Fee Review-notes | 6/17/2003 | 6/17/2003 | 6/17/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/28/1999 | 12/28/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/28/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8063 issued 12-28-99 to Oreck Vacuum in the TJ Maxx Plaza.
|
BLD-Final | 12/17/1999 | 12/20/1999 | 12/20/1999 | A | PASS |
Carl Dependahl
|
|
|
###-#### Card not onsite; C/N ok.
|
BLD-Final | 12/14/1999 | 12/15/1999 | 12/15/1999 | A | FAIL |
Carl Dependahl
|
|
|
###-#### Need to complete framing corrections, ok for T/O (brace part. Wall, spreader bars).
|
FIRE-Final Inspection | 12/13/1999 | 12/13/1999 | 12/13/1999 | | PASS |
|
|
|
|
FIRE-Final Inspection | 12/13/1999 | 12/13/1999 | 12/13/1999 | P | PASS |
Joe Tawney
|
|
|
DON ###-#### Reinsp. Ok for permanent occupancy.
|
FIRE-Final Inspection | 12/10/1999 | 12/10/1999 | 12/10/1999 | P | FAIL |
Joe Tawney
|
|
|
richard-- cell ###-#### fire fn Final fail c/N issued.
|
BLD-Final | 12/9/1999 | 12/9/1999 | 12/9/1999 | P | FAIL |
Carl Dependahl
|
|
|
ceiling and a final todd ###-#### Need all other insp. 1st.
|
BLD-Framing/Rough-in | 11/16/1999 | 11/16/1999 | 11/16/1999 | P | PART |
Carl Dependahl
|
|
|
DON-- ###-#### FR INSP Walls ok; check bracing w/grid Clg.
|
Issue PAID IN FULL permit | | | 11/4/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/3/1999 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 9/24/1999 | | 10/12/1999 | | PASS |
|
|
|
10/12/1999 06:54:00 RMH - activity updated through activity BLDA022 from case BLD99-02773.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/1999 | | RMH |
Ron Hill
|
|
|
|
Inspection Record Card- Bld | | | 10/12/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/12/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/12/1999 | | DONE |
|
|
|
pattrick ###-#### left message with Trent
|
Plan resubmittals received | | | 10/11/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PAT MCKEEGAN ARCHITECTS, FORWARDED SAME TO RON HILL. 10/8/99 DAR
|
Routing - FIRE | 10/5/1999 | 10/7/1999 | 10/7/1999 | | PASS |
|
|
|
Review notes returned 10/07/99./jwa PLANS FORWARDED TO FLOYD. FED EXED OFFICE COPY TO FLOYD, AND ROUTED ISSUE COPY TO BILL A. 10/5/99 DAR
|
Plan Review Completed(1st rev) | | | 10/7/1999 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 10/5/1999 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to the architect. Will route to fire department.
|
Routing - PLAN CHECK | 9/24/1999 | | 10/5/1999 | | FAIL |
Ron Hill
|
|
|
route to fire department
|
Pending Assignment by MYS | 9/15/1999 | | 9/24/1999 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 9/24/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Routing - PUBLIC WORKS | 9/17/1999 | 9/17/1999 | 9/20/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 9/17/1999 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/17/1999 | | DONE |
|
|
|
|
Fee Review-notes | 9/15/1999 | 9/15/1999 | 9/15/1999 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/15/1999 | | DONE |
|
|
|
|
Application received | | | 9/15/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 10/11/1999 | 10/11/1999 | | | |
|
|
|
|