###-#### Wayne temp occ. ok for coridor 100 only copey of all sign offs with occ. card on file in bld.25. 6/8/00 10:03:07 AM
|
BLD-Framing/Rough-in | 6/1/2000 | 6/1/2000 | 6/1/2000 | P | FAIL |
Jim Storey
|
|
|
|
Plan resubmittals received | | | 5/24/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HDR VIA MICRON , TWO SETS OF SHEETS A2.1.1, A2.1.4, A2.14A AND A3.0. FORWARDED SAME TO JIM STOREY. 5/23/00
|
BLD-Framing/Rough-in | 4/25/2000 | 4/26/2000 | 4/26/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/25/2000 at 14:11:11. Contact: ###-####. southstair framing ok need resubmital for as built at this location. 4/26/00 11:57:57 AM
|
FIRE-Conference | 4/14/2000 | 4/17/2000 | 4/17/2000 | A | PART |
Rick Jackson
|
|
|
###-#### Sprinkler requirements for AHU room 4/17/00 1:48:06 PM
|
(F) Reprint permit | | | 4/13/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/13/2000 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/13/2000 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 3/22/2000 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/17/2000 | 3/17/2000 | 3/17/2000 | A | PART |
Jim Storey
|
|
|
Rated wall const. at center 2nd floor TAL ok.
|
Print Occupancy Form | | | 3/17/2000 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 2/18/2000 | 2/22/2000 | 2/22/2000 | A | PASS |
Jim Storey
|
|
|
wayne ###-#### fr Clean Rm. skin sheet metal ok for cover on walls. 2/28/00 2:02:15 PM
|
Plan resubmittals received | | | 1/31/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HDR ENGINEERINGSHEET A2.10 SUB FLOOR PLAN. 1/31/00 DAR
|
BLD-Framing/Rough-in | 1/19/2000 | 1/20/2000 | 1/20/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/19/2000 at 11:17:22. Contact: ###-####. Conf. on 2hr area at service trench wall grid North/South. 1/20/00 4:16:29 PM
|
Plan Reviewer's activity | | | 1/12/2000 | | PASS |
|
|
|
REVIEWED REVISED STRUCTURAL PLANS TO INCLUDE USE OF METAL PAN DECK AT THE SECOND FLOOR LEVEL. AT JIM STOREY'S REQUEST, I E-MAILED DAVE WHITE REQUESTING THAT SOMEONE COME IN TO PICK UP THE APPROVED PLANS. I ALSO GAVE THE REVISE PLAN SHEETS AND CALCULATIONS TO ARCHIVES TO BE IMAGED.
|
Plan resubmittals received | | | 1/4/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CH2M HILL, KENT SOELBERG, FORWARDED SAME TO JOHN MENARD. SHEETS SO.2,S2.1.2, S4.2,S5.1,S5.3,S5.4, S5.3 AND CACULATIONS. 1/5/99 DAR
|
Received partial PAYMENT | | | 12/15/1999 | | DONE |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 12/15/1999 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/5/1999 | 10/5/1999 | 12/8/1999 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 9/17/1999 | 9/17/1999 | 12/8/1999 | | PASS |
John Menard
|
|
|
12/8/1999 14:29:33 JCM - activity updated through activity BLDA022 from case BLD99-02762.
|
Routing Off Site - STRUCTURAL | 12/6/1999 | | 12/8/1999 | | PASS |
|
|
|
RECEIVED REVIEW RESPONSE BACK FROM OUTSIDE ENG. ROUTED TO JOHN M. KMM 12-9-99 RECEIVED PLANS BACK FROM OUTSIDE ENG. ROUTED TO JOHN M. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 12/8/1999 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/3/1999 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS SO.2, S2.0.1, S2.1.1, S2.1.2, S2.1.3, S2.1.4, S3.1, S3.2, S4.1, S4.2, S5.1, S5.2, S5.3, S5.4 AND THREE COPIES OF CALCULATIONS. ROUTED TO JOHN M. KMM
|
Plan resubmittals received | | | 11/22/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HDR VIA MESSENGER, FORWARDED SAME TO JOHN MENARD. 11/22/99 DAR
|
Plan resubmittals received | | | 10/28/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A.2.1.4A A3.0 AND A7.0. ONE COPY OF RESPONSE TO PRELIMINARY PLAN REVIEW. ROUTED TO JOHN M.. KMM
|
Plan resubmittals received | | | 10/27/1999 | | PEND |
|
|
|
Received plan resubmittals from HDR engineering, forwarded same to John Menard. 10/17/99 dar
|
Routing Off Site - STRUCTURAL | 9/17/1999 | 9/17/1999 | 10/6/1999 | | FAIL |
|
|
|
MARA PICKED UP ISSUE COPY TO MAKE A COPY OF PLANS FOR OUTSIDE ENG. WHEN SHE RETURNS I WILL SEND COPY TO OUTSIDE ENG. AND RETURN ISSUE COPY TO PW FOR THEM TO SIGN OFF. KMM
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan resubmittals requested | | | 10/6/1999 | | PEND |
|
|
|
FAXED MARA FOLEY AT HDR A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing - FIRE | 10/1/1999 | 10/4/1999 | 10/4/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/4/1999 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/17/1999 | 9/17/1999 | 10/1/1999 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 10/1/1999 | | PEND |
|
|
|
E-MAILED DAVE WHITE AND MAILED HDR A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Received Certificate of Value | | | 9/17/1999 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/17/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/15/1999 | 9/15/1999 | 9/17/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/17/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETA3.0. MARA PUT ONE COPY IN WITH OUTSIDE ENG. SET BEFOR I SENT THAN SET OUT. KMM
|
Plan routing begun/NEW & ADDTN | | | 9/15/1999 | | |
|
|
|
|
Application received | | | 9/14/1999 | | |
|
|
|
|